Title: FED hardware status


1
FED hardware status
  • As of Sept 2005
  • From J. Coughlan communication

2
FED Production (I)
  • Progress is good. We are slightly ahead of the
    predicted FED delivery profile shown at last
    Tracker week. Now expect to start with delivery
    to CERN of 25 boards in October and 50 in
    subsequent months.
  • Our special FED Test setups were prepared and
    fully installed at the Assembly plant in
    July/August. Their staff were trained by our
    engineer and are now routinely running the tests,
    although with some expert assistance from our
    engineer on request.

3
FED Production (II)
  • The 1st batch of 50 FED boards was manufactured
    in August and are now under test. 48 have so far
    passed the Assembly plant tests. About 2 have
    persistent problems and will need some rework.
  • 42 of the passed boards are at RAL
  • 26 of these have now passed our additional tests
    (optical testing, TTC and SLINK).

4
FED Production (III)
  • 4 have some problems which we are investigating.
    But there are no common faults yet.
  • remainder are still being tested...
  • Our general policy is to put any boards failing
    tests to one side and go back to them after
    testing the whole batch. Of course if we spot a
    systematicfailure we would halt production.
  • The 2nd batch of 50 boards is now being assembled
    and should start being tested at the Assembly
    plant next week.

5
Transition cards for SLINK
  • 70 cards have been manufactured and all tested
    ok.
  • 35 of these are now at B904.
  • (We have only 5 twin Slink kits _at_CERN to connect
    up to 10 FEDs)

6
Firmware
  • The problems with VME Block Transfers with both
    CAEN and SBS are fixed.
  • We are now improving the readout speed.
  • There are many other firmware improvements being
    made Fake Frames, Spy channel, Zero
    Suppression Lite....