AMS02 Increased Mass Loads Assessment - PowerPoint PPT Presentation

1 / 10
About This Presentation
Title:

AMS02 Increased Mass Loads Assessment

Description:

Current manifest weight budget for AMS-02 is 14,809 lbs (6717 kg) ... Keel Block and Retainer to Keel Trunnion. 1018. 0.470. 1060. 0.490. Keel Trunnion ... – PowerPoint PPT presentation

Number of Views:40
Avg rating:3.0/5.0
Slides: 11
Provided by: Somm3
Category:

less

Transcript and Presenter's Notes

Title: AMS02 Increased Mass Loads Assessment


1
AMS-02 Increased Mass Loads Assessment
  • Chris Tutt (Jacobs Sverdrup)

2
Introduction
  • Current manifest weight budget for AMS-02 is
    14,809 lbs (6717 kg)
  • AMS Project Office has requested that the total
    mass of AMS-02 be increased to 15,100 lbs (6849
    kg)

3
Modeling Approach
  • The AMS-02 Finite Element Model (FEM) was fully
    updated to assess the impact of the current
    weight estimate of 15,100 lbs (6849 kg) for the
    payload.
  • All primary structural component models were
    fully updated to match the current mass estimates
    for both the Vacuum Case and USS-02.
  • Updates to all sub detector loads models was
    performed to reflect the detectors current
    geometry and mass estimates that were given in
    the October 2005 TIM in Geneva.
  • All 192 load cases (64 Launch, 64 Abort Landing
    and 64 Nominal Landing) were run and post
    processed to determine the impact of the
    increased mass to the USS-02 and VC only.

4
AMS-02 Model 12-05
Primary Trunnion View
Secondary Trunnion View
5
Analysis Results
  • Analysis results reflect only the primary
    structural bolted and riveted interfaces of the
    USS-02 and Vacuum Case.
  • Reasons for checking only these interfaces
  • To determine the overall loads behavior of the
    structure to help assess if additional analysis
    is needed for any particular component.
  • Most of the structural components of the USS-02
    were analyzed to the original design load
    factors, which were higher than the current
    loads. (with the exception of the Vacuum Case
    Rings and Lower Vacuum Case Joint)

6
Margins of Safety
7
Conclusions for Primary Structure
  • All primary structural interfaces of the USS-02
    show positive margins of safety for the Launch
    condition with the exception of the Diagonal Sill
    Bracket to Sill Trunnion Joint.
  • Negative margins of safety associated with
    landing loads can be shown positive by adjusting
    the fasteners preload.
  • The two primary riveted connections analyzed
    using the updated loads show positive margins of
    safety.

8
Remaining Work for Primary Structure
  • Additional analysis of the Vacuum Case Upper
    Support Ring will be necessary given the
    increased loads at the USS to Vacuum Case
    interfaces. The current margin of safety for
    this component is approximately 7.
  • Updated analysis results for the remaining
    riveted connections has not yet been performed.
  • Effects of the increased mass to ISS on-orbit
    load environment will need to be assessed.

9
Impacts to Large Subdetectors
  • Subdetector developers for the TOFs, RICH, TRD,
    Radiators, and ECAL will need to conduct their
    own structural analysis to assess the impact of
    the increased mass of the payload to their
    structure.
  • ESCG will supply each subdetector developer the
    USS interface displacements and case consistent
    load factors necessary to perform their own
    structural assessment.
  • ESCG will also provide the necessary engineering
    support to answer any questions concerning this
    analysis.

10
Impacts to Remaining AMS-02 Components
  • Smaller subdetectors and experiment components
    such as the CAB, TRD Gas Supply (S-Box and
    C-Box), Tracker, UPS and various other items that
    currently use secondary structure load factors
    will not be affected by the increased mass of the
    payload.
Write a Comment
User Comments (0)
About PowerShow.com