TL 9000 Measurements Auditing the Validation Process - PowerPoint PPT Presentation

1 / 10
About This Presentation
Title:

TL 9000 Measurements Auditing the Validation Process

Description:

TL 9000 Program Manager / Lead Auditor. T V S D America, Inc. T V S D AG. 2. Focus ... DCR's indicating zero for NPR / SPR (especially for several consecutive months) ... – PowerPoint PPT presentation

Number of Views:397
Avg rating:3.0/5.0
Slides: 11
Provided by: jerryw2
Category:

less

Transcript and Presenter's Notes

Title: TL 9000 Measurements Auditing the Validation Process


1
TL 9000 MeasurementsAuditing the Validation
Process
  • Jerry Wilson
  • TL 9000 Program Manager / Lead Auditor
  • TÃœV SÃœD America, Inc.

2
Focus
  • There are 4 basic components to the TL 9000
    measurements process as shown below. Today we
    will focus on the Validate step and review a few
    of the things that are verified during an audit
    of this process step.
  • Data Sources
  • Customer
  • Supplier
  • Internal system

3
Simplified Process Flow
Inputs
Process
Validate
Y
Collect
Analyze
N
Correct Data
Outputs
  • Report to
  • MRS
  • Organization
  • Customers (if required)

4
INPUTS
  • The Auditor must gain an understanding of
  • the product categories being reported
  • the inputs
  • What customers or suppliers provide data?
  • What data do they supply?
  • The collection methodologies for each
  • How do they supply it?

5
INPUTS
  • The Auditor must assess
  • the status of any N/A or Exempt and ensure
    acceptability
  • consistency with scope of registration
  • Example All Common and Hardware measurements are
    collected if the organizations scope is H
  • Review corrective actions if organization has
    previously been on suspended or probation
    status(ref Alert 06-003A)

6
PROCESS
  • Look for
  • documented validation process (measurements
    handbook 3.5.2. a))
  • responsibilities for review and approval
  • handling of invalid data
  • access to the source data is available for
    validation
  • verification that the output from any software
    application or spreadsheet has been verified
    (7.1.C.4 Tools Management)
  • ensure correct calculations and proper use of the
    counting and exclusion rules
  • Sample calculations, counting, and exclusion
    rules
  • Ensure that validation personnel are trained and
    understand the counting rules

7
PROCESS CHANGE
  • Look for
  • Evidence that when changes are made to software
    applications / spreadsheets used to consolidate
    the information that there is verification that
    the output is acceptable (7.1.C.4 Tools
    Management)
  • verify correct calculations
  • verify data filters are working correctly
    (counting rules vs. exclusions)

8
OUTPUT
  • Look for
  • evidence data validation occurs prior to each
    reporting period
  • acceptable DCRs for each category
  • sample the summary data and comparing to DCRs

9
Indicators
  • Possible Indicators
  • Management Reviews show consistent poor results
  • DCRs indicating zero for NPR / SPR (especially
    for several consecutive months)
  • may indicate that the linkage between the
    reporting method and collection system is broken
  • Large variations in quantities reported
  • Issues related to the date filters orcounting
    rules