East Link Light Rail EIS Schedule

Description:

Month of March: Sound Transit Board member briefings on Bellevue's Preferred ... April 23rd: Anticipated Sound Transit Overview of all East Link segments, ... – PowerPoint PPT presentation

Number of Views:41
Avg rating:3.0/5.0
Slides: 2
Provided by: KBe67
Category:
Tags: eis | couplet | east | feis | go | light | link | rail | schedule | transit

less

Transcript and Presenter's Notes

Title: East Link Light Rail EIS Schedule


1
East Link Light Rail EIS Schedule
  • Month of March Sound Transit Board member
    briefings on Bellevues Preferred Alignment and
    Sound Transit Board member tours of East Link
    study area
  • March 26th Sound Transit Board East Link Public
    Meeting and Summary Information (including brief
    overview of Councils Preferred Alignment)
  • April 9th Sound Transit Public Meeting on East
    Link (including formal presentation of Councils
    Preferred Alternative)
  • April 23rd Anticipated Sound Transit Overview of
    all East Link segments, including At-Grade
    alternative in downtown (Alternative C4A
    at-grade couplet 110th/108th)
  • May 14th Anticipated Sound Transit Board action
    to identify preliminary preferred alternative(s)
    based upon information developed to date.
  • May-December Most promising alternatives
    selected by Board advance to approximately 15
    design though all alternatives are retained
    should additional study be warranted later.
  • January-Summer 2010 Continued design work to 30
    and selection of Boards final Preferred
    Alignment following issuance of FEIS