TRD ROC Status Clemens Adler

Description:

Procedure in place for the last batch of AW106 and AW116 (all Parameters were OK) GSI will do some own tests for comparison. Do we want QC procedure for old glue? ... – PowerPoint PPT presentation

Number of Views:53
Avg rating:3.0/5.0
Slides: 8
Provided by: wwwali
Category:
Tags: roc | trd | adler | bonn | clemens | huntsman | status

less

Transcript and Presenter's Notes

Title: TRD ROC Status Clemens Adler


1
TRD ROC Status
  • TRD Meeting
  • 30.3.07

2
Glue Quality Control
  • Quality control at Huntsman established (thanks
    to H. Risch, GSI)
  • Electrical and mechanical parameters are measured
  • -gt We accept (or not) the batch.
  • Procedure in place for the last batch of AW106
    and AW116 (all Parameters were OK)
  • GSI will do some own tests for comparison
  • Do we want QC procedure for old glue? (Pro
    we know what we used so far, Con we know
    what we used so far, Money)

3
Padplane Production
  • Papdlane soldering moved from Frankfurt to TU
    Darmstadt (H.Oeschler)
  • Production running since February
  • 5 people (Anton Przybyla et al.)
  • 100 paplanes done
  • Some problems with test device (solved)

4
Radiator grounding
  • Radiators are grounded with Scotch copper
    (conductive) tape to L-profiles
  • Christian discovered decreasing conductivity with
    time (leading to periodic discharges -gt HV
    instabilities)
  • Lesson Conductive copper tape (Scotch3M) is not
    suited for long term grounding (used in other
    places?!?)
  • Solution Silver epoxy. (procedure needs to be
    defined)

5
ROC Production planning
  • Status (3/2007)
  • Finished chambers to be done Total
  • Bucharest 67 41 108
  • Dubna 91 14 103
  • Frankfurt 27 44 71
  • GSI 68 78 146
  • Heidelberg 39 46 85
  • Production rates (historical average)
  • Bucharest 1 ch/week
  • Dubna 1 ch/week
  • Frankfurt 0.7 ch/week
  • GSI 1.2 ch./week
  • Heidelberg 0.5 ch/week

6
ROC Production planning
  • Status (3/2007)
  • Finished chambers to be done Total
  • Bucharest 67 41 108
  • Dubna 91 14 103
  • Frankfurt 27 44 71
  • GSI 68 78 146
  • Heidelberg 39 46 85
  • Production rates (historical average)
  • Bucharest 1 ch/week
  • Dubna 1 ch/week
  • Frankfurt 0.7 ch/week
  • GSI 1.2 ch./week
  • Heidelberg 0.5 ch/week
  • Further Production)
  • Type to be done Lab prod at Lab
  • LxC0 14 Dubna all
  • L0C1 44 Frankfurt all
  • L1C1 46 Heidelberg all
  • L2C1 42 Bucharest 20
  • L3C1 42 Bucharest 20
  • L4C1 39 GSI all
  • L5C1 39 GSI all
  • Timescale estimate
  • (assuming 4 weeks Summer vacation, 2 weeks
    Christmas vacation)
  • Lab Duration (weeks) End of prod
  • Bucharest 41 3/ 2008
  • Frankfurt 63 7-8/ 2008
  • GSI 65 7-8/ 2008

7
Production planning cont.
  • Scenario 1
  • Dubna takes over 22 chambers
  • Bucharest takes 22 chambers (130 ch. total) ?
  • Heidelberg works twice as fast
  • GSI, Frankfurt keep the rate
  • -gt ROC production finished 8/2008
  • Question
  • Dubna L3C1 only, or L3C1L2C1 (mixture)
  • Scenario 2
  • ???