Traffic Management for Resurfacing in the Wanganui Region - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

Traffic Management for Resurfacing in the Wanganui Region

Description:

Industry discussion why? Speeding traffic was one of the primary causes ... Use of road cones to ensure whole of new surface is uniformly compacted ... – PowerPoint PPT presentation

Number of Views:45
Avg rating:3.0/5.0
Slides: 25
Provided by: joanna71
Category:

less

Transcript and Presenter's Notes

Title: Traffic Management for Resurfacing in the Wanganui Region


1
Traffic Management for Resurfacing in the
Wanganui Region
Joanna Towler, NZTA National Office Ross McCoy,
NZTA Wanganui Office 1 - 3 November 2009 NZ
Transport Agency NZIHT 10th Annual
Conference
2
Key Message
  • Chipsealing Needs Positive Traffic Management

3
Embedment of Sealing Chips
4
(No Transcript)
5
Scabbing Stripping
6
The Wanganui Story
  • Unacceptable amounts of stripping
  • Industry discussion why?
  • Speeding traffic was one of the primary causes
  • Also uneven compaction across the road

7
Wanganuis Approach
  • From industry meeting agreement there needed to
    be an improvement in Traffic Control after
    chipsealing
  • More emphasis needed on Positive Traffic
    Management (COPTTM C10)
  • Active Temporary Traffic Control
  • Passive Temporary Traffic Control

8
Wanganui Trial Results
  • First trial in 2000
  • Dramatic results
  • Scabbing reduced from 240 m/km to 85 m/km
  • 65 reduction in scabbing

9
West Wanganui Visual Condition Rating
10
Wanganui Trial Results - Analysis
  • West Wanganui resurfaces about 90 km (11 of the
    network) per annum
  • Reduction in scabbing by 175 m/km over 120 to 140
    sites saves
  • 60,000 to 70,000 in rework costs (to the
    contractor)
  • 90,000 to 100,000 to the client (as contractor
    would have allowed for rework costs in tender
    price).

11
Wanganui Traffic Control Clauses Original
  • Original Clause (2001 2008)
  • Traffic Control Layout COPTTM figures E2.6 and
    E2.7 (Two-way Two- lane Level 1 road, one lane
    closure)
  • Minimum 48 hours
  • Minimum of two workers on site
  • Use coned lanes to move the traffic over the full
    width of the carriageway at a reduced speed

12
(No Transcript)
13
Wanganui Traffic Control Clauses New
  • New Clause (2009/10)
  • 48 hours, may reduce to 36 hours for
  • Single coat grade 5 or 6, or,
  • Traffic count lt 2000 VPD
  • Contractor may nominate alternative seal types
  • Continuous management of each site
  • Use of road cones to ensure whole of new surface
    is uniformly compacted

14
(No Transcript)
15
(No Transcript)
16
West Wanganui Visual Condition Rating
17
Increased Chipseal Life in Wanganui
18
National State Highway Chipseal Lifetimes
19
Average Chipseal Lifetimes
20
Average Chipseal Lifetimes Wanganui SH
21
Chipsealing Industry Working Group Agrees
  • Best Practice Chipsealing involves Positive
    Traffic Control

22
Implementation Nation-Wide
  • Choice of
  • Engineer specifies Positive Traffic Control for
    high stress and high profile sites, or,
  • This is best practice and everyone should be
    doing it.

23
Conclusion
  • Best Practice Chipsealing involves Positive
    Traffic Control
  • And everyone should be doing it

24