SCHEDULINGPERT NETWORKING AND LINEAR OPERATIONS - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

SCHEDULINGPERT NETWORKING AND LINEAR OPERATIONS

Description:

Traditionally construction process information is communicated with paper ... Construction Group at the NIST Gaithersburg, MD is developing this concept. ... – PowerPoint PPT presentation

Number of Views:34
Avg rating:3.0/5.0
Slides: 21
Provided by: KellyNW
Category:

less

Transcript and Presenter's Notes

Title: SCHEDULINGPERT NETWORKING AND LINEAR OPERATIONS


1
SCHEDULING-PERT NETWORKING AND LINEAR OPERATIONS
CHAPTER - 8
VRML Model of NIST Research Facility Emission
Control System
VRML Excavator, Tower Crane and Dump Truck
2
THE NEED
  • Traditionally construction process information is
    communicated with paper documents and 2D CAD
    drawings
  • Recently, the industry has embraced web-based
    technologies, but construction still uses
    document-based models.
  • It is believed that transition model-based
    information can be done through web-based 3D
    models.
  • Moreover, there is a need to easily model
    structures to be used in a web-based user
    interface.

3
THE TECHNOLOGY
  • The applicability of the VRML is being
    investigated for visualizing construction
    activities at a site and creating an advanced
    web-based 3D user to construction process
    information.
  • The Computer-Integrated Construction Group at the
    NIST Gaithersburg, MD is developing this concept.
  • These interfaces are based on web-based 3D
    visualizations of a model.

4
INTRODUCTION
  • Acquisition of Bar Charts and CPM
  • PERT addresses variability of project duration
  • Variability is defined in terms of three
    estimates
  • Calculation of the expected duration time (te)
  • Definition of normal distribution
  • Standard deviation and variance
  • Calculation of longest path and project duration
    using te
  • Probability distribution longest path of te
    values as a mean of normal distribution

5
Figure 8.1 Selected Areas under the Normal
Distributed Curve
6
AN EXAMPLE OF PERT NETWORK
  • Fig. 8.2 and table 8.1
  • Calculation of expected duration, variance for
    each activity, the standard deviation
  • What is the probability that the project can be
    completed in N days?
  • What is the probability that the project can be
    completed in 19 days? (see fig. 8.3, and example

ta4tmtb
For instance for Activity 7
42813
45
7.5
te




6
6
6




2
9
2
(tb-ta)
(13-4)
a2




2.25
6
6
6
7
Table 8.1 Three Estimate Values and Calculated
Values for Each Activity
8
Figure 8.2 Small PERT Network
Figure 8.3 Normal Distribution of Total Project
Durations for Small PERT Network
9
PERT SHORTCOMINGS
  • PERT results are too optimistic
  • Assumption that duration is most probable value
    is not accurate
  • PERT underestimates the duration, the cause is
    called Merge Event Bias
  • One solution to the Difficulties is to use Monte
    Carlo Simulation

Figure 8.4 Merge Event Bias
10
LINEAR CONSTRUCTION OPERATIONS
  • Often construction sites have linear properties
    that influence the production sequence. (example
    road construction)
  • The required sequentiality leads to the Train
    effect.
  • That is, a section must be complete 5-in concrete
    before preceding to 9-in concrete. Therefore,
    the section can be thought of as a train or
    parade of work that must pass each station
    represented by the six construction process.
  • Many types of project exhibit this kind of rigid
    work sequence.
  • Examples
  • A high-rise building, each floor to pass though a
    set of operations
  • Tunnels are worked in sections
  • Pipeline work

11
Figure 8.5 Road Project Divided Into 14 Sections
12
PRODUCTION CURVES
  • Bar charts and network schedules provide only
    limited information when modeling linear
    operations and projects.
  • They do not reflect production rate or speed with
    which section are processed.
  • First unit delay occurs due to mobilization.
  • Near completion, production rate declines due to
    demobilization.
  • Max production is during mid periods of the
    process duration
  • This leads to a production curve with the shape
    of a lazy S. (Fig. 8.6)
  • The slope is flat at the beginning and the end,
    but steep in the middle.
  • The slope of the curve is the production rate.
  • These curves are called as time-distance,
    time-quality or velocity diagrams. (Fig. 8.7)
  • The slope represents the number of unit produced
    over a given time increment.
  • The slope of the curve, therefore represents the
    number of units produces over a given increment.
    This is the rate of production.
  • Unbalanced production roles. (Fig. 8.9)
  • Prevent work stoppage (Continuity of work)
  • One way to avoid this is to control production in
    each process so that sloped of the curves are
    parallel.

13
Figure 8.6 Production Curve
Figure 8.7 Velocity Diagrams for a Road
Construction Project
14
Figure 8.8 Planned Status Construction at Week 12
Figure 8.9 Unbalanced Process Production Rated
15
LINE-OF-BALANCED CONCEPTS
  • LOB is a graphical method for production control
    integrating barcharting and production curve
    concepts
  • LOC serves two fundamental purposes
  • To control Production
  • To act as a Project Management Aid
  • Each objective is interrelated through 4 LOB
    elements
  • The objective chart
  • The program chart
  • The progress chart
  • The comparison

16
Figure 8.10 Objective Chart
Figure 8.11 Program Chart with Lead Time in Work
Days
17
Figure 8.12 Progress Chart
Figure 8.13 Progress Chart with Line of Balance
18
Figure 8.15 Program Chart and Objective Chart
Figure 8.14 Schematic of Floor Cycle Work Tasks
19
Figure 8.16 Enlarges Projection of Program Chart
onto Objective Chart
Figure 8.17 Line of Balance for Week 5
20
8.7 LOB APPLIED TO CONSTRUCTION
  • To illustrate the use of LOB in a construction
    context, consider a high-rise building in which
    repetitive activity sequences are a part of the
    floor-to-floor operation.
  • Each floor consists of four sections (A, B, C,
    and D)
  • Each floor section must be processes through the
    following work activities (1) erect forms, (2)
    Placing reinforcement, (3) Place concrete, (4)
    Dismantle forms, (5) Place curtain wall (exterior
    façade), (6) Place window.
  • Figure 8-14 shows a schematic of the status of
    activities at a given point in time.
  • The diagram in figure 8-15 shows the LOB
    objective chart for a 10-story building. The
    program chart for a typical section is shown
    above the objective chart.
  • A diagram of Projection is shown in Figure 8.16
  • The LOB values can be calculated by determining
    the slop relating horizontal distance (Lead time
    to vertical distance (required sections)).
Write a Comment
User Comments (0)
About PowerShow.com