Title: EQUITY PARTICIPATION AND RISK SHARING ALASKA GAS PROJECT
1EQUITY PARTICIPATION AND RISK SHARING ALASKA GAS
PROJECT
October 13, 2004 Pedro van Meurs Presentation
to the Legislative Budget and Audit
Committee Senate Resources Committee
2EQUITY PARTICIPATION AND RISK SHARING BY THE
STATE OF ALASKA
- This presentation will deal with the following
issues related to State equity participation - The risk-reward balance
- The international experience
- The issue of risk on pipeline project
- The unique position of Alaska
-
3RISK REWARD BALANCE
- The more risk investors have to accept the more
profits they want. - The more risk a government is prepared to accept
the higher the government revenues.
4RISK REWARD BALANCE
- Stranded Gas is being developed around the world
by lowering project risk.
5INTERNATIONAL EXPERIENCE
- Many jurisdictions alter the risk-reward balance
in order to achieve policy objectives. This can
be done through - Equity participation, and/or
- Production/Risk sharing agreements
-
6INTERNATIONAL EXPERIENCE
- These methods are used by governments in gas
projects - To create additional revenues for the State
- To make marginal or stranded gas projects more
competitive, in particular with respect to LNG -
- Two concepts are employed
- Joint Ventures
- Production/Risk Sharing Agreements
-
7INTERNATIONAL EXPERIENCE
- Joint Ventures are typically of three different
types - Joint Stock Companies
- Joint Operating Agreements
- LLCs or LPs
-
8INTERNATIONAL EXPERIENCE
- JOINT STOCK COMPANIES
- Parties are shareholders
- Assets owned by the company
- Decisions are made by the Board appointed by the
shareholders - Capital to be contributed is share capital
- Individual shareholders cannot "opt out" of any
of the project of the company - Operations are managed by the Managers of the new
joint corporation - Income is distributed as dividends
- the new joint venture is a separate taxable entity
9INTERNATIONAL EXPERIENCE
JOINT OPERATING AGREEMENTS
- Parties remain independent
- Assets owned pro-rata by the working interest
owners - Parties can vote in accordance with their working
interest in the venture - Decision are made by the Operating Committee
- Capital is contributed project by project on the
basis of cash calls - Parties can "opt out" of certain projects they do
not consider attractive, - Operations are managed by one of the Parties
(Operator) - All gross income (less operating costs) is
distributed in accordance with working interest
percentages - each party remains a separate taxable entity.
10INTERNATIONAL EXPERIENCE
LIMITED LIABILITY COMPANIES/LIMITED PARTNERSHIPS
- Parties remain independent members
- Assets owned by the LLC/LP
- Parties can vote in accordance with their
membership interest in the venture - Decision are made by the Management Committee,
often levels of voting - Capital is contributed project by project on the
basis of cash calls - Parties can "opt out" of certain projects they do
not consider attractive, - Operations are managed by a Manager
- All gross income (less operating costs) is
distributed in accordance with working interest
percentages - each party remains a separate taxable entity.
11INTERNATIONAL EXPERIENCEExamples Joint Ventures
- Joint ventures involve the contribution of
equity capital in upstream and/or midstream - The Netherlands
- Venezuela
- Russia
- Brunei
- Oman
- Qatar
12INTERNATIONAL EXPERIENCEExamples Joint Ventures
- Joint ventures involve the contribution of
equity capital in upstream and/or midstream - Norway
- Malaysia
- China
- Colombia
13INTERNATIONAL EXPERIENCEExamples Production
Sharing
- Production sharing involves the taking of a
share of the gas in kind, rather than levying
royalties and tax -
- Trinidad Tobago
- Indonesia
- Malaysia
- China
- Bangladesh
- Egypt
- Yemen
14THE ISSUE OF RISK
- With respect to a pipeline project there are two
important parties - The Shipper of the Gas
- The Pipeline Owner
-
15THE ISSUE OF RISKShipper vs Pipeline Owner
- The most rudimentary project, would be a 14
billion pipeline from Prudhoe Bay/Point Thomson
to the BC/Alberta border. - The tariff could be estimated as 1.20 per MMBtu
(2004 ) (incl. feeder line, GTP and Alberta Hub
entry). - To build the line a pipeline owner would need a
shipping commitment for at least 15 years of
throughput. At 4.1 Bcf/day of sales gas this
would be for 22 Tcf of gas. - In other words a 28 billion contract is
required.
16THE ISSUE OF RISKShipper vs Pipeline Owner
Example
- The main risk is committing to a 28 billion
contract. This is the shippers risk. - On the basis of the guaranteed income of a 28
billion contract, the pipeline owner can invest
the required 14 billion to build the line.
17THE ISSUE OF RISKProducer decision
- The producers can take the decision to either
- Commit 14 billion to the construction of the
pipeline, or - Commit to a 28 billion contract, so pipeline
company can built the line -
18UNIQUE ALASKA ISSUES
- The main risks in the case of the Alaska Gas
Project are - The huge size of the project
- Gas Price Risk
- Cost Overrun Risk
- Regulatory Risk
19UNIQUE ALASKA ISSUES Project size
- The gigantic size of the Alaska project compared
to projects in the rest of the world increases
the difficulties in absorbing risk.
20UNIQUE ALASKA ISSUES Project size
- The huge up front capital requirements of the
Alaska Project create a project that has a low
rate of return compared to competing projects
21UNIQUE ALASKA ISSUES Project Size
- The huge size of the project also creates the
opportunity for huge rewards.
22UNIQUE ALASKA ISSUES Price Risk and Cost Overrun
Risk
- However, ..significant price uncertainty and
cost overrun risk create a huge down side risk.
23UNIQUE ALASKA ISSUES
- In summary the Alaska Project has unique
challenges - An extra-ordinary large project, with
- A low rate of return, and
- Huge downside risks, in
- The most complex regulatory environment in the
world - But potentially also a huge reward for Alaska
and Producers under upside conditions. - To get this project going requires unique
solutions.
24RISK REWARD BALANCE
- The low profitability of the project makes it
imperative to lower risk otherwise the project
will not go forward.
25NEW IDEAS Risk Reduction
- On April 7, 2004, I already presented to the
Joint Caucus the overall strategy as follows - A Stranded Gas Agreement with improved
competitiveness and fiscal stability - A Risk Sharing Package between the State and the
Producers, and - The need for a Federal Energy Bill.
26NEW IDEAS Risk Reduction
- The Federal Energy Bill is a classic example of
a superb risk reduction package, which contains - Enabling provisions to significantly reduce
regulatory risk - Federal Loan Guarantees to reduce financing risk
and - Attractive tax provisions to reduce down side risk
27NEW IDEAS Risk Reduction
- The passing of the Federal Energy Bill is a
gigantic step forward for the Alaska Gas Project.
- The onus is now on Alaska to implement quickly
the next steps.
28NEW IDEAS Risk Reduction
- We are negotiating with various parties, to
bring one or more Stranded Gas Contracts to the
Legislature with competitive fiscal regimes and
appropriate fiscal stability provisions.
29NEW IDEAS Risk Reduction
- The last piece of the puzzle is the Risk Sharing
Package. - We can use ideas that have been employed
elsewhere to make Stranded Gas projects economic,
such as - Equity participation and participation in
shippers risk - Taking Gas in Kind in a manner similar to
production sharing provisions in other countries.
-
30NEW IDEAS Risk Reduction
- A well structured Alaska risk sharing package
will eliminate the need for Federal tax credits
in order to deal with downside risk. It will be
a structure that much better protects the Alaska
interests.