Title: CEVP Cost Estimate Validation Process TEA Conference 2004
1CEVP Cost Estimate Validation ProcessTEA
Conference 2004
- Jay Drye, P.E.
- Assistant State Design Engineer
- Monica Bielenberg, P.E.
- CREM Program Manager
2Why an Estimate is Not a Number
- Estimates are uncertain . . .
- Ultimate project cost and schedule cannot be
known with certainty during estimating and design
- Project cost and schedule are functions of many
variables - scope and strategy
- other policy
- technical (e.g., associated unit costs and
quantities) - They are essentially a snapshot in time
- . . . Therefore single number estimates are
dangerous - Number hits the street before estimate is
complete or more often does not include all of
the uncertainty inherent to a project
3Estimate Refinement
Cost or Schedule
estimate
1
3
10
20
30
Design Level
4Uncertainty in Traditional Estimating
5Traditional Estimating
Risk Assessment
Geotech
20
40
Enviro
ROW
Risk or Opportunity
30
Contingency
10
Unknown
- All known and unknown risks are equally weighted
- Expresses very little knowledge of project risks
- Ability to weight known risks according to
potential impact to project cost and schedule - Better defines those risks we can identify and
refine the amount of unknown risks
6Poor assessments of uncertainty lead to poor
estimates . . .
- Impacts of poor cost and schedule estimates
include - Cost and schedule over-runs or under-runs
- Reduction in scope
- Resource competition
- Media attention / negative publicity
- Public mistrust
7Impacts of Uncertainties WSDOT
- We have a strong estimating track record
- Construction generally completed within 10 of
Engineers Estimate - Cost of change orders during construction 6-7 of
bid price - Overall programs delivered within 3-5 of total
budgeted biennial program
However . . . we have our share of black-eyes
too SR 167 1990 150 million 2000
972 million
8A New Tool Emerged CEVP
- Evaluate estimate
- Break down known items, uncertain or risky
items (contingencies, allowances, etc) - Build back up
- Better defined, more accurate numbers
- Include uncertain risk/opportunity events
- Run simulation model
- Integrated cost and schedule model
- Express costs and durations to complete the
project in terms of ranges (distributions) - Prioritize critical risk and opportunity factors
to enable more-effective project management
9CEVP Participants and Process Steps
Review Project Scope and Strategy (Flow Chart and
Assumptions)
- Workshops, interviews
- preparatory
- base/risk assessment (1 or 2)
- risk management / updates
- Participants
- project team
- review team
- facilitator / elicitor
- base assessments
- risk assessments
- technical experts (validate)
- modeler
10CEVP - Base Cost Determination
- Determine the base costs - the most probable
cost that can be expected if the project goes as
planned - Remove all contingency - i.e. provision for
unknowns (representing uncertainty - risk and
opportunity) - Consider at the particular stage of the project
- What are our assumptions? Where do they come
from? How valid are they, how do we know? - What do we know we know? (components, units,
prices) - What do we know but cant quantify? (allowances)
- What do we know we dont know? (uncertainty of
items) - What dont we know that we dont know?
(uncertainty)
11CEVP - Develop Project Flow Chart
- Develop the project schedule (flow chart) of
major activities required to complete the project
12Identify Risk Opportunity Events(Assess Impact
Probability)
13Risk Event - Detail
14Evaluate Uncertainty
15CEVP Results
- Combine base costs, risk and opportunity events,
with probabilities, to create potential ranges of
cost schedule
16Schedule comparison after Risk Management was
initiated
17What does it take to do CEVP?
- A knowledgeable/committed owner (who wants to
know the potential cost) - A well-shaped project estimate
- Available/involved project team members
- Sufficient independent subject matter experts
- Skilled risk and cost elicitors (debiasing)
- Risk modeling - technology and experience
- Time / available funding
18(No Transcript)
19CEVP produced very useful results
transportation department effort to plan more
accurately and manage money more effectivelySo
give DOT some credit for those intimidating
estimates. They should show us that its way
past time to pass a funding package and get to
work. Delay will only increase the
cost. Spokesman-Review June 2002
The Transportation Department developed its new
numbers through a new process called cost
estimate validation or CEVP, which features
another layer of review by outside expertsThe
agencys Urban Corridors Administrator
characterized it as an effort to deal more openly
and honestly with risks and uncertainties.
Seattle Times, June 2002 Giving citizens a
range of costs, including full disclosure of the
variables, is not only politically smart, but
its common sense Seattle Post-Intelligencer,
June 2002
20CEVP
- CEVP has been registered by WSDOT to recognize
their sponsorship of its development and to
ensure that the term is not loosely applied in
other settings to cost review procedures that
contain less than all the tools and controls that
have been incorporated into the process, as used
at WSDOT.