Title: JIRS Magnet Feasibility Study


1
JIRS Magnet Feasibility Study
US LHC Accelerator Research Program
bnl - fnal- lbnl - slac
P. Wanderer LARP CM9 October 18, 2007
2
JIRS task 3.3.2.2
  • Magnet Feasibility Study
  • Subtask 1 QA specifications, bench tests
  • QA Phase I upgrade 2012
  • Subtask 2 QB magnet design studies
  • QB Phase II upgrade 2016
  • Subtask 3 Slim magnets study design
    parameters, including type of superconductor
  • Slim inside ATLAS, CMS Phase II - 2016

3
Recent input
  • Email from Steve Peggs, Oct. 10
  • in yesterdays "extended PAF" meeting (Aymar,
    Garoby, Schmickler, Rossi, Evans, Bruning, )
    there was support from the top down, including
    Lyn, for Lucio's proposal for the U.S. to build 5
    Nb3Sn Q1 quads (includes 1 spare) for the Phase 1
    upgrade.

4
Budget allocation
  • Total 80k ( ¼ FTE 440 hours)
  • QA 60k (in view of PAF meeting)
  • QB 10k
  • Slim 10k

5
QA concept
  • Install Nb3Sn quad in an accelerator (e.g.,
    Tevatron, RHIC, LHC) or beamline to judge
    performance in real world situation (lifetime
    test, radiation heating, radiation damage)

6
If QA ? Q1 for Phase I
  • FY08 Q1 objectives
  • Establish who does what e.g., US provides
    cold mass, CERN the cryostat
  • Establish list of critical parameters length,
    gradient, aperture (gtQ1),
  • Establish list of needs for new conductor
    (strand, cable), hardware,
  • FY08 Q2 objectives
  • Establish values for the above (by 1/31?)

7
If QA ? Q1 for Phase I
  • FY08 Q3 objective
  • Conceptual Design Report (present draft at DOE
    annual review, June 08)
  • FY08 Q4 objective
  • Establish resources needed for Preliminary Design
    Report, begin work on report

8
QB Phase II - 2016
  • Determine QB parameter space
  • FY08 Q1 objectives
  • Establish list of people working on the task
  • List magnet parameters, design constraints
  • FY08 Q2 objective
  • Establish values for design constraints or
    estimates when values will be available
  • Draft intro to magnet design for non-experts

9
QB Phase II - 2016
  • FY08 Q3 objectives
  • Discuss constraints with other task groups via
    video and at CM10
  • Iterate intro to design document
  • FY08 Q4 objective
  • Prepare initial report jointly with other JIRS
    tasks

10
Slim magnets - 2016
  • Are the slim magnet meetings with
    AT/AB/ATLAS/CMS continuing?
  • FY08 Q1 objective
  • Establish task force members, CERN contacts,
    develop status report
  • FY08 Q2 objective
  • Prepare list of interface parameters (e.g.,
    allowed fringe field on detectors required
    spatial stability of magnets)

11
Slim magnets - 2016
  • FY08 Q3 objective
  • Prepare constraints, based on interface parameter
    list
  • Establish constraints, based on different
    superconducting materials (NbTi, Nb3Sn, HTS)
  • FY08 Q4 objective
  • Select superconductor(s)
  • Write report

12
Summary
  • Task interacts with several other
    disciplines/tasks in LARP and at CERN
  • QA Rapid action needed for QA Q1 Phase I
  • QB and slim magnets longer time frame -- need
    experience with machine, detectors to settle
    parameters