AMS02 Functional Integration Test FIT - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

AMS02 Functional Integration Test FIT

Description:

AMSFIT - 05 AMS PDL Command Test. AMSFIT - 06 AMS Housekeeping Data Test ... AMSFIT - 08 AMS PDL Telemetry Test. AMSFIT - 09 AMS HRDL End to End Test ... – PowerPoint PPT presentation

Number of Views:45
Avg rating:3.0/5.0
Slides: 16
Provided by: Lockheed7
Category:

less

Transcript and Presenter's Notes

Title: AMS02 Functional Integration Test FIT


1
AMS-02 Functional Integration Test (FIT)
  • October 21, 2004
  • Presenter P. Nemeth/LM

2
Objective
  • The AMS-02 Functional Integration Test (FIT) is a
    risk-mitigation test designed to exercise the
    avionics and ground segments of the experiment in
    the ISS and STS environments
  • FIT will utilize the STS and ISS test facilities
    within the SSPF
  • FIT will utilize the AMS-02 front-end avionics
    crates on table-tops (not the entire payload)
  • FIT is designed to verify end-to-end data flow in
    a high fidelity development test
  • All testing is to be performed at KSC, no
    requirement for remote data routing (tapes will
    be available post-test for further remote testing
    as desired)
  • Target Date for test January 18-28, 2004

3
FIT Setup
  • FIT testing is broken into two test setups, one
    for STS and one for ISS
  • STS testing in the Cargo Integration Test
    Equipment (CITE) Stand
  • ISS testing in the Payload Test and Checkout
    System (PTCS) Facility
  • AMS-02 Hardware to include
  • Qualification Unit J-Crate and JPD
  • Low fidelity Model AMS Crew Operations Post
    (ACOP)
  • Engineering Unit Power Distribution System (PDS)

4
STS Testing
  • STS testing will include
  • Power (including T0 for prelaunch and from
    Orbiter (APCUs) for in-flight) routed through AMS
    Power Distribution front-end
  • Data Compatibility Testing
  • LRDL Data (1553) testing (T0 and in-flight)
  • Will test RT4 and RT 28
  • Verify data handling between OIU, PDI/PSP, and
    Ground still yields expected end data/format
  • High Rate (RS-422) testing (T0 and in-flight)
  • Redundant data sets
  • bent-pipe Ku throughput
  • recorded on Digital Data Recorder System (DDRS),
    STS provided PGSC with interface board and
    cabling to PDIP
  • 2Mbps

5
STS Data Flow
OIU Orbiter Interface Unit PDI Payload Data
Interleaver PSP Payload Signal Processor POCC
Payload Ops Control Center
  • This segment omitted for test

This segment will be simulated by KSC command
terminals and AMS Ground Support Computers
6
ISS Testing
  • ISS testing will include
  • Power simulation with simulated line loses
  • Data Compatibility Testing
  • LRDL Data (1553)
  • Will test unique design implementation
  • Four protocol engines acting as one RT
  • Each wakes in monitor, first command
    no-response but identifies which PE to go to RT
  • Verify data handling between PLMDM, APS, HRFM,
    and MSFC (EHS) still yields expected end
    data/format at POCC
  • HRDL testing
  • AMS-02 generating 2Mbps continuously
  • AMS-02 Crew Operations Post (ACOP), located in
    Express Rack, records data, maintains continuous
    communication with AMS-02, and provides burst
    capability for downlink of playback data

7
ISS Data Flow
PLMDM- Payload Multiplexer-Demultiplexer APS-
Automated Payload Switch ACOP AMS Crew
Operations Post EHS- Enhanced HOSC Software
This segment will only be simulated with KSC
owned EHS software
8
Progress
  • A FIT Procedures Development TIM was held at KSC
    October 14-15, 2004
  • Substantial progress was made in
  • Development of test objectives
  • Development of procedures list
  • Development of individual procedures
  • Communication of test setup requirements
  • Facility requirements definition
  • Floor Space in SSPF
  • Office Space identified/reserved
  • User Room Location identified/reserved

9
FIT Stand-Alone Procedures
  • AMSFIT - 01 AMSFIT Receiving Inspection
  • AMSFIT - 02 AMS Offline Checkout
  • AMSFIT 03 AMS Preliminary Interface Test
  • AMSCFG A AMS Standard Configuration Procedure
    for STS
  • AMSCFG B AMS Standard Configuration Procedure
    for ISS

10
PTCS Procedures
  • AMSFIT - 04 AMS Ground Segment Commanding Test
  • AMSFIT - 05 AMS PDL Command Test
  • AMSFIT - 06 AMS Housekeeping Data Test
  • AMSFIT - 07 AMS Cold Start and Initialization
    Test
  • AMSFIT - 08 AMS PDL Telemetry Test
  • AMSFIT - 09 AMS HRDL End to End Test
  • AMSFIT - 10 ACOP Operations Test
  • AMSFIT - 11 AMS Nominal Operations Test
  • AMSFIT - 12 AMS Telemetry Recording Session
  • AMSFIT - 13 AMS Telemetry Loading Test

11
CITE/PRCU Procedures
  • CITE Procedures
  • AMSFIT - 14 AMS T-0 1553 and RS422 Operations
    Test
  • AMSFIT - 15 AMS OIU 1553 Operations Test
  • PRCU Procedure
  • AMSFIT - 16 PRCU Check out of the AMS Power
    Distribution System (PDS)

12
Issues/Concerns
  • Procedures development went well, but more work
    needs to be done
  • Umbilical Mechanism Assembly testing
  • ACASS simulator
  • UMA Active/Passive halves
  • Back-up plans developed for Passive UMA (Flight
    or GSE)
  • Power Distribution System Engineering Unit
    schedule is tight
  • Safety Package for test must be worked with Paul
    Kirkpatrick/KSC
  • PRCU testing need procedures from CGS

13
Resolved issues
  • APS and HCOR scheduling issues resolved arrive
    December
  • HRFM availability resolved, delivery 1/15/05
  • KSC Funding issue resolved through January

14
Test Schedule
  • Test 2 weeks (January 5)
  • Internal Pre-ship review/Prelim Constraints
    Review
  • Verify ACASS/UMA setup complete
  • January 12
  • Wednesday during General TIM (tentative)
  • Badging
  • Hardware on-dock
  • Test Readiness Review/Constraints Review (joint)
  • Safety training
  • January 17 Off/off-line activities
  • Internal checkout
  • AMS-02 Hardware configuration in CITE

15
Test Schedule (Continued)
  • January 18-19 CITE Operations
  • January 20
  • 4 hours contingency ops
  • Transfer hardware to PTCS
  • Perform standalone ground segment command test
  • January 21 PTCS Operations begin
  • January 22-23 Weekend (contingency)
  • January 24-27 PTCS Operations (cont.)
  • January 28 PRCU Ops (PDS only)
  • January 29 Packing (if not completed on 28th)
Write a Comment
User Comments (0)
About PowerShow.com