Title: Recent Electricity Auctions
1Recent Electricity Auctions
- Dr. David J. Salant
- Senior Vice President
- National Economic Research Associates
June 2003
2Agenda
- Electricity restructuring, auctions and new
markets - New Jersey Basic Generation Service auction
- Texas Capacity auctions
- CALPX/CAISO
- Alberta
- FTR auctions
- Parallels in other states and other types of
electricity markets
3Auctions and Regulation
- Auctions have been used increasingly to replace
regulatory processes - Spectrum auctions replaced beauty contests and
lotteries - Default Service Auctions
- Customers who are not being served by a
competitive third party supplier must be served
by the electricity distribution company at
regulated rates - Auctions now have been used for utility energy
purchases to serve these consumers - RFPs tend to be followed by bilateral
negotiations, providing more scope for regulators
to question the results. - Entitlements and PPAs
- Utilities required to divest assets
- Rather than sell off entire assets, auctions now
are used to sell entitlements, strips, PPAs, as
in Texas and Alberta
4New Types of Electricity Auctions
- Simultaneous clock auctions
- Used for buying or selling multiple units of a
few types of lots or products, such as system
slices or energy entitlements. - First application for default service procurement
was Simultaneous Descending Clock Auction (SDCA)
which NERA developed for New Jersey. - Variations of clock auctions have been used to
sell energy entitlements in Texas capacity
auctions and French VPPs. - Clock auctions are well suit for interconnection
capacity. - Simultaneous multiple round auctions has been
used on one occasion for selling PPAs in Alberta. - Other, more traditional, auctions such as Yankee
auctions and English auctions used for energy
entitlements in Alberta and for interconnection
in Netherlands did not work well.
5Auction Design Objectives
- Auction design adopted should best match
objectives
- Simultaneous multiple round/clock auctions are
appropriate for efficiently allocating multiple
lots, with value interdependencies, such as
energy entitlements, capacity and spectrum
licenses - Theory suggests that simultaneous auctions will
result in economically efficient assignments
assuming substitutes and straightforward
bidding - Simultaneous auctions work adequately when
bidders have similar views about complements - Clock auctions are well suited for dividing
shares of load.
- Simultaneous auctions can create some incentives
for bidders to withhold supply, but these
incentives can be mitigated with volume
adjustments - Simultaneous auctions work less well with strong,
overlapping complements
6The New Jersey BGS Auction
6
7The New Jersey BGS Auction
- Four utilities were under legislative mandate to
purchase energy in a competitive bidding process. - NJ EDCs needed to secure one-year forward
supplies for approximately 17,000 MW of forecast
peak load - Auction was for one year forward contracts.
- The auction outome
- Prices appeared to be competitive, between 4.87
and 5.82 for entire year. - Over 20 bidders competed to sell and there were
15 winners. - in first ever simultaneous descending price clock
auction. - New Jersey Board rendered decision on auction
results within 48 hours of the close of the
auction
8New Jersey Winning Bidders
BGS Winning Bidders for Year 4 Winning Bidder
Number of Tranches Won per EDC territory
PSEG
JCPL
Conectiv
RECO
5.112 /kWh
4.865 /kWh
5.117 /kWh
5.819 /kWh
ALLEGHENY ENERGY SUPPLY
AMERADA HESS CORPORATION
AQUILA ENERGY MARKETING
CONECTIV ENERGY SUPPLY INC
CONSOLIDATED EDISON ENERGY
DTE ENERGY TRADING INC
DUKE ENERGY TRADING
FIRSTENERGY SOLUTIONS CORP
MIECO
NRG ENERGY
PPL ENERGY PLUS CORP
SELECT ENERGY INC
SEMPRA ENERGY TRADING CORP
TXU ENERGY TRADING
WILLIAMS ENERGY MARKETING TRADING
9What was Being Purchased?
- Full requirements slices of BGS load of each EDC
- Payments will be based on load measured at the
PJM interfaceno risk of losses - Slices set at roughly 100 MW resulted in
- 96 PSEG tranches
- 51 GPUE/JCPL tranches
- 19 Conectiv tranches
- 4 RECO tranches
- Starting prices set by auction manager/EDCs
- Maximum and minimum possible starting prices in
the EDC filing - Not capped by shopping credits
- Will be based on indicative bids
- Will provide adequate risk premiums
- Auction manager had discretion to restrict
auction volume if competition proves very limited
10Market Background
- NJ EDCs BGS requirements of nearly 17,000 MWs
represented over 95 of all NJ energy consumption - Total native capacity of approximately 20,000 MW
including some NUGs (although 29,600 MW showed up
at the start of the auction) - PS Power controlled 57 of native resources
- The top four firm concentration, HH4 76
- Limited import capacity from South and West
through PJM - Energy prices North and East in NYISO tends to be
higher than in NJ - PJM structure facilitated competition in the
auction - FTR allocation coordinated with BGS contract
- PJM spot market provided options for both buyers
and sellers
11The New Jersey Year 5 BGS Auction
11
12Changes to the BGS Auction in Y5
- BGS Load Split into two groups
- Hourly Electric Price (CIEP/HEP) for large
corporate and industrial customers - Fixed Price (FP) for small and residential
customers - Separate but concurrent SDCAs will be held
- HEP Auction is for capacity (/MW-day)
- FP Auction is for all-inclusive price (/kWh,
same as Y4) - Regulatory approval for each auctions result is
separate. - Winning Bidders sign different contracts BGS-HEP
Supplier Master Agreement and BGS-FP Supplier
Master Agreement differ.
13Design of the New Jersey BGS Auction
13
14BGS Auction RulesOverview
- The standard Simultaneous Multiple Round (SMR)
auction format - Bidding in rounds
- Reverse auctionsthe sellers bid
- Uniform pricing
- Form of bidsquantities instead of prices
- Total bids cannot increase
- Switchingsuppliers can switch between EDCs
during auction - Ending the auction
15Sample Results Start of Auction
Round
1
EDC
Bid
Available
Ratio
Price ?
65.00
PSEG
142
1.48
2.40
65.00
JCPL
84
1.65
3.24
70.00
Conectiv
55
2.89
9.47
62.00
RECO
6
1.50
2.50
Totals
287
1.6882
170
Round
2
Bid
Available
Ratio
P rice ?
EDC
96
PSEG
51
JCPL
19
Conectiv
4
RECO
1.6765
Totals
170
16Sample Results Near Auction End
Round
EDC
Bid
Available
Ratio
Price ?
42
PSEG
52.10
102
96
1.06
0.31
JCPL
53.10
62
51
1.22
1.08
Conectiv
49.50
20
19
1.05
0.26
RECO
56.40
4
4
1.00
0.00
Totals
188
170
1.1059
Round
EDC
43
Bid
Available
Ratio
Price ?
PSEG
51.94
100
96
1.04
0.21
JCPL
52.53
63
51
1.24
1.18
Conectiv
49.37
20
19
1.05
0.26
RECO
56.40
4
4
1.00
0.00
Totals
187
170
1.1
17Exit Bids
- The following situation is possible
Round 45 price /kWh
Round 44 price /kWh
Tranches bid
Tranches bid
PSEG (20)
94
JCPL (12)
Conectiv (5)
RECO (1)
18Exit Bids
- When bidders reduce their quantity, they can
elect to submit an exit price - An exit price is a final price for a slice on
which a bidder will no longer be bidding. - Exit prices are
- EDC specific
- Required to be below the previous rounds going
price and above the current rounds price e.g.,
between 5.2 and 5.175 - If auction ends, slices would be allocated at the
exit price of the slice that just fills the load
for the product
19Other Auction Features
- Additional Rules
- Size of decrement depended on excess of tranches
subscribed over number of tranches available - If an EDCs tranches are just subscribed or
under-subscribed, bidders were not allowed to
decrease number of tranches offered - Switching restrictionsswitching was not allowed
if it would result in under-subscription - Load capseach EDC imposed a maximum on the
number of tranches that a bidder can supply - Pace
- Length of rounds were kept as short as possible,
but to still allow bidders time to decide on when
to reduce eligibility or switch - Bidders allowed limited recesses toward end of
auction
20Auction Closing Rules
- As long as there is some excess supply for at
least one product (more slices subscribed than
available) - Bidding continues
- Prices continue to tick down from one round to
the next - At a given point in the auction there can be
excess supply for one product but not for others - For auction to end
- Bidding on all products must have stopped
- The offered supply equals the number of available
slices for all products - Bidders are paid the closing prices per MWh
21Starting Prices andAuction Volume Adjustments
- Starting prices and auction volume adjustments
are two instruments to limit adverse consequences
if there is limited competition in the auction - The Auction Manager announced starting prices
three days prior to auction - Starting prices were required to be above PJM
forward curve by a percentage that was approved
by the BPU - Indicative bids were due two weeks prior to the
auction will factor into the setting of the
starting prices
22Starting Prices andAuction Volume Adjustments
Continued
- Target auction volume could be adjusted based on
total interest - If supply, as expressed in the indicative bids is
limited, auction volume could have been reduced - Target auction volume was to have been set at no
more than a multiple of initial supply - Further auction volume adjustments permitted
based on competition
23Auction Design Issues
- Factors affecting expected supplier costs/bidder
values - NUG contractstranche size depended on existing
NUG contracts - Line losses in the distribution system
- Capacity obligations
- BGS suppliers are required to satisfy the
renewable energy (green) standards. Combined rate
ranges from 3 in 2002 gradually up to 6.5 in
2012 - Starting prices
- Back-up provisions if supply was limitedauction
volume adjustments - Minimum stay rules, customer switching, slamming
- Implementationcredit, qualification, software
24The Texas Capacity Auctions
24
25The Texas Capacity Auctions
- The Texas Public Utility Commission (PUC)
mandated auctions of capacity by Power Generation
Companies (PGCs) beginning August 23, 2001 - All the PGCs (AEP, Reliant and TXU) have been
required to sell at least 15 of total capacity - The PUC has imposed specific auction
mechanicsincluding simultaneous auctions of all
PGC capacity of a given duration - Auctions were initially parallel and simultaneous
auctions - Activity rules initially were not comparable to
usual SMR auction formats - Due to price gaps, PUCT adopted switching rule
26The Texas Capacity Auctions
Continued
- Sellers were provided some latitude in setting
starting prices and minimum bid increments - Differences in approaches to starting prices and
bid increments drove auction dynamics in some
cases
27Auction Background
- Products are 25 MW entitlements defined by
- Zone (North, South, West and Houston (except
first auction)) - Type (baseload, gas-intermediate, gas-cyclic,
gas-peaking) - Seller (AEP, Reliant, TXU)
- Term (2-year, 1-year, 1-month)
- Timing
- Quarterly auctions
- At each quarterly auction, there were
- All 2-year contracts were auctioned
simultaneously (all types in all zones by all
PGCs) - Then, all 1-year contracts were auctioned
simultaneously - All 1-month contracts were auctioned
simultaneously were auctioned last
28Implications of Texas Experience for FTR/CRR and
Capacity Auctions
- FTR auctions in CA and elsewhere do not allow
switching between substitute paths - As in Texas, equivalent FTRs can and are likely
to sell for much different prices - Lack of switching implies
- Bidders need to guess when developing bidding
strategy - Allocative inefficiency when higher value bid on
one FTR loses to lower value bid on a near or
perfect substitute FTR (or CRR) - NYISO, ISO-NE, PJM are also planning to run
parallel auctions for each zone
29Additional Factors in CRR/FTR Auction Design
- Kirchoffs law implies possible non-convexities
in set of feasible power transfers - Non-convexities of feasible set will imply that
support prices (LMP) will result in corner
solutions - Implications for auction is that strong
incentives can exist for bidders to strategically
under or over report net demands - Package bidding and contingent bidding can be
useful in finding optimal allocations - Testing can involve simulation and experiments
- Recent developments in package bidding include
SAAPB adopted by FCC and Ausubel-Milgrom proxy
bidding procedures
30Alberta PPA Auctions
30
31Alberta PPA and MAP Auctions
- Alberta conducted two sets of auctions
- PPA auction for 12 PPAs in late 2000
- MAP auction for strips from unsold PPAs in 2001
- PPAs for energy entitlements of generating units
- Auction was a variation SMR auction format used
in NJ BGS and developed for FCC spectrum auctions
32Alberta Power Purchase ArrangementAuction
Results
33CALPX/CAISO
33
34California Energy Markets
- Three utilities PGE, SDGE/Sempra and Southern
California Edison - Peak demands of approximately 45K MW in summer
months - 18 of supplies from imports
- Five main generators controlled nearly half of
fossil fuel generation within CA - Summer 2000 crisis began and continued past the
close of the CALPX in Feb. 2001 with - Stage 2 emergencies declared on scattered days in
May September 2000 - Stage 3 emergencies in Dec. 2000 (1 day), January
2001 (18 days), February 2001 (16 days), March
2001 (2 days) and May 2001 (2 days). - Average loads of lt 33K MW through the latter part
of the crisis - AB 1890 mandate IOUs purchase energy through
CALPX/CAISO
35Some Explanations of What Happened?
- Strategic withholding of supplies (JK BBW) and
less than perfectly competitive behavior (Puller) - Lack of forward contracts
- CALPX had block forward market,
- IOUs were permitted to purchase much more block
forward than they did and they could hedge with
derivatives - Ex post regulatory review of forward/derivative
purchases placed all the downside risk with IOU,
so this was not a factor - Ability of other WECC buyers to be active in
forward markets and inability of CA IOUs placed
burden on latter (Allaz and Vila/SalantLoxley
NJ experience) - Lack of capacity credits/markets or regulation
- Nature of equilibrium in CALPX/CAISO SFE type
auctions
36NJ vs. California
- CA
- 3 large utilities
- Moderate HHI in generation
- Capacity and other reserves needed to respond to
demand peaks no longer mandated - CAISO/WECC provides links between zones
- High price spikes
- CALPX/CPUC did not give utilities much of an out
- Theoretically unsound Supply Function Auction
format
- NJ
- 3 large utilities
- High HHI gt 3200 in generation
- Significant transmission constraints to the
remain of PJM - Capacity credit market mandates reserve margins
- Outcome competitive average 5.1 for entire year
- Combination of primary long term contracts and
options for spot and short term contracts gave
more flexibility for buyers to get a more
competitive price - Clock auction designed to attenuate market power
of the sellers
37Example Price Competition with Capacity
Constraints
- One buyer who demands D units at any price up to
R. - Two sellers. Each seller can produce up to its
capacity K at zero marginal cost. - K lt D, so neither seller can supply the whole
market. - Sellers compete in prices each seller names a
single price at which it will sell up to K units. - Supply is dispatched in order of increasing
price, and sellers are paid as bid.
38No MC Equilibrium
Price
Demand
p2
R
Profmin
Supply
Units
p1 0
D
K
If both set p MC, then each sells D/2 at price
0, earning a profit of 0 If Seller 2 charged R
instead, it would sell D K earning a profit of
Profmin R(D K).
39Applicability of SDCA in Other States
39
40US Experience with Competition in Generation
Services
41Division of Load and Contract Terms
- Many options for dividing up load
- Uniform slices of system
- Division by customer segment
- Firm and non-firm tranches
- Metered vs. non-metered customer segments
- Contract terms
- Wholesale vs. resale
- Fixed price service vs. variable (market) price
- Seasonal adjustments
- Duration
- Uniform vs. non-uniform
- Length
42Contract Duration
- SDCA can permit contracts of different durations
e.g., Texas capacity auctions - Some longer term contracts can facilitate bidder
financing - Some shorter term contracts can allow bidders to
adjust portfolios, and can be especially useful
for bidders with plants coming on or going off
line.
43CA Demand and Supply Concentration
- As in NJ experience, CA has three main utilities
- Supply in California is less concentrated than in
NJ - Import capacity comparable in both regions
- Affiliation of PS Power with PSEG for
approximately 50 of native energy was potential
limitation of benefits of the auction - PJM FTR approach facilitated competition in
auction for default service load procurement - CAISO only control intra-state transmission,
inter-state transmission with rest of WECC could
limit competition in an auction
44Forward vs. Day Ahead Markets
- Auction volume adjustments left open possibility
of load procurement in day ahead or hour ahead
markets - Suppliers apparently wanted to avoid having to
sell in what could be a competitive day ahead
market, and so had incentives to bid aggressively
in BGS auction - Starting prices and process were reviewed and
approved by BPU in advance of auction - Auction process required BPU review within 48
hours of auction close - EDC and supplier exposure to risks were both
mitigated by prior approval and transparency of
process
45(No Transcript)