Ph' Lalieux, J' Bel, M' Demarche, C' De Bock - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Ph' Lalieux, J' Bel, M' Demarche, C' De Bock

Description:

vis- -vis regulatory or other stakeholder requirements) Remaining open issues with SC/OPC ... Large-scale heater test (over 10 y duration) ... – PowerPoint PPT presentation

Number of Views:41
Avg rating:3.0/5.0
Slides: 22
Provided by: vinci
Category:

less

Transcript and Presenter's Notes

Title: Ph' Lalieux, J' Bel, M' Demarche, C' De Bock


1
The PRACLAYProject An Evolving Cornerstone in
the Belgian Deep Disposal Programme
  • Ph. Lalieux, J. Bel, M. Demarche, C. De Bock
  • HLW/MLW Disposal Programme Coordinator

2
Content
  • Introduction
  • Original aims and current achievements
  • Current design review
  • Redefining PRACLAY
  • PRACLAY Components
  • Conclusions

3
Introduction (i)
  • PRACLAY Project as a pivot between
  • Phase of methodological RD
  • Pre-project phase
  • Initially set up as an in situ, large-scale
    demonstration of the technical, industrial and
    economic feasibility of disposing of
    heat-emitting vitrified HLW in Boom Clay

4
Introduction (ii)
  • However
  • Numerous design developments
  • Review of the functions to be ensured by EBS
  • Increased consideration of operational issues
  • Complete review of the SAFIR 2 design
  • Requires long-term preparatory work
  • Sufficient underground access
  • Adequate phenomenological understanding
  • Rethinking PRACLAY

5
Original aims and current achievements (i)
  • Dig a gallery using industrial techniques
    representative for a full-size repository
  • Successful realisation of the connecting gallery
    (2001-2002) using TBM and wedge blocks
  • Realise a crossing between main and disposal
    galleries
  • Partially met by the crossing between the second
    shaft and the connecting gallery
  • To be fully met by the construction of the
    crossing between the connecting gallery and the
    PRACLAY gallery study of its behaviour under
    different constraints such as thermal load

6
Original aims and current achievements (ii)
  • Establish and observe a set up which is identical
    to a planned disposal gallery for vitrified HLW
  • SAFIR 2 design
  • VHLW simulated by electrical heater
  • Not been met yet
  • However, experimentally prepared through the
    OPHELIE Mock up

7
Original aims and current achievements (iii)
  • Improve EBS knowledge
  • Some parts included in the OPHELIE works
  • On-surface, large-scale hydration test of
    pre-fabricated bentonite blocks under a thermal
    load (1995-2003)
  • Contributed extensively to the current design
    revision
  • Contributed to further refine instrumentation

8
Phases of the HADES URF
9
SAFIR 2 Design OPHELIE Mock-Up (dismantling)
10
Current design review
  • Current preferred option supercontainer
  • OPC Ordinary Portland Cement buffer
  • Carbon steel overpack
  • Still many issues to be solved
  • Behaviour under thermal stress
  • Alkaline effect (within EBS and Boom Clay)
  • Overall feasibility

11
Supercontainer design (radial)
12
Supercontainer design (radial)
13
Redefining PRACLAY (i)
  • Considering notably
  • Current evolution of the reference design
  • Flexibility approach (incl. vis-à-vis regulatory
    or other stakeholder requirements)
  • Remaining open issues with SC/OPC
  • Need for further characterisation work
  • No need to test everything now and in situ
  • Clear that the realisation of a unique large
    scale demonstration specific to one (nearly
    definitive) design may not be the most adequate
    option

14
Redefining PRACLAY (ii)
  • Support to stepwise design development
  • Confirmation aspects of the feasibility and
    understanding of some EBS elements
  • Testing issues that are generic to, and key for,
    all potential designs (i.e. that are
    design-independent) e.g.
  • Thermal impact on the Boom Clay and its EDZ, the
    gallery lining and crossing
  • Efficiency of gallery plugs
  • Starting as soon as possible
  • Extended experimental duration needed to ensure
    representativeness

15
Redefining PRACLAY (iii)
  • Combining surface and in situ
  • Surface when
  • No added value of going underground e.g.
  • Overpack construction
  • Supercontainer construction and handling
  • In situ conditions not imposing key requirements
    on the short term performances
  • EBS internal interactions
  • Help
  • Better control experimental conditions
  • Ease follow up
  • Increase cost effectiveness

16
PRACLAY Components (i)
  • In situ experiments
  • Crossing and gallery
  • Heater (and EDZ) test
  • Backfill test
  • Plug test
  • Witness test
  • On surface experiments
  • EBS material characterisation
  • EBS construction and handling
  • EBS interaction experiments

17
PRACLAY Components (ii)
  • PRACLAY gallery and crossing (2005-06)
  • Large-scale heater test (over 10 y duration)
  • THM perturbation might be the most severe
    transient (large spatial scale, short time)
  • Thermal impact on Boom Clay (EDZ whole
    thickness), lining, crossing and backfill
  • Combined excavation thermal effects
  • Confirmation of THM behaviour predictions
  • C (oxidation, pCO2, )

18
PRACLAY Components (iii)
  • Backfill test (EC IP ESDRED)
  • Definition in situ installation and testing of
    annular space between the supercontainer and the
    gallery lining
  • Plug test
  • PA poor plug performances do not contribute
    significantly to overall RN releases
  • However e.g. limit interactions between
    repository zones, increase resilience to
    intrusion, avoid gas migration
  • Focus on
  • Cutting hydraulic connection along lining and EDZ
  • Horizontal emplacement

19
PRACLAY Components (iv)
  • Witness test
  • Check the long term behaviour (several decades)
    of the EBS and the host rock in conditions
    representative of the planned ones
  • Test long term monitoring devices
  • Engineered analogue
  • Could only be installed after interpretation and
    (partial) dismantling the previously mentioned
    in-situ tests (not before 2017)

20
Schematic and preliminary overview of the PRACLAY
in situ experiments
21
Conclusions
  • Original objective demonstration of design for
    vitrified HLW
  • Reduced (more realistic expectations) to
  • Take into consideration design reviews and
    evolution
  • Tackle design-independent open issues
  • Enlarged to
  • Fully support iterative design development
  • Foster complementarity between small surface and
    large in situ experiments
Write a Comment
User Comments (0)
About PowerShow.com