Title: Tehachapi Renewable Transmission Project
1Tehachapi Renewable Transmission Project
Public Draft EIR/EIS
- Web Seminar
- March 12, 2009
- Aspen Environmental Group
- Lead Agencies
- California Public Utilities Commission (CPUC)
- USDA Forest Service, Angeles National Forest
(ANF)
2 Dial-in Number 800-550-8104Participant ID
2345678
- Web Seminar
- Host Jon Davidson, Aspen Environmental Group
- Schedule This web seminar is scheduled for one
hour the PowerPoint presentation is 45 minutes - Q A Questions will be answered after the
presentation in the order received. - Please submit questions during the presentation
using the Instant Messaging feature in the
toolbar. - For questions that cannot be answered in the
time allotted, we will follow up with you
individually.
3 Agenda
- Overview of the Project and Alternatives
- Organization of the Draft EIR/EIS
- Major Conclusions
- How to Submit Comments
4 Agenda
- Overview of the Project and Alternatives
- Organization of the Draft EIR/EIS
- Major Conclusions
- How to Submit Comments
5 Overview of the Project and Alternatives
- Southern California Edisons (SCE) proposed
Tehachapi Renewable Transmission Project (TRTP)
includes new and upgraded transmission line and
substation infrastructure along approximately 173
miles of new and existing rights-of-way (ROW) in
portions of Kern County, Los Angeles County, and
San Bernardino County. - Project Alternatives include
- Alternative 1 No Project/Action Alternative
- Alternative 2 Proposed Project
- Alternative 3 West Lancaster Alternative
- Alternative 4 Chino Hills Alternative Routes A
D - Alternative 5 Partial Underground Alternative
- Alternative 6 Maximum Helicopter Construction in
the ANF Alternative and - Alternative 7 66-kV Subtransmission Alternative.
6 Overview of the Project and Alternatives
- Purpose and Need
- California Renewables Portfolio Standard (RPS)
goal - Tehachapi Wind Resource Area (TWRA) in southern
Kern County expected to provide up to 4,500 MW of
new wind generation - Antelope Transmission Project (ATP) previously
approved to provide 700 MW of transmission
capacity - Project Purpose
- Provide transmission capacity for planned wind
energy projects in the Tehachapi/Mojave area of
southern Kern County. - Eliminate transmission constraints when
transmission lines need to be shut down in the
Cajon Pass. - Enhance the reliability of the transmission grid
in the Antelope Valley where power load is
growing. - Executive Order 13212
- Expedite the completion of energy-related projects
7 Overview of the Project and Alternatives
- Alternative 2 Proposed Project
- Project Segments in Geographical Order, from
North to South - Segment 10 (North Region Kern County)
- New 500-kV single-circuit transmission line (T/L)
in new ROW for 17 miles between Windhub and
Whirlwind Substations - Segment 4 (North Region Kern County, Los Angeles
County City of Lancaster) - Two new 220-kV single-circuit T/Ls in new ROW for
4 miles between Cottonwind and Whirlwind
Substations - New 500-kV single-circuit T/L in new ROW for 16
miles between Whirlwind and Antelope Substations - Segment 5 (North Region Los Angeles County City
of Lancaster, City of Palmdale) - Rebuild existing 220-kV T/Ls (two) to 500-kV
standards for 18 miles between Antelope and
Vincent Substations
8 Overview of the Project and Alternatives
- Alternative 2 (continued)
- Segment 11 (Central Region Los Angeles County
Angeles National Forest) - Rebuild existing 220-kV T/L to 500-kV standards
for 19 miles between Vincent and Gould
Substations, traversing USDA Forest Service lands
in the Angeles National Forest (ANF) - Segment 6 (Central Region Los Angeles County
Angeles National Forest ) - Rebuild existing 220-kV T/L to 500-kV standards
for 32 miles between Vincent Substation and the
southern boundary of the ANF - Segment 11 (South Region Los Angeles County
Cities of La Cañada Flintridge, Pasadena,
Temple City, Rosemead, Monterey Park) - New 220-kV circuit on the vacant side of existing
220-kV double-circuit structures between Gould
and Mesa Substations - Segment 7 (South Region Los Angeles County
Cities of Duarte, Irwindale, Baldwin Park,
City of Industry, South El Monte,
Montebello, Monterey Park) - Rebuild existing 220-kV T/L to 500-kV standards
for 16 miles between the southern boundary of the
ANF and Mesa Substation
9 Overview of the Project and Alternatives
- Alternative 2 (continued)
- Segment 8 (South Region)
- Rebuild existing 220-kV T/L to 500-kV standards
for 33 miles between the San Gabriel Junction
and Mira Loma Substation - Rebuild existing 220-kV T/L from single-circuit
to double-circuit structures for 7 miles - Segment 9 (Substations)
- New Whirlwind Substation (500/220-kV), located 4
- 5 miles south of Cottonwind Substation in Kern
County - Upgrade five existing substations to accommodate
new T/L construction and system compensation
elements - Antelope Substation (Segments 4 and 5)
- Vincent Substation (Segments 5, 11, and 6)
- Mesa Substation (Segments 11 and 7)
- Gould Substation (Segment 11)
- Mira Loma Substation (Segments 8)
10 Overview of the Project and Alternatives
- Alternative 3 West Lancaster Alternative
- Suggested by members of the public prior to the
scoping period, due to potential land use
conflicts in west Lancaster - Deviates from the Alternative 2 alignment for 3.4
miles along Segment 4 - At Segment 4, Mile 14.9, the Alternative 3
alignment turns south down 115th Street West,
versus 110th Street West under Alternative 2 - The new 500-kV T/L continues for 2.9 miles then
turns east for 0.5 mile - Alternative 3 rejoins the Alternative 2 alignment
at Segment 4, Mile 17.9 - Increases the overall length of Segment 4 by 0.4
mile - Requires one less transmission structure due to
greater spacing between towers along Segment 4
11 Overview of the Project and Alternatives
- Alternative 4 Chino Hills Route Alternatives
- Suggested by the City of Chino Hills during the
scoping period to avoid the proximity of T/L
infrastructure to existing residences - Avoids the construction of 16 miles of Segments
8A, 8B, and 8C through Chino Hills - Includes four routing options that deviate from
the Alternative 2 alignment at Segment 8, Mile
19.2 and continue southeast, terminating within
or near Chino Hills State Park
12 Overview of the Project and Alternatives
- Alternative 5 Partial Underground Alternative
- Developed to avoid impacts of overhead T/Ls to
residential areas in the City of Chino Hills - Follows the same alignment of Alternative 2, with
3.5 miles of the T/L installed underground along
Segment 8 between Mile 21.8 and Mile 25.4 - Primary components of the underground segment
include - An underground tunnel with vertical access shafts
- Circular tunnel with a 16-foot internal diameter
and 18-foot external diameter - Monitoring systems, ventilation systems, lighting
system, communication system, power source,
electrical distribution system, and telemetry
will be included during tunnel construction - Western access shaft is 420 feet deep, 75 feet
long, 20 feet wide eastern access shaft is 100
feet deep, 75 feet long, 20 feet wide - Two aboveground transition stations (one at each
end of the underground segment) - Gas Insulated Line (GIL) system infrastructure
13 Overview of the Project and Alternatives
- Alternative 6 Maximum Helicopter Construction
- Requested by the Forest Service to reduce ground
disturbance within the ANF by minimizing new road
construction through use of helicopters during
construction - Requires the construction of eleven 4-acre
helicopter staging areas throughout the ANF - Avoids the need to construct or improve 42 miles
of access and spur roads in the ANF that are
required under Alternative 2
14 Overview of the Project and Alternatives
- Alternative 7 66-kV Subtransmission Alternative
- This alternative re-routes and/or places the
existing 66-kV subtransmission line underground
in three locations to avoid or minimize Project
impacts - Segment 7, Mile 8.9 9.9
- 66-kV line is placed underground
- Requested by the Los Angeles County Board of
Supervisors - Minimizes impacts to passive recreation
opportunities in the planned River Commons at the
Duck Farm Project - Segment 7, Mile 11.4 12.0
- 66-kV line is re-routed and placed underground,
as identified by SCE - Provides habitat enhancement for least Bells
vireos in the Whittier Narrows Recreation area - Segment 8 Mile 2.2 3.8
- 66-kV line is re-routed, as identified by SCE
- Provides habitat enhancement for least Bells
vireos in the Whittier Narrows Recreation area
15 Agenda
- Overview of the Project and Alternatives
- Organization of the Draft EIR/EIS
- Major Conclusions
- How to Submit Comments
16 Organization of the Draft EIR/EIS
- Organization of the Draft EIR/EIS
- Executive Summary
- Chapters
- 1 Introduction
- 2 Alternatives, including the Proposed
Project ROW cross sections - 3 Affected Environment and Environmental
Consequences - 4 Comparison of Alternatives
- 5 Other Required NEPA and CEQA Considerations
- 6 Development of the Tehachapi Wind Resource
Area (TWRA) - 7 Consultation and Coordination
- 8 References
- 9 Glossary and Acronyms
- 10 Index
- Technical Appendices
- A Alternatives Screening Report
- B Notice of Preparation, Notice of Intent, and
Federal Register Notice - C Air Pollutant Emissions Calculations
- D Project Road Crossings
- E Summary of the PdV Wind Energy Project EIR
17 Organization of the Draft EIR/EIS
- Chapter 3 Affected Environment and Environmental
Consequences - Section 3.X-1 Introduction
- Describes the resource/issue area addressed and
identifies issues raised during scoping - Section 3.X-2 Affected Environment
- Includes an in-depth description of existing
conditions relevant to the identified
resource/issue area - Section 3.X-3 Applicable Laws, Regulations, and
Standards - Section 3.X-4 Impact Analysis Approach
- Presents the Applicant-Proposed Measures (APMs)
identified by SCE for the resource/issue area - Lists the Significance Criteria that will be used
to determine environmental impacts - Section 3.X-5 3.X-11 Analysis of Alternatives
- Includes full environmental impact analyses for
the proposed Project and all alternatives, as
determined by the resource/issue area-specific
Significance Criteria. Also includes discussion
of cumulative effects. - Section 3.X-12 Impact Significance Summary
- Provides a summary of all identified
environmental impacts, including direct,
indirect, and cumulative impacts, as relevant to
the resource/issue area
18 Organization of the Draft EIR/EIS
- Chapter 3 (continued)
- Significance Criteria
- Environmental impacts of the Project would be
significant if they meet any of the identified
Significance Criteria for the applicable
resource/issue area - CEQA Guidelines (Appendix G, Environmental
Checklist Form, Section IX) are commonly used to
identify Significance Criteria - Impact Statements
- For each resource/issue area, each identified
impact has a unique number and title, followed by
a full discussion/analysis of the impact - For example, the first impact identified in the
Agricultural Resources analysis is - Impact AG-1 Construction activities would
temporarily preclude the agricultural use of some
Farmland - Many impact discussions address the north,
central, and south regions of the Project Area
separately due to substantial differences in how
impacts occur within each region
19 Organization of the Draft EIR/EIS
- Chapter 3 (continued)
- Mitigation Measures
- As feasible and applicable, mitigation is
identified following each impact discussion - For each resource/issue area, each identified
mitigation measure has a unique number and title,
followed by a full discussion of the required
action(s) - For example, the first mitigation measure for
Impact AG-1 is, Mitigation Measure AG-1
Coordinate construction activities with
agricultural landowners. - Mitigation measures would be applied in addition
to Applicant-Proposed Measures (APMs) and Best
Management Practices (BMPs) included as part of
the Project - CEQA Significance Conclusions
- Provided for each identified impact, following
the presentation of all applicable mitigation - Class I Significant and unavoidable impact
- Class II Less than significant impact with
implementation of mitigation - Class III Less than significant impact with no
mitigation required - Class IV Beneficial impact
20 Agenda
- Overview of the Project and Alternatives
- Organization of the Draft EIR/EIS
- Major Conclusions
- How to Submit Comments
21 Major Conclusions
- Impact Overview
- Most impacts of the proposed Project and
Alternatives would be construction related and
temporary in nature - Significant long-term impacts include
- Adverse visual changes associated with new
transmission infrastructure - Increased corona noise levels
- Constraints to aerial suppression of wildfires
- Land disturbance in the ANF, particularly as
related to road construction, would result in
temporary impacts that would be of longer
duration than most - Implementation of a multi-year mitigation and
monitoring plan would be required to facilitate
re-vegetation and prevent the establishment of
invasive species - Visual scars from hillside road improvements
would be apparent until Forest Service standards
associated with relevant Operation Maintenance
Levels (OMLs) are restored
22 Major Conclusions
- Significant and Unavoidable Impacts (Class I)
- Air Quality
- Class I impacts would occur under Alternatives 2
- 7 - Construction emissions exceed daily significance
thresholds in the South Coast Air Quality
Management District and the Antelope Valley Air
Quality Management District - Biological Resources
- Class I impacts would occur under Alternatives 2
- 7 - Construction activities would disrupt vegetation
and wildlife in a variety of ways - Cultural Resources
- Class I impacts would occur under Alternative 2 -
7 - Construction may have direct effects to National
Register of Historic Places (NRHP) properties, or
to NRHP-eligible properties - Land Use
- Class I impacts would occur under Alternative 4
(Chino Hills Route Alternatives) and Alternative
5 (Partial Underground Alternative) - Alternative 4 would not be consistent with the
Chino Hills State Park General Plan - Alternative 5 would require the take of property
and businesses through eminent domain
23 Major Conclusions
- Significant and Unavoidable Impacts (continued)
- Noise
- Class I impacts would occur under Alternatives 2
7 - Construction activities would substantially
increase ambient noise conditions for sensitive
receptors within 200 feet of construction
activities - Permanent noise levels along the ROW would
increase due to corona noise from operation of
the transmission lines and substations in the
vicinity of sensitive receptors - Corona noise would not be in compliance with
noise standards of Los Angeles County or the
Cities of Chino, Monterey Park, and Whittier - Visual Resources
- Class I impacts would occur under Alternatives 2
7 - Construction would result in visual impacts on
landscape character and visual quality of
landscape views as seen from various vantage
points - Wildfire Prevention and Suppression
- Class I impacts would occur under Alternatives 2
7 - Potential failure of Project components could
result in wildfire ignitions and damage to homes
from Project-related wildfires
24 Agenda
- Overview of the Project and Alternatives
- Organization of the Draft EIR/EIS
- Major Conclusions
- How to Submit Comments
25 How to Submit Comments
- Submit Comments on the Public Draft EIR/EIS
- Email
- TRTP_at_AspenEG.com
- Voicemail/Fax
- (888) 331-9897
- Postal Service
- John Boccio / Justin Seastrand
- CPUC / USDA Forest Service
- c/o Aspen Environmental Group
- 30423 Canwood Street, Suite 215
- Agoura Hills, CA 91301
- Attend a Public Meeting
26 How to Submit Comments
27 Questions / Comments