Bill Headley - PowerPoint PPT Presentation

1 / 27
About This Presentation
Title:

Bill Headley

Description:

Bill Headley – PowerPoint PPT presentation

Number of Views:47
Avg rating:3.0/5.0
Slides: 28
Provided by: Head1
Category:
Tags: bill | headley | qrz

less

Transcript and Presenter's Notes

Title: Bill Headley


1
Bill Headley Project Director

2
University Hospitalof North Durham1st Wave
Scheme96m3 year programmeSigned in
1998Completed in 200127 year contract
3
Transforming the Newcastle Hospitals
  • Largest health project in North East -
    304million
  • Project Agreement signed - 27th April 2005
  • over 210million expended to date by contractor
  • 8 year overall programme (on RVI site)
  • RVI Scheme is 60,000m2 / Freeman Scheme is
    21,000m2
  • 35 year contract

4
RVI AERIAL VIEW Pre-Contract
5
RVI AERIAL VIEW Completed Scheme
6
RVI AERIAL VIEW November 2007
7
RVI - Main entrance
8
RVI - Plaza
9
(No Transcript)
10
(No Transcript)
11
Freeman Hospital - View From Level 2
12
(No Transcript)
13
(No Transcript)
14
PFI in Health
  • Pre 1994
  • Prisons/Roads
  • 1994
  • Conservative initiative
  • all major health schemes to be tested
  • market immature
  • no guidance
  • Reinforced by Labour in 1996
  • 1st deal signed c 1997
  • November 2007
  • 69 Operational Schemes
  • 26 in construction
  • 8 in procurement

15
Why PFI ?
  • NHS Infrastructure in need of significant
    investment
  • NHS history of poor management of capital schemes
  • time and cost overruns
  • No public money
  • Need to consider long term investment (ie whole
    life costs)
  • NHS to concentrate on healthcare delivery

16
PFI PRINCIPLES
  • Private Sector Design, Build, Finance and Operate
    Hospitals
  • Design and Build
  • NHS provide output specification
  • Private Sector to deliver clinical functionality
  • Finance
  • Bank/Bond funding over a period of up to 35 years
  • Operate
  • Provide Facilities Management services
  • Soft FM services optional (Catering Domestics
    etc)
  • Staff transfer to Private Sector
  • Trust Continues to run Clinical Services

17
Risk
  • Risk should lie with party best able to manage
    it
  • Construction
  • Private Sector assumes all building risks once
    layout etc agreed with trust
  • NHS doesnt pay anything until completed
    (incentivises private sector)
  • Facilities Management
  • Contract is linked to Performance and
    Availability
  • Buildings to be maintained to high standard over
  • life of contract
  • Balance Sheet Treatment

18
One size doesnt fit all
19
Issues for Audit
  • Governance / Project Management
  • Value for Money
  • Balance Sheet Treatment
  • Change Control / Variations
  • Performance Monitoring

20
Variations (Change Cost)
  • During Construction
  • Significant contractor mark up from Contractor
    and SPV
  • Need to re run the Financial Model
  • Lifecycle Adviser costs
  • Technical Adviser costs
  • Adds to Unitary Payment (Lifecycle and FM costs)
  • or
  • Trust funds via Capital Programme
  • Operational Phase
  • Agreed schedule of rates for minor works

21
Payment Mechanism
  • Private Sector Incentivised to Perform
  • Service Failures (Specific)
  • Service Failures Weighted according to severity
    of incident
  • - broken door handle in office
  • -burst water main in operating theatre
  • Areas Weighted according to importance to Trust
  • office - low
  • operating theatre - high
  • Response and Rectification Times also linked to
    importance of area
  • Quality Failures (General non compliance)
  • Identification badges
  • Non compliance with Good Industry Practice

22
Payment Mechanism
  • Financial Penalties
  • Cannot exceed total Unitary Payment made
  • Penalty Points
  • Rolling period
  • Early Warning
  • Ultimate means of replacing service provider

23
(No Transcript)
24
Failure Events
25
Quality Failures
26
Payment Mechanism Calculation
27
Does PFI Deliver?
?
  • Whole Life consideration
  • Constructional expertise introduced earlier in
    design process
  • Innovation in FM service delivery
  • Innovative Design
  • Faster project delivery
  • Risk transfer
  • Value for Money

X
?
?
Write a Comment
User Comments (0)
About PowerShow.com