Title: PPA BETWEEN BSES ANDHRA POWER Ltd' and APTRANSCO
1PPA BETWEEN BSES ANDHRA POWER Ltd. andAPTRANSCO
- Presentation by
- K. Raghu
- Associate President
- APSEB Engineers Association
- Dt 16/01/2002
2This presentation consists of
- Load forecast-Need for additional power.
- Availability of gas reserves in K-G basin.
- Trends in gas prices/implications.
- Alternatives.
- Issues involved in the present PPA.
- Prayer to the Commission.
3Load forecast-Need for additional Power
- Load forecast plans are not brought to public
scrutiny. - State is landing in a surplus(?) situation.
- For Year 2001-02
- Available energy 45400MU
- Energy purchased by APTRANSCO 41500MU.
- Addition of NTPCs Simhadri power station (
2x520MW) during 2002-03 would result in huge
surplus situation. - Surplus is not a welcome sign in the absence of
potential buyers, as it involves huge fixed cost
commitments for APTRANSCO
4Load forecast-Need for additional Power
- Growth in consumption is not in keeping with the
capacity additions. - it is almost stagnant for the past three
years.(between 40000MU and 42000 MU). - With the reduction of TD losses there may be no
need for any capacity addition for five more
years. - Fall in subsidising sections(HT) and increase of
agriculture consumption. - Capacity additions must be carefully planned.
- Load forecast plans must be brought to public
scrutiny.
5Load forecast-Need for additional Power
- While maintaining our reservation on addition of
any new power projects without these Plans being
brought under public scrutiny, in the present
case, I.e the PPA between APTRANSCO and M/S BSES
Andhra power Limited, we submit our
objections/suggestions presuming that the
APTRANSCO needs the power sought to be generated
by M/S BSES Andhra Power Limited.
6Availability of gas reserves in K-G basin
- For the BAPL project gas is supplied from
Krishna-Godavari Basin- from the oil fields
located at Tativaka, Parsarlapudi, Kesnapalli,
Mori and other nearby fields and in and around
fields and Ravva offshore as fuel for the plant. - It is important to examine whether the gas
reserves in K-G basin are sufficient to meet the
requirement of existing and future projects,
including the BAPL project.
7Availability of gas reserves in K-G basin
- Gas reserves in the K-G basin -various estimates
(In Billion Cubic Meters) - As per CEA in the Fourth National Power Plan
1997-2012...16.36BCM. - FICCI Task Force Report 2000..37.35BCM.
- Hand book on Indian petroleum
and Natural gas Industry and
Investment scenario40.00BCM.
8Requirement of gas
- A) Existing Plants
- APGPCL 12 (272MW)
- GVK (216MW)
- SPECTRUM (208MW)
- KONDAPALLY(355MW)
- TOTAL 1051 MW.
- Therefore, gas required for the existing plants _at_
0.005 MCMD per MW - 1051X 0.005 5.255.
- Gas required per year 5.255X3651918MCM.
- I.e 1.918 BCM.
- _at_ 85plf gas requirement will be
0.85X1.9181630.36MCM 1.63BCM.
9Requirement of gas
- B) Future Plants for which gas has already been
allocated on firm basis - GVK(220MW), KONASEEMA (445 MW), VEMAGIRI (520
MW), GOUTAMI NCC (598MW), SPECTRUM (220
MW)8.53MCMD - Annual requirement 8.53X3653113MCMD 3.113BCM
- _at_ 85plf gas requirement will be 0.85X3.1132.64
BCM. - C)For BAPL project
- Daily requirement 1MCMD
- Annual requirement 365 MCM. 0.365 BCM.
- D) Other users of ONGC/GAIL per year 2.58 BCM
10Life of gas reserves in K-G basin
11Life of gas reserves in K-G basin
- Thus, it is very clear that
- Even if no future additions are made, life of gas
reserves (for the existing and other obligations
of GAIL) is 3.63years (as per fourth national
power plan) and 8.30 years ( as per FICCI
estimates). - Where as the plant life for these projects varies
from 15 to 18 years. - In the absence of gas reserves these plants will
depend on costly alternate fuels like Naphtha,
whose variable cost is very high. - It is not wise to go in for gas based projects,
when such heavy risk is associated with these
projects.
12Trends in natural gas prices-implications
- The pricing of indigenous natural gas is under an
administered price regime wherein the price is
decided by the GOI from time to time. - The pricing today is done with considerable
amount of subsidy. - It is govt. policy to avoid and eliminate
subsidies in the pricing of natural gas and bring
it on par with international LS/HS fuel oil
price. - Recently, the Petroleum ministry has proposed to
the cabinet a hefty 81 increase at the floor
level and 107 increase at the ceiling level
prices of natural gas.
13Trends in natural gas prices-implications
- Implications of proposed changes on the power
projects - The variable cost of generation may increase
steeply. Considering Fuel Oil price prevalent
during Sept. 2001 the price of gas is likely to
become double from its existing level. - Increase in cost of fuel per unit generation will
reduce in scheduling given for generation under
merit order operation. This inter-alia will cause
reduction in PLF and consumer will land up paying
higher costs without drawing the power. - Since PLF shall go down, Power Sector will have
to pay for the gas as committed even without
consumption thereby incurring huge losses.
14Trends in natural gas prices-implications
- Even fixed charges per kwh will also increase due
to lower off-take of power thus increasing the
power cost both on account of fuel price as well
as fixed charges per kwh. - Operating the gas based plants as peaking load
stations has its own problems - Since the pipeline network for supply of gas can
not take wide fluctuations in its rate of gas
delivery, therefore, such a situation will affect
the overall gas availability to the Power sector
at a pointed time. - For the all above reasons, even if sufficient gas
reserves are available, addition of gas- based
stations is not in the interest of consumers.
15Alternatives
- SNC Lavalin commented in its document of Long
term indicative Generation Plan for Andhra
Pradesh, availability of gas will be a major
concern. - The T.L. Shanker Committee observed that
indigenous coal would be natural choice for power
projects in India on both economic and other
grounds.
16Alternatives
- NTPC, in a detailed paper on the choice of fuels
for future projects in India, had concluded that
preference should be given to coal based
generation capacity as the cost of generation
with domestic coal is cheaper than power
generation with other fuels and the country has
good reserves of coal. - We request the commission to encourage only coal
based plants for any future capacity additions.
17Issues involved in the present PPA
- What is the subject matter before the Commission?
- Is it giving consent to the
- Amendment Agreement to the modified PPA
- or simply
- PPA between BAPL and APTRANSCO?
- Since various covenants, such as achieving
financial closure within 12 months from the date
of signing of modified agreement(Art.7.1.(e)),sche
duled date of completion - have not been
achieved, there is no obligation on the part of
APTRANSCO to adhere to the provisions of PPA .
18Issues involved in the present PPA
- Thus, there is no binding agreement between
APTRANSCO and BAPL. - Any proposal for power purchase shall be treated
as a new PPA between APTRANSCO and BAPL. - Hence, the proposal of APTRANSCO can not be
treated as amendment agreement to the modified
PPA, but only as a new PPA. - It is also not clear from the documents as to how
both original and modified PPAs were signed on
the same date, I.e on 31.03.1997, when proposal
for merger came at a much later date.
19Issues involved in the present PPA
- Who should bear the risk?
- It is also not clear how the BAPL went ahead with
the project, without having a legally binding
agreement with APTRANSCO. - By proceeding with the Project, without having
the consent of the Commission, the developer has
taken the riskand the Commission should ensure
that any consent to the PPA will not put
APTRANSCO and the consumers of the State in Risk. - As already stated there are so many risks
associated with the gas-based plants viz, - .availability of gas, deregulation of gas prices
etc,. - Also need for capacity additions at this point of
time should be looked in to.
20Issues involved in the present PPA
- Need for fresh bidding
- These projects are planned by the GOAP as short
gestation projects(SGPs). - However they could not come up in time and lost
their relevance now. - Originally these projects were awarded to various
developers through ICB route. - Since these projects could not be completed in
time , there is need for calling fresh bids and
awarding the contracts to the lowest bidders.
21Issues involved in the present PPA
- Reasons stated for giving extensions to the same
developers - It is claimed that going for fresh bids will
cause enormous delay. - It is also claimed that the fixed charges per
unit of all these projects have been brought on
par with the lowest bidder of all the Short
Gestation Projects, I.e.Goutami Power project,
and thus there is no need for going for fresh
bids.
22Issues involved in the present PPA
- The above reasons are not justified for the
following reasons - there is no need for any urgency for setting
upshort gestation projects at this point of
time, since we are already having surplus power. - Important parameter for evaluating these projects
at the time of awarding contracts was short
gestation I.e. some weightage was given for
completing the project in short duration,(
including Goutami Power Project) at the expense
of unit cost. - Now that these projects could not come up in
time, calling for fresh bids may result in
lowering of unit cost.
23Issues involved in the present PPA
- The claim that unit cost has been brought down to
the level of Goutami Project, is also not totally
true. - In the original PPA with Goutami the PLF for
fixed cost recovery was pegged at 80. - In the revised PPA with Goutami(Now placed before
the Commission for consent), PLF for fixed cost
recovery has been raised to 85. - I.e. net increase of Fixed Cost payment by
(85/80)x1006.25. - In real terms the increase in fixed cost
597x0.876x6.25x0.99/100Rs 32.35 Crore/year.
24Issues involved in the present PPA
- For other projects also the claim of substantial
reduction of fixed cost is not true. - For Ex it is claimed that for BAPL, the fixed
cost has been brought down from Rs 1.30/Unit to
Rs 0.99/ Unit(at present dollar exchange rate).
25Issues involved in the present PPA
- However, it can be seen that following factors
have the effect of increasing the fixed cost. - 1. Effect of increasing PLF for fixed cost
recovery - 99x 85/80-996.187 paise.
- 2. Effect of increasing the debt repayment period
from - 9 to 11 years 0.006x48x100x2/96.40
Paise. - 3. Effect of increasing the capacity from 200MW
to - 220MW(220/200)x99-99108.9-999.9 paise.
- 4. Effect of provision for increase in capacity
by 51.05x108.9-108.95.44 paise. - Total increase 6.1876.409.95.4427.92 paise.
26Issues involved in the present PPA
- Hence the fixed cost recovery per unit in real
terms is not 99 paise but 99 27.92 126.92
Paise. - I.e. 220x0.876x0.85x0.2792x1.05 Rs 48.01 crore
more than what is stated. - The total additional burden on APTRANSCO and
consumers of the state during the life of project
is Rs 720 crore. - Thus it is not true that substantial savings have
been achieved through negotiations with the
reduction of fixed cost per unit. - Hence, there is a need for calling fresh bids,
keeping revised capacity additions in view, which
may result in substantial savings to the
APTRANSCO.
27Fixed cost for similar project-Is 0.6990.006
cheaper?
28Fixed cost for similar project-Is 0.6990.006
cheaper?
29Fixed cost for similar project-Is 0.6990.006
cheaper?
- Average fixed cost for the identical project
- 1662.66/15 Rs 110.844 Crore
- Fixed cost per unit _at_ 85 PLF
- 110.844/(2200.8760.85)Rs 0.676 per unit
- i.e. 67.6 paise/ unit
- Therefore, for similar capital cost the fixed
cost obligation for APTRANSCO is 31.71 less than
the BAPL project.
30What should be the Fixed cost for BAPL?
- Average fixed cost to be
- allowed Rs 110.844Crore.
- _at_ 85 plf fixed cost per unit
- 110.844/(2200.8760.85) 67.66 Paise.
- Since the OM contract provides for 92 PLF, the
fixed cost per unit shall be - 67.6685/92 62.51paise.
- If 5 increase in installed capacity is allowed,
fixed cost recovery per unit shall be
62.51/1.0559.53 Paise - However, the old practice for payment of fixed
charges may be followed, for more clarity and to
avoid complications.
31Issues involved in the present PPA
- Other important issues
- It is not clear from the Agreement whether there
is any provision for disincentive when the PLF
falls below 85 and is above 68.5. - Clause 3.6 deals with the disincentives for PLFs
below 68.5 only. - Section 5.2.(c) which deals with the Monthly
tariff bills, only specifies the recovery to be
made if PLF falls below 80, and not for PLFs
below 85.
32Issues involved in the present PPA
- It is also not clear from 5.2.(c), whether the
recovery proposed is for all the PLFs below 80
or Only upto 68.5. - Also it is to be made clear whether the recovery
is in addition to the penalties that are proposed
to be levied. - Section 5.2.(c) states that in case PLF is less
than 80 for any tariff year, the company shall
refund to the Board as a credit against the
amounts due in the next monthly tariff bills.
33Issues involved in the present PPA
- this is totally unjust, as APTRANSCO will lose
the interest during this period for the payments
already made. - Even for the adjustments of disincentives, there
is no mention of any interest being added to the
disincentive paid by the Company to APTRANSCO,
before it is adjusted in the next tariff bills. - Also, there is no additional disincentive if the
project achieves the PLF below 50.5
34Issues involved in the present PPA
- it means that, even if the plant does not operate
APTRANSCO is bound to pay an amount equal
to220x0.876x0.85x(0.99-.46x0.699)x1.05 - Rs 114.97 Crore.
- This is equal to 115/700x10016.42 Return on
investments made.
35Issues of concern in Gas Supply Agreement(GSA)
- Allocation of gas is on fall back basis. As per
the definition in Section 1.16 of GSAFALL BACK
BASIS shall mean Second alternative I.e. supply
of GAS on As And When Available Basis without
any commitment on the part of the SELLER and
depending upon surplus GAS available after
meeting the demand of other firm consumers and
fall back consumer use alternate fuel when GAS is
not available for supply. - Also, according to Article 5, SELLER agrees to
sell and deliver GAS, on as and when available
basis,for supply to the BUYER, subject to the
maximum of 1.0 MSCMD.
36Issues of concern in Gas Supply Agreement(GSA)
- Period of contranct Article 2.01 states that
this CONTRACT shall come in to force from the
date it is signed and shall remain valid for a
period upto 31.12.2010. Subject to Article 5.01
hereinafter the supply of GAS under this CONTRACT
would commence from 1.10.2001 or from any earlier
date that may be mutually accepted by the SELLER
and the BUYER and shall continue for a period
ending 31.12.2010. - Whereas the plant life is 15 years, the GSA is
valid only for only 8 1/2 years from now, subject
to the conditions of fall back basis and maximum
availability of 1.0MCMD.
37Issues of concern in Gas Supply Agreement(GSA)
- It is important to note that existing plants
viz,.GVK, SPECTRUM and APGPCL, which have gas
allocation on Fall back firm Basis, are being
supplied gas only to the extent of Firm allotment
made to these projects. - Even if there is slight short fall in supply of
GAS, it should be mixed with certain minimum
quantity of NAPHTHA on technical considerations. - At present for APGPCL a ratio of 8020 between
gas and naphtha is used for power generation.
This is increasing the variable cost by 5
paise/unit.
38Issues of concern in Gas Supply Agreement(GSA)
- Quality of GAS
- Even though certain specifications are laid down
in Annexure-I of GSA, there is no mention of
Gross Calorific Value of gas that is supplied by
the GAIL. - Without Gross Calorific Value specifically
mentioned in the GSA, it is difficult to estimate
the actual gas that is consumed and variable
cost per unit of energy generated. - If there is any savings in GAS consumption it
must be passed on to the consumer.
39Issues of concern in Gas Supply Agreement(GSA)
- Delivery of GAS
- According to Article 4.03, in addition to the
price of GAS, the BUYER shall pay to the SELLER
monthly transmission charges of Rs
1,93,15,175 per month for facilities provided by
the SELLER for supply of GAS. (I.e. total fixed
cost commitment to APTRANSCO is (16323.16)Rs
186.16 crore.) - Also, during the currency of the CONTRACT
irrespective of total/partial/non-supply of
quantity of gas as per Article 5.01, the buyer
shall pay the above monthly fixed transmission
charges - the above monthly Transmission charges shall be
increased by 3 on yearly basis with effect from
1.4.2001.
40Issues of concern in Gas Supply Agreement(GSA)
- Thus the entire Gas Supply Agreement is heavily
biased in favour of supplier, full of
uncertainties and does not meet the requirement
of APTRANSCO.
41Equipment Supply OM contracts.
- Various technical parameters specified in the
Equipment Supply and OM contracts viz,. - Guaranteed output
- gross heat rate
- auxiliary consumption
- sheduled date of completion
- liquidated damages for delays, short fall, heat
rate,shortfall in auxiliary consumption,
guaranteed availability etc,. - PLF below which penalties are levied
- are found to be far superior than those provided
in the PPA.
42Equipment Supply OM contracts.
- This will unduly benefit the IPP, as all the
benefits from EPC and OM contract are to be
passed on to the consumer. - For ex it is stated in the Equipment Supply
contract that minimum availability shall be 93
and in OM contract minimum PLF to be maintained
as 92. IPP will levy penalties for any shortfall
from the stated PLF during the operation. - However, in the PPA it is stated that IPP will
get incentive for generation above 85 and
disincentive for PLFs below 68.5. - If the plant is operated at 90PLF, the IPP will
not only collect incentive from APTRANSCO but
also gets benefited from the penalty levied on
OM contractor.
43Issues involved in the present PPA
- Plant Life Plant life is stated as only 15
years. Where as for other IPP projects like GVK
and SPECTRUM the plant life is 18 years. - Escrow facility in addition to the irrevocable
revolving letter of credit in favour of the
company, as an additional security to the
company, APTRANSCO has to open escrow account
with any of the Boards scheduled Bank. This is
totally unjustified and not in the interest of
APTRANSCO. - Buy out procedure The buy out procedure adopted
in the PPA will result in the higher buy out
price for the project at the end of 15 years.
Since most of the capital cost (more than 90) is
recovered by the IPP by way of fixed charges, the
actual cost of plant shall only be 10 of the
total capital cost
44Prayer to the Commission
- Not to give consent to the PPA in view of the
following - Inadequate demand for power and consequent burden
of huge fixed costs. - Inadequate gas reserves available in
Krishna-Godavari Basin. - Lack of firm allocation of gas from GAIL.
- Uncertainties associated with the Gas prices, in
view of GOI policy to bring prices of natural gas
on par with the international LS/HS fuel oil
prices.
45Prayer to the Commission
- To recommend to the GOAP to call for fresh bids
for gas based projects, in case capacity
additions are necessary. - To give serious consideration to the
ramifications of planning for gas based power
projects in view of scarce natural gas resources,
high cost of alternate fuels, high forex
outflows, etc,.
46Prayer to the Commission
- 4. In case Commission decides to give Consent to
the proposed PPA, to consider the following
issues - To reduce the fixed cost burden as per the
calculations suggested in this petition. - Plant life shall be increased to 18 years from
existing 15 years on par with other Gas based
IPPs. - Recovery for full fixed costs shall be at 92PLF
as per OM contract, and in case unit cost method
for fixed charge recovery is used, the total
fixed cost shall be limited to the levels
suggested in this petition.
47Prayer to the Commission
- Disincentives shall be applied for PLFs below
50.5. - Gas supply shall be on firm basis, for full life
of the plant.Also Gross calorific value of Gas
shall be clearly stated. - Provisions relating to technical parameters of
Equipment Supply Contract and OM contract shall
be incorporated in the PPA. - Escrow facility shall not be given.
- Buy out procedure shall be modified to reflect
the actual cost at the end of plant life.
48- THANK YOU
- APSEB ENGINEERS ASSOCIATION