ISS Front End Replacement (FEPR) - PowerPoint PPT Presentation

1 / 6
About This Presentation
Title:

ISS Front End Replacement (FEPR)

Description:

Network Design Concept. Private Layer 3 IP network over NTR backbone. Three logical triangles ... Equipment Testing at JSC is scheduled for Feb 07 ... – PowerPoint PPT presentation

Number of Views:75
Avg rating:3.0/5.0
Slides: 7
Provided by: Jos586
Category:
Tags: fepr | iss | end | front | replacement | testing

less

Transcript and Presenter's Notes

Title: ISS Front End Replacement (FEPR)


1
ISS Front End Replacement (FEPR)
  • Overview

2
Introduction
  • Existing ISS FEPs are obsolete and must be
    replaced by FY08/09.
  • ISS doing an IDEA-type implementation for FEPR
    with connections from an ISS FEPR Equipment Rack
    to the Space Network Low Rate Data Switch
  • Level 0 processing of ISS S-band data moves from
    JSC to White Sands Complex
  • Interface from FEPS at White Sands is via TCP/IP
  • Interface from JSC to / from FDF is moved from
    4800 bit block serial to TCP/IP
  • Communications among various FEPR sites is via a
    Private TCP/IP network over NTR backbone

3
Network Design Concept
  • Private Layer 3 IP network over NTR backbone
  • Three logical triangles
  • JSC-WSGT-STGT
  • MSFC-WSGT-STGT
  • GSFC-WSGT-STGT
  • A point-to-point link from JSC to KSC (no backup)

4
Proposed FEPR Routing
Available on request from Vicki Stewart, NASA,
NTR Project Manager 301-286-6205
Victoria.Stewart_at_nasa.gov
5
Operational Concept
  • IP NOC will manage the FEPR Routers and the
    Firewalls used to connect the ISS FEPR Network to
    Open IONet
  • A network probe managed by IPNOC will be
    installed at each FEPR site
  • Each FEPR site will be connected to an OOB
    secured modem accessible only from IPNOC
  • NISN Mission Security will perform IDS Monitoring
    at the connection to Open IONet

6
Current Status and Schedule
  • Delta SDDR held in August
  • SCP Factory Acceptance Test Underway
  • NISN has tested Routers
  • Equipment Testing at JSC is scheduled for Feb 07
  • Installation of Racks at WSC is scheduled for Mar
    07