Public Interest Energy Research Natural Gas - PowerPoint PPT Presentation

1 / 10
About This Presentation
Title:

Public Interest Energy Research Natural Gas

Description:

Natural Gas in California ... California's total demand for natural gas is increasing: ... Some of the primary natural gas issues in California are consumer ... – PowerPoint PPT presentation

Number of Views:69
Avg rating:3.0/5.0
Slides: 11
Provided by: CEC128
Category:

less

Transcript and Presenter's Notes

Title: Public Interest Energy Research Natural Gas


1
  • Public Interest Energy Research Natural Gas
  • Program Status
  • Presentation to Air Emissions Advisory Committee
  • May 12, 2005
  • Philip Misemer
  • California Energy Commission
  • Energy Research and Development Division

2
  • Natural Gas in California
  • The CECs IEPR provides background and
    information on natural gas usage, patterns and
    issues in California.
  • Californias total demand for natural gas is
    increasing
  • Core demand (including residential, commercial,
    and smaller industrial customers) will increase
    at a rate of 0.9 percent per year
  • Non-core demand (large industrial customers) will
    increase at a rate of only 0.4 percent
  • Electric generation demand will increase at a
    rate of 1.5 percent per year.
  • Currently, pipelines from sources outside the
    State supply 85 percent of natural gas consumed
    in California.
  • Some of the primary natural gas issues in
    California are consumer gas costs, adequacy and
    security of supply, use of LNG, and gas
    distribution and storage infrastructure.

3
  • Natural Gas RD
  • Natural gas RD in California has historically
    been conducted by the States natural gas
    utilities, both regulated and public purpose
    research. Regulated gas RD has been the primary
    focus of the utilities efforts.
  • The trend in government, not-for-profit, and
    private-sector investment (including GRI/GTI) in
    gas-related RD has been downward over the past
    decade.

4
  • Natural Gas Research Legislative and Regulatory
    Background
  • Assembly Bill 1002 granted the California Public
    Utilities Commission (CPUC) authority and
    discretion to determine appropriate natural gas
    funding levels for low-income, energy efficiency
    and public interest RD activities.
  • Public Utilities Code Sections direct the CPUC to
    establish a natural gas surcharge for public
    policy programs and annually determine the
    amounts required to administer and fund these
    programs.
  • The CPUC issued Order Instituting Rulemaking (R.)
    02-10-001 on October 3, 2002, to determine broad
    policy issues and adopt a long-term framework to
    implement AB 1002.
  • During August of 2004, the CPUC, in Decision
    04-08-010 designated the California Energy
    Commission as Administrator of the Natural Gas
    Public Interest Research and Development Program.
  • Public interest gas RD activities are directed
    towards developing science or technology, 1) the
    benefits of which sic accrue to California
    citizens and 2) are not adequately addressed by
    competitive or regulated entities.
  • In addition, the CPUC expects approved RD
    projects to meet the following criteria
  • Focus on energy efficiency, renewable
    technologies, conservation and environmental
    issues
  • Support State energy policy
  • Offer a reasonable probability of providing
    benefits to the general public
  • Consider opportunities for collaboration and
    co-funding opportunities

5
  • Natural Gas Program Administration and Budget
  • CEC will manage daily activities and RD
    projects, including planning, project
    procurement, project accounting and program
    evaluation
  • CPUC will review and approve the annual program
    plans for RD projects to be funded
  • The CPUC adopted a 2005 (calendar year) Gas RD
    Program cap of 12 million
  • The CPUC also adopted the principle of zero-based
    budgeting for the RD Program
  • The budget can be increased by up to 3 million
    annually pending identification and approval of
    additional RD projects, to a maximum cap of 24
    million after four years. After this period, the
    CPUC will assess the reasonableness of the
    funding level, and the overall RD program.

6
2005 Program Plan
  • CEC submitted a 2005 program plan to the CPUC on
    10/31/04
  • The plan was prepared in about two months and
    involved an abbreviated planning process
  • Working with the utilities on their transition
    plans
  • PGE had no projects for continuation
  • SEMPRA had several projects for continuation
  • Collaborating with CPUC staff on what level of
    detail was required and process issues
  • Working with other CEC Divisions and the RD
    Committee
  • Input and review from the PIER team leads
  • Meetings with stakeholder groups (Governors
    office, GTI, EPRI, LBNL, PGE and SEMPRA)
  • The Abstract process - received about 170
    concepts (by 9/30/04) that were ranked per CPUC
    requirements
  • The core element of the research plan was
    selection of the four research areas for PINGR
  • The Plan was approved by the CPUC on 12/16/04

7

8
Thus far projects have been identified that could
expend over 80 percent of the 10.5 million
available for research to be initiated 2005.
Staffing and program technical assistance should
be fully in place for the 2006 program.
9
  • On-Going CPUC Requirements
  • Produce annual program report on RD activities
    and spending March 31st of each year
  • Show CPUCs Energy Division that projects are
    performed in a timely manner, within a budget and
    at reasonable cost and justify program RD
    expenditures
  • Close coordination with IEPR/ER
  • Stakeholder (public) input to program
  • Inform Energy Division if and when any commercial
    benefits result from the gas RD projects funded
    through the gas surcharge
  • Suggested projects should be provided to the CEC
    and the Energy Division by July 31 of each year
    for adopting the next annual gas RD program.
  • By August 31 of each year, the CEC is to provide
    a prioritized list of projects that meet the
    CPUCs adopted project criteria to the Energy
    Division.
  • Up to 15 million RD Plan for 2006 due by August
    31, 2005

10
  • On-going Issues
  • Contract Terms and Conditions
  • Contracting/procurement processes
  • July project submittals
  • August 31 Program Plan deadline
Write a Comment
User Comments (0)
About PowerShow.com