Title: AMS02 Functional Integration Test FIT
1AMS-02 Functional Integration Test (FIT)
- October 21, 2004
- Presenter P. Nemeth/LM
2Objective
- The AMS-02 Functional Integration Test (FIT) is a
risk-mitigation test designed to exercise the
avionics and ground segments of the experiment in
the ISS and STS environments - FIT will utilize the STS and ISS test facilities
within the SSPF - FIT will utilize the AMS-02 front-end avionics
crates on table-tops (not the entire payload) - FIT is designed to verify end-to-end data flow in
a high fidelity development test - All testing is to be performed at KSC, no
requirement for remote data routing (tapes will
be available post-test for further remote testing
as desired) - Target Date for test January 18-28, 2004
3FIT Setup
- FIT testing is broken into two test setups, one
for STS and one for ISS - STS testing in the Cargo Integration Test
Equipment (CITE) Stand - ISS testing in the Payload Test and Checkout
System (PTCS) Facility - AMS-02 Hardware to include
- Qualification Unit J-Crate and JPD
- Low fidelity Model AMS Crew Operations Post
(ACOP) - Engineering Unit Power Distribution System (PDS)
4STS Testing
- STS testing will include
- Power (including T0 for prelaunch and from
Orbiter (APCUs) for in-flight) routed through AMS
Power Distribution front-end - Data Compatibility Testing
- LRDL Data (1553) testing (T0 and in-flight)
- Will test RT4 and RT 28
- Verify data handling between OIU, PDI/PSP, and
Ground still yields expected end data/format - High Rate (RS-422) testing (T0 and in-flight)
- Redundant data sets
- bent-pipe Ku throughput
- recorded on Digital Data Recorder System (DDRS),
STS provided PGSC with interface board and
cabling to PDIP - 2Mbps
5STS Data Flow
OIU Orbiter Interface Unit PDI Payload Data
Interleaver PSP Payload Signal Processor POCC
Payload Ops Control Center
- This segment omitted for test
This segment will be simulated by KSC command
terminals and AMS Ground Support Computers
6ISS Testing
- ISS testing will include
- Power simulation with simulated line loses
- Data Compatibility Testing
- LRDL Data (1553)
- Will test unique design implementation
- Four protocol engines acting as one RT
- Each wakes in monitor, first command
no-response but identifies which PE to go to RT - Verify data handling between PLMDM, APS, HRFM,
and MSFC (EHS) still yields expected end
data/format at POCC - HRDL testing
- AMS-02 generating 2Mbps continuously
- AMS-02 Crew Operations Post (ACOP), located in
Express Rack, records data, maintains continuous
communication with AMS-02, and provides burst
capability for downlink of playback data
7ISS Data Flow
PLMDM- Payload Multiplexer-Demultiplexer APS-
Automated Payload Switch ACOP AMS Crew
Operations Post EHS- Enhanced HOSC Software
This segment will only be simulated with KSC
owned EHS software
8Progress
- A FIT Procedures Development TIM was held at KSC
October 14-15, 2004 - Substantial progress was made in
- Development of test objectives
- Development of procedures list
- Development of individual procedures
- Communication of test setup requirements
- Facility requirements definition
- Floor Space in SSPF
- Office Space identified/reserved
- User Room Location identified/reserved
9FIT Stand-Alone Procedures
- AMSFIT - 01 AMSFIT Receiving Inspection
- AMSFIT - 02 AMS Offline Checkout
- AMSFIT 03 AMS Preliminary Interface Test
- AMSCFG A AMS Standard Configuration Procedure
for STS - AMSCFG B AMS Standard Configuration Procedure
for ISS
10PTCS Procedures
- AMSFIT - 04 AMS Ground Segment Commanding Test
- AMSFIT - 05 AMS PDL Command Test
- AMSFIT - 06 AMS Housekeeping Data Test
- AMSFIT - 07 AMS Cold Start and Initialization
Test - AMSFIT - 08 AMS PDL Telemetry Test
- AMSFIT - 09 AMS HRDL End to End Test
- AMSFIT - 10 ACOP Operations Test
- AMSFIT - 11 AMS Nominal Operations Test
- AMSFIT - 12 AMS Telemetry Recording Session
- AMSFIT - 13 AMS Telemetry Loading Test
11CITE/PRCU Procedures
- CITE Procedures
- AMSFIT - 14 AMS T-0 1553 and RS422 Operations
Test - AMSFIT - 15 AMS OIU 1553 Operations Test
- PRCU Procedure
- AMSFIT - 16 PRCU Check out of the AMS Power
Distribution System (PDS)
12Issues/Concerns
- Procedures development went well, but more work
needs to be done - Umbilical Mechanism Assembly testing
- ACASS simulator
- UMA Active/Passive halves
- Back-up plans developed for Passive UMA (Flight
or GSE) - Power Distribution System Engineering Unit
schedule is tight - Safety Package for test must be worked with Paul
Kirkpatrick/KSC - PRCU testing need procedures from CGS
13Resolved issues
- APS and HCOR scheduling issues resolved arrive
December - HRFM availability resolved, delivery 1/15/05
- KSC Funding issue resolved through January
14Test Schedule
- Test 2 weeks (January 5)
- Internal Pre-ship review/Prelim Constraints
Review - Verify ACASS/UMA setup complete
- January 12
- Wednesday during General TIM (tentative)
- Badging
- Hardware on-dock
- Test Readiness Review/Constraints Review (joint)
- Safety training
- January 17 Off/off-line activities
- Internal checkout
- AMS-02 Hardware configuration in CITE
15Test Schedule (Continued)
- January 18-19 CITE Operations
- January 20
- 4 hours contingency ops
- Transfer hardware to PTCS
- Perform standalone ground segment command test
- January 21 PTCS Operations begin
- January 22-23 Weekend (contingency)
- January 24-27 PTCS Operations (cont.)
- January 28 PRCU Ops (PDS only)
- January 29 Packing (if not completed on 28th)