Flexible Containment Concepts in Real Application - PowerPoint PPT Presentation

1 / 34
About This Presentation
Title:

Flexible Containment Concepts in Real Application

Description:

OC Technical Guidelines - 1994. RBEC Guideline -1998, revised 2001 ... GES, GSS, QA. Major Solid Dosage Sites. Key PSC manufacturing Sites ... – PowerPoint PPT presentation

Number of Views:117
Avg rating:3.0/5.0
Slides: 35
Provided by: gcsgra
Category:

less

Transcript and Presenter's Notes

Title: Flexible Containment Concepts in Real Application


1
Flexible Containment Concepts in Real Application
  • Jon Gast
  • Steven Meszaros
  • PSG 2009

2
PSC Guideline Presentation Overview
  • RBEC History
  • Motivation
  • Scope
  • Strategy
  • Expectations
  • Gap Analysis RBEC Checklists
  • Fixed Containment
  • Flexible Containment Solutions

3
PSC Guideline History
  • OC Technical Guidelines - 1994
  • RBEC Guideline -1998, revised 2001
  • RBEC Interpretation Guideline - 2002
  • PSC Task Force 2003
  • PSC Guideline 2004 EHS Policy 404
  • IH Policy 401
  • Containment Technology Matrix (CTM) 2009

4
PSC Guideline Motivation
  • Regulatory Requirements
  • API Product Cross Contamination
  • Worker Health Safety
  • Environmental Air, Water Waste - PNAEELs
  • Third Party Contractual Obligations Liability
  • cGMP Harmonization - CS 14-8-4
  • OHC, OEGs and RBEC levels
  • Aligned with RD TOPS Decision Gates

5
Historical PSC Risk Control Issues
  • Pre-RBEC Facility Designs Equipment
  • Historical levels gt 1,000 X OEG
  • Cross Contamination Potential
  • Pharmaceuticals In the Environment

6
Real Risks
7
PSC Guideline Scope
  • RD API Manufacturing Handling
  • Pharmaceutical Manufacturing
  • BioPharmaceutical Manufacturing
  • New Products Facilities and Areas
  • Renovated Facilities and Areas
  • Third Party Manufacturing
  • Requires project-specific RBEC Criteria
    interpretation - -The key is to design is to meet
    our OEG !

8
Rollout Strategy
  • Endorsement from TOPS
  • and RD senior management
  • Stakeholder meetings planned for
  • TOPS, RDCPD/PDC
  • GES, GSS, QA
  • Major Solid Dosage Sites
  • Key PSC manufacturing Sites

9
PSC Guideline New Expectations
  • Responsibilities Defined
  • Timelines for Conformance Specified
  • cGMP Cross Contamination Harmonization of
    Engineering EHS approaches
  • GAP Analysis
  • Short Term, Long Term Actions
  • Conformance Action Plans Site Master Plans

10
RBEC Risk Based Exposure Control
  • 4-Tier Banding System
  • Aligned to OEG
  • Conforms to Pharmaceutical Industry
  • Hierarchy of Controls
  • Engineering Project Guidance
  • RBEC Criteria Tables
  • Containment Technology Matrix

11
PSC RBEC Criteria Table Gap Checklist
  • Facility Design for Containment
  • Room Work Surfaces
  • HVAC Systems
  • Local Exhaust Ventilation
  • Process Equipment
  • Unit Operations milling, blending, sieving, etc.
  • Product Transfers
  • Maintenance Cleaning
  • Medical Surveillance
  • Work Methods SOPs
  • PPE Respirators
  • Waste Containment Disposal
  • cGMP Regulatory conformance

12
PSC GAP Assessment
  • Facility Team EHS, Engineering, management, and
    Quality Assurance.
  • RBEC Gap Checklist - For each API by area,
    process or unit operations.

RBEC 3 Gap Checklist
 
13
API Dispensing Containment
14
New Technologies Bin Blending
15
Surrogate Testing Protocol Containment Technology
Matrix
  • Real conditions
  • Assume sub-optimal technique
  • Worst case operator shift

16
PDC CONTAINMENT PROJECT AN OVERVIEW
17
Facility Airlocks Added
18
Facility Expansion of Process Areas
19
Flexible Containment Systems Summary
20
Flexible Containment Concept Designs
Note Glove-ports in not shown in all concept
sketches. Blender and Mi-Pro SMI system not
shown
21
Transfer Systems
  • All the isolator systems provided with a Bag
    in/out canister to allow contained transfer in
    and out of materials. The canister is 11.73
    internal diameter.
  • This canister also serves a duel purpose of
    allowing connection of the In-Process Isolator to
    them. Canisters are mounted at standard height to
    allow easy connection.
  • The only isolators that the In-Process isolator
    can not connect to directly are the Extruder and
    Spheronizer systems (due to height issues.). A
    connection can be made using a length continuous
    liner if it is required.

22
In-Process Isolator
The In-Process Isolator is a general purpose
piece of equipment designed to allow any number
of tasks to be carried out. It can be used
independently or connected to other flexible
isolator systems as shown.
23
Typical Process Flow
24
Typical Process Flow
25
Typical Process Flow
26
Extruder Spheronizer Design Progress
Flange Mock Up
Flanges Installed
Finalized 3D Design Drawing
Enclosure Installed December2008
27
Glatt GPCG1 Design Progress
Ergonomic Flange Mock Up
Finalized 3D Design Drawing
Enclosure Installed December 2008
28
Korsch Design Progress
Finalized 3D Design Drawing
Enclosure Installed December 2008
29
Procept SMI Press
SMI Press Flange Installed
Enclosure Installed December 2008
Procept Final Design

30
Strea Design Progress
Finalized 3D Design Drawing for Flange
Enclosure Installed December 2008
31
Roller Compactor Design Progress
Finalized Design Concept Final Assembly Shipped
to Newbridge December 2008
Gerteis Mini-Pactor
32
Bohle BTS-100 Cone Mill
Finalized 3D Design Drawing
Enclosure Installed December 2008
33
Collette UltimaGral 10 25 Liter
Finalized 3D Design Drawing
Enclosure Installed December 2008
34
Installation Training
Training Carried Out January 2009
Write a Comment
User Comments (0)
About PowerShow.com