Title: Consultant Inspection Training


1
Consultant Inspection Training
2
Introduction Welcome
  • Importance Of Compliance
  • Goals And Objectives
  • ACEC PennDOT Team
  • Scope Of Training

3
Importance Of Contract Compliance
  • Media Issue
  • Comptroller Audit
  • PennDOT Reviews
  • Not quality of work issue
  • Contract compliance

4
Goals And Objectives
  • Consultants Department to Comply With Contract
    Provisions
  • Process Actions In A Timely Manner Before Work
    Occurs
  • Have All Actions Documented For Accountability

5
ACEC/PA PennDOT Team
  • Consultant Representatives Across The State
  • Bureau Of Construction Materials
    Representatives
  • Bureau Of Design Representatives

6
Scope Of Training
  • Revised Policies Pub 93
  • Process Control
  • Consultants How To ECMS-II
  • PennDOT How To ECMS-II
  • Questions

7
Revised Policies Pub 93
  • Classifications And Experience
  • Substitutions
  • Time Frames
  • Assignments In Writing

8
Classifications And Experience
  • Uniform Resume Requirements
  • Identification Of Work Experience With Time
    Frames
  • Pay Grade Level
  • Evaluation Method
  • New Resume Templates
  • Resume Submissions In ECMS

9
Substitutions
  • Reason For Change In Resume
  • Document Person Is Equal Or Better
  • Equal Or Higher Pay Grade
  • Total Experience
  • Experience On That Type Of Work

10
Substitutions
  • Substitutions Can Only Be Made After Exhausting
    Everyone In The SOI At That Classification
    Skills including alternates
  • Information to be in Resume
  • Waiver For Providing Equal Substitute To Be
    Submitted To Contract Management Division
    Bureau Of Construction

11
Time Frames
  • Wage Rate Request To Be Approved Within 5 Working
    Days Through ECMS.
  • Absolutely No Work Without ECMS Wage Rate
    Approval Even At No Cost
  • Substitutions With Resume And Wage Rate Approvals
    Prior To Any Work

12
Assignments In Writing
  • All Assignments Requests In Writing to Consultant
    - Email Or Fax
  • The Department Requests Classifications (TCI,
    TCIS, TCM,TA) And Experience (Asphalt Paving, CDS
    Operator, Etc). 
  • Individuals Pay grade Will Be Determined By The
    Consultant. 

13
Assignments In Writing
  • The District May Not Request People By Name Or
    Pay Level (TCI2).
  • The Prime Consultant Is Solely Responsible For
    Adding Or Removing Subconsultants To Meet
    Contractual Obligations.

14
Process Control
  • Process Control Parameters
  • Contractual Violations
  • Subconsultants
  • Administrative Deficiencies
  • Appeals

15
Contractual Violations
  • Major Violations Fraud - Intentional
    Modification Of Data / Information Without
    Supportive Justification Intended To Deceive The
    Recipient.
  • Sanction Any Violation Calls For Immediate
    Debarment Procedures.

16
Intermediate Violations
  • 1. Inspector Working Without A PennDOT Executed
    Wage Rate Approval Letter.
  • 2. Inspector Working In A Classification For
    Which They Do Not Qualify.
  • Inspectors Resume Has To Support The Check Box
    In The Construction Inspection Qualification

17
Intermediate Violations Sanctions
  • 1st Violation Within 2 Years - Written
    Notification And Submission Of A Corrective
    Action Plan Within 30 Days.

18
Intermediate Violations Sanctions
  • 2nd Violation Within 2 Years - Written
    Notification And A Warning Of Three-month
    Preclusion From Submitting A Statement Of
    Interest As A Prime Or Subconsultant On Any
    PennDOT Construction Inspection Project

19
Intermediate Violations Sanctions
  • 3rd Violation Within 2 Years 3 Month
    Preclusion From Submitting A Statement Of
    Interest As A Prime Or Subconsultant On Any
    PennDOT Construction Inspection Project.

20
Intermediate Violations Sanctions
  • 4th Violation Within 2 Years 12 Month
    Preclusion From Submitting A Statement Of
    Interest As A Prime Or Subconsultant On Any
    PennDOT Construction Inspection Project.

21
Minor Violations
  • 1.Substitution Made With Less Qualified
    Personnel. Substitutions Needs To Be Equal To Or
    Better Than The Resume(s) Submitted In The
    Statement Of Interest. Consultant Firm Needs To
    Be Prepared To Stand Behind The Skill Set Of The
    Substitute.

22
Minor Violations
  • 2.Failure Of Inspector To Maintain Required
    Registrations/Certifications
  • If Certification Lapses, The Consultant Must
    Submit A Revised (Downgraded) Wage Rate Request.
    It Is An Intermediate Violation For Working In
    Classification Not Qualified.

23
Minor Violation Sanctions
  • 1st Violation Within 1 Year Period Is A Written
    Notification Of Violation.
  • 2nd Violation Within 1 Year Period Is A Written
    Notification And Required Submission Of A
    Corrective Action Plan Within 30 Days.

24
Minor Violation Sanctions
  • 3rd Violation Within 1 Year Period Is A Written
    Notification And A Warning Of Three-month
    Preclusion From Submitting A Statement Of
    Interest On Any PennDOT Construction Inspection
    Project

25
Minor Violation Sanctions
  • 4th Subsequent Violations Within 1 Year Period
    Is Three-month Preclusion From Submitting A
    Statement Of Interest On Any PennDOT Construction
    Inspection Project

26
Process ControlSubconsultants
  • The Prime Consultant Has The Responsibility To
    Manage The Subconsultant And Conduct A Cursory
    Review Of The Subconsultant Employees Resumes.

27
Subconsultants
  • In The Event Of An Violation, Where The Violation
    Constitutes An Error On Its Face Or
    Subconsultants Inspector Is Working Without A
    Wage Rate Approval, Both The Prime And
    Subconsultant Are Subject To The Full Sanction.

28
Subconsultants
  • If An Intermediate Or Minor Violation Occurs With
    A Subconsultant That Is Not Evident Through A
    Cursory Review, Including Expiration Of
    Certifications, The Sanctions Will Be Levied To
    The Subconsultant And 25 Percent Rate To The
    Prime Consultant.

29
Administrative Deficiencies
  • Resume Submitted With Incomplete Data (Invalid)
    Inspector Resumes Must Clearly Delineate, By
    Month And Year, And Specific Work Activity, The
    Skill set Of The Inspector
  • Wage Rates Proposed Outside The Approved Range
    For The Classification

30
Administrative Deficiencies Substitutes
  • Justification For Substitutions Not Provided.
    The Consultant Must Clearly Describe The Reason
    For The Substitution Request And Must Demonstrate
    That The Substitute Is Equivalent Or Better Based
    On
  • Equal Or Higher Pay Grade Or
  • Total Experience Or
  • Experience On That Type Of Work

31
Administrative Deficiencies Substitutes
  • On All Open End Agreements, Or Other Agreements
    Where Notice To Proceed Occurs More Than 2 Weeks
    After The Anticipated Published NTP Date, The
    Consultant Is Entitled To Request Relief
    Regarding Proposed Substitutions.

32
Administrative Deficiencies Substitutes
  • If The Consultant Cannot provide an equal
    substitute, they must Contact Chief Of Contract
    Management Division, BOCM And Request Relief In
    Writing.

33
Administrative Deficiencies Sanctions
  • 1st Violation Within 1 Year Period Is A Written
    Notification Of Violation.
  • 2nd Violation Within 1 Year Period Is A Written
    Notification Of 2nd Violation And Required
    Submission Of A Corrective Action Plan Within 30
    Days.

34
Administrative Deficiencies Sanctions
  • 3rd And Subsequent Violations The Number And
    Severity Of Administrative Deficiencies Will Be
    Considered When The Department Completes The
    Consultant Performance Report.

35
Notification
  • All Violations identified in the Districts are to
    be forwarded to Consultant Agreement Section
    Bureau of Design

36
Appeal Process
  • Upon Notification Of A Violation By The
    Department, (Intermediate Violation, Minor
    Violation Or Administrative Deficiency) The
    Consultant Firm May Request An Administrative
    Review Of The Particular Circumstances Of The
    Violation
  • Consultant Not Satisfied May Request A Formal
    Hearing.

37
Stay In Time Frame
  • There Will Be A Stay In The Timeline During
    Administrative Review Or Formal Hearing Until The
    Review Process Is Completed

38
Consultants How To ECMS-II
  • New Resume TemplateSOI And ResumeAdding
    ResumesSubmitting Wage Rate RequestsMaking
    AssignmentsSubmitting SubstitutionsManaging
    Subconsultants

39
Current ECMS
40
Prime consultants add resumes here Substitute
Resumes will also be added here
41
New ECMS
42
New Statement of Interest Screen
43
Consultant Information Portal Page
Ability to perform Quick jump to info if you
know the ID/Number
User specific, saved searches to quickly execute
your favorite search.
Link to more customizable searching
Entry points for typical operations, usually
based on who you are.
System defined searches and links
Other Information and links as needed
44
New Excel Spreadsheet with Drop Down Boxes to Aid
Completion
45
Additional Drop Down Boxes
46
Work History and Other Experience
47
Word Version
48
Bottom Section of Word Version
49
Page 2 for Word Version for Work History and
Experience
50
Current ECMS Roster Maintenance from Consultant
view
51
Click on add employee button to access and
complete information
Be sure to add Agreement number
52
Current View for Approval by Negotiation Engineer
53
New ECMS Consultant View to Add New Employee
Click Create Employee
54
Consultant Enters Required Information and Saves
55
Additional Information Required
Click New
56
Enter information, Click Save and under Workflow
Click Submit
57
PennDOT How To ECMS-II
  • Scope of work developmentChanges in
    SOWReviewing resumesReviewing and approving
    wage ratesRejecting resumes and wage rate
    requestsRequesting staffing

58
Resume Approvals
59
To Review Resumes within the Statements of
Interest
  • Once in ECMS
  • Click on Consultant Services
  • Agreement Headers
  • Header
  • On drop down list go to Statements of Interest
  • Click on the Prime Consultant you want to view

60
In the future, the Department is looking to move
the wage rate approval process for consultant
construction inspection agreements from the
consultant agreement section within PennDOT to
the District level
  • This would allow the Districts to verify resumes
    against requested wage rates
  • This would eliminate paperwork for both the
    consultants and the Department
  • All approvals would be input and approved in ECMS

61
New ECMS Screen for PennDOT Approval
Click Here
62
Can Filter Business Partners or View All
63
District Will Approve or Reject
64
Accountability Compliance
  • Consultant Concerns
  • Sanction Issues Are Strict
  • Availability Of Personnel In Summer Is Limited
  • Resumes Need To Be Correct And Complete

65
Accountability Compliance
  • PennDOT Concerns
  • 5 Days For Approvals
  • Cannot Name People
  • Limited On Controlling Cost TCI1 vs TCI3
  • No Work Without Wage Rate Approval
  • Assignments Email Or Fax Not Verbal

66
Effective Date
  • January 1, 2008 New Process In Effect

67
Questions
  • FAQs
  • Frequently Asked Questions
  • On ECMS Under Consultant Inspection