Title: SonoraMohave Desert Renewable Transmission Project Proposal


1
Sonora-Mohave Desert Renewable Transmission
Project Proposal
  • Potential project being defined for transmission
    for renewables in Western AZ and southern CA
  • All elements and variations thereof identified
    through statements of interest received in a
    public process conducted by Western Area Power
    Administration last spring
  • Feasibility study to start this year

2
Sonora-Mohave Desert Renewable Transmission
Project Proposal
  • 4 potential elements
  • 3 500-kV lines
  • 2 potential double circuit 500/230-kV
  • Phased developmentbased on element readiness
  • Elements A-C previously identified in AZ
    utilities 10-year plans
  • All elements would involve participation by
    multiple entities
  • All elements would facilitate delivery of
    renewables to market

3
Sonora-Mohave elements
  • APalo Verde-North Gila
  • 500-kV, 100 miles
  • BPalo Verde-Blythe
  • 500-kV, 110 miles
  • CSouth of Parker
  • Potential double circuit, 230/500-kV, 330 miles

4
Sonora-Mohave elements
  • CNorth of Parker
  • Potential double circuit, 230/500-kV,
  • 135 miles
  • D-Imperial Valley
  • Potential 500-kV network addition to the
    Southern California grid in Imperial County,
    California