Kansas City Hyatt Regency Walkway Collapse - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

Kansas City Hyatt Regency Walkway Collapse

Description:

The Kansas City Building Code requires a minimum support value of 151 kN. ... From the Kansas City example, the importance of an engineer's responsibility can ... – PowerPoint PPT presentation

Number of Views:2813
Avg rating:5.0/5.0
Slides: 15
Provided by: stude1751
Category:

less

Transcript and Presenter's Notes

Title: Kansas City Hyatt Regency Walkway Collapse


1
Kansas City Hyatt RegencyWalkway Collapse
  • AME30362 Design Methodology, Spring 2006

2
An Engineer's Responsibility
  • Engineers have a tremendous responsibility to
    insure the safety, health, and welfare of the
    public.
  • The public well-being can be maintained only if
    engineers follow all codes and standards, and
    uphold their professional obligations.
  • Safety during the construction phase of projects
    will help to insure the ultimate safety of the
    completed structure.
  • The Kansas City Hyatt Regency Walkway Collapse is
    an incident where construction safety was
    compromised, leading to the eventual collapse of
    the walkway.

3
Walkway Collapse
  • On July 17, 1981, the Hyatt Regency Hotel in
    Kansas City, Missouri held a videotaped tea-dance
    party in their atrium lobby. The hotel had only
    been open for approximately one year.
  • Many people were standing and dancing on the
    suspended walkways.
  • Several of the walkways collapsed, resulting in
    114 people killed, and over 200 injured. Millions
    of dollars in costs resulted from the collapse.

4
Walkway Collapse (cont.)
  • The connections supporting the ceiling rods that
    held up the second and fourth-floor walkways
    across the atrium failed, and both walkways
    collapsed onto the crowded first-floor atrium
    below.
  • The fourth-floor walkway collapsed onto the
    second-floor walkway, while the offset
    third-floor walkway remained intact.

5
Basic Walkway Design
  • Three walkways, on the second, third, and fourth
    floors, span the atrium.
  • The third floor walkway was designed for higher
    traffic than the other walkways, and was
    consequently wider and offset from the other
    walkways.
  • The third and fourth floor walkways were
    suspended from the atrium roof, with the second
    floor walkway connected to the fourth floor
    walkway.

6
A Collapse During Construction
  • A collapse occurred on October 14, 1979 while the
    hotel was under construction.
  • Over 2700 square feet of the atrium roof
    collapsed because a roof connection failed.
  • After this collapse, the engineering firm in
    charge promised to review all steel connections
    and requested on-site representation during
    construction.
  • The owner rejected the request, due to the
    additional cost involved.

7
Change In Design
  • While the hotel was under construction, The
    fabricator changed the design from a one-rod to a
    two-rod system to simplify the assembly task,
    doubling the load on the connector, which
    ultimately resulted in the walkway collapse.

Initial Design
New Design
8
Change In Design (cont.)
  • The fabricator did not want to have to thread the
    entire rod in
  • order to install the washer and the nut. The
    revised design
  • consisted of
  • The top ends of the third and fourth floor
    support rods were attached to the atrium roof.
  • The bottom ends went through the box beam where a
    washer and nut were threaded on.
  • A second rod was attached to the box beam four
    inches from the first rod.
  • The second floor walkway was suspended from the
    fourth floor walkway in a similar fashion.

9
FBD of Each Design
10
Cutting Corners
  • The fabricator, while in sworn testimony, claimed
    that his company had telephoned the engineering
    firm for change approval. The engineering firm
    declared they had not received the phone call.
  • Even as originally designed, the walkways were
    barely capable of holding up the expected load,
    and would have failed to meet Kansas City
    building requirements.
  • The Kansas City Building Code requires a minimum
    support value of 151 kN. The original design was
    capable of supporting 90 kN. With the design
    changes made during construction, the walkways
    would be supporting double that amount, or 180
    kN, assuming the walkways were loaded at the
    maximum recommended weight limit.

11
Walkway Failure Mode
  • The box beams could not support the applied loads
    and the fasteners on the end of the rods tore
    through the seam in the box beams, leading to the
    collapse.

12
Who was responsible?
  • A lack of communication between the designer and
    the fabricator is one of the contributors to the
    failure of the walkways.
  • The engineering firm did receive revised drawings
    during construction and stamped them with their
    engineering review seal, authorizing
    construction.
  • The revised design was significantly less capable
    of holding up the required forces, and was not
    designed in accordance with the Kansas City
    building code.

13
Consequences
  • 114 people were killed and over 200 injured.
  • Many principals involved lost engineering
    licenses.
  • Engineers were found guilty of gross negligence,
    misconduct, and unprofessional conduct in the
    practice of engineering.
  • Expensive legal suits were settled out of court.
  • Several firms involved went bankrupt.

14
Conclusion
  • From the Kansas City example, the importance of
    an engineer's responsibility can be seen in
    aspects ranging from design to construction.
  • The collapse of the atrium roof during
    construction was indicative of problems with the
    overall design.
  • Engineers should thoroughly review all designs
    and modifications made during the construction
    phase to insure the safety of the project.
Write a Comment
User Comments (0)
About PowerShow.com