Ring to Main Linac RTML: Status and Plans - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Ring to Main Linac RTML: Status and Plans

Description:

The RTML is almost unchanged from the design described in the BCD ... Attend Sisters of Mercy concert _at_ Warfield in San Francisco. 27 Mar: ... – PowerPoint PPT presentation

Number of Views:60
Avg rating:3.0/5.0
Slides: 17
Provided by: quar3
Category:
Tags: rtml | linac | main | plans | ring | status | warfield

less

Transcript and Presenter's Notes

Title: Ring to Main Linac RTML: Status and Plans


1
Ring to Main Linac (RTML)Status and Plans
  • ILC January Meeting (KEK)
  • Peter Tenenbaum
  • 19-Jan-2006

2
A Few Improvements
  • The RTML is almost unchanged from the design
    described in the BCD
  • There are a few changes which are proposed
  • Move boundary of Damping Ring section to include
    damping ring extraction region (DRX)
  • Proposed boundary is at zero-dispersion point at
    end of DRX
  • Replace multi-wire emittance station in Emit1
    with single wire or other profile device
  • Insert 610 m (approx) transfer line (DRStretch)
    to optimize DR position within site boundary
  • Remove skew correction section from Emit2
  • Extend Linac Launch diagnostic section (not
    quite long enough in BCD)
  • Remove first diagnostic section in main linac
  • Redundant with last diagnostic station in RTML!
  • This talk assumes that these changes will be
    accepted, and describes the changed system

3
RTML Footprint
4
Basis for Estimates of Lengths and Components
  • Bunch compressors lattice files of 3rd
    generation designs from 2005
  • Other systems scaling from TESLA or NLC
    lattices based on changes in beam parameters, if
    any
  • These estimates are necessarily rougher than the
    bunch compressors

5
System Lengths
6
Magnet Counts
7
Instrumentation
8
BC RF Systems
  • BC1 has 3 cryomodules, 1 klystron, plus one spare
    klystron with waveguide switch
  • BC2 has 57 cryomodules, 19 klystrons, of which 1
    klystron 3 cryomodules are spare
  • Gradients modestly lower than 31.5 MV/m needed
  • Stations operate far from RF crest
  • Need to change klystron amplitude and phase
    during train to compensate beam loading
  • Larger average power goes to RF loads than in
    main linac stations
  • Phase and amplitude tolerances are tight
  • Phase jitter lt 0.1 ? 2 loss of integrated
    luminosity from longitudinal jitter of collision
    point
  • Most promising bunch length monitor requires crab
    cavity
  • Based on system prototyped at SPPS and TTF2
  • Might need crab cavities for bunch length
    measurement, depending on downselect of BLM
    technology

9
Bunch Compressor Wiggler
  • Each BC in baseline has 240 meters of bend
    magnets arranged in chicanes to generate
    compression
  • Long!
  • Considering two approaches to reducing length
  • Enhancing R56 by forcing nonzero D at quads
  • Replacing wiggler with 4-bend chicane with
    optimized lattice functions for emittance
    preservation
  • Issue here is control of vertical dispersion and
    emittance growth from pitched cavities
  • Studies ongoing at this time

10
Beam Stops
  • Current design has 3
  • Low power (lt 1 kW) insertable stopper
  • Somewhere in skew correction or collimation
    section need to find the best spot for it
  • Allows single-bunch tuneup of beams extracted
    from DR
  • Full power (220 kW and 660 kW) pulsed dumps after
    BC1 and in Linac Launch
  • Allow bunch length tuneup without sending beam
    into next RF section
  • Also may have machine protection role
  • 3 possible modes of operation
  • Train-by-train, using pulsed bends
  • Intra train, with fast (100 nsec risetime)
    kickers
  • Bunch stealing take 1 bunch out of train for
    diagnostic purposes (open to debate)
  • Are these enough?
  • Or possibly too much?
  • Can we save money in pulsed systems by limiting
    their average power but allowing a large peak
    power?
  • Can take a full train for MPS occasionally, or a
    fraction of a train forever

11
Spin Dynamics
  • Each side has 1 complete spin rotator
  • Implications
  • Cant simultaneously run to 2 IRs with spin
    optimized in both
  • Need 2 spin rotators per side
  • Cant to train-to-train spin-flipping of
    positrons
  • Would need either 2 or 4 spin rotators on
    positron side
  • How important is this?
  • Can we do it upstream of the DR? At 250 MeV?

12
Tunnels etc.
  • Current assumption RTML is laser-straight
  • Main linac is curved
  • Somewhere there must be dispersion matching
    between RTML and ML
  • Two parts of RTML beamline (upstream of
    turnaround and downstream) share tunnel
  • Is that OK? Is it cost-optimal?

13
Collimation
  • Assuming 2 phases x 2 planes x 1 iteration of
    collimation
  • Spoiler survival probably not a problem
  • Large geometric emittances
  • Close to DR can halt extraction quickly
  • Collimated halo points at BC2 and BC1 RF stations
  • Is that OK?
  • Assuming energy collimation in turnaround or
    bunch compressor wigglers

14
Progress since Frascati
  • Work started on shorter BC wigglers and
    turnaround optics
  • Leaders of all Technical and Global systems
    contacted
  • Notified about potentially interesting issues in
    the RTML
  • Dialogue begun What do you need from us, when
    do you need it, and with whom should we be
    corresponding?
  • Most TS and GS have replied already!

15
Upcoming Milestones (Tentative Map)
  • 20 Jan
  • Finalize boundaries and other changes described
    on Slide 2
  • 29 Jan
  • Site layout, RF unit, PPS / MPS issues finalized
  • Impact DR Stretch and other areas
  • 12 Feb
  • Complete optics for turnaround
  • Complete optics for collimation system
  • Complete optics for BC wigglers
  • 26 Feb
  • Complete optics for pulsed dumplines
  • Select BLM technology (or technologies)

16
Milestones (2)
  • 12 Mar
  • Complete all optics
  • Select size monitor technology for Skew section
  • 22 Mar
  • Attend Sisters of Mercy concert _at_ Warfield in San
    Francisco
  • 27 Mar
  • Complete system integration of lattices
    (Woodley-fication)
  • April
  • Review RTML design and place lattices and
    documentation under change control
Write a Comment
User Comments (0)
About PowerShow.com