Title: Chornobyl, Ukraine
1Chornobyl, Ukraine
April 15,1998
2Chornobyl Time Line
- 1986 -- Chornobyl Disaster
- Alerted world to safety threat of Soviet-designed
reactors - 1991 -- Soviet Union Breakup
- Provided opportunity for cooperative safety
activities - 1992 -- Lisbon Initiative
- Multiple bilateral agreements for cooperative
safety projects - Fire at Chornobyl
- Temporary closure of Unit 2
- 1994 --
- Jan. -- No assistance to Chornobyl (3 units
continue to operate) - April -- Lash assumes NE Director role
- Oct. -- PNNL accepts lead role for INSP
IG98040040.2
3Chornobyl Time Line (Cont.)
- 1995 --
- May
- Presidential endorsement of bilateral agreement
- Creation of Chornobyl Center
- Safety upgrades at Unit 3
- July
- Agreements on specific safety upgrades
- December
- G-7/Ukraine MOU for Chornobyl Closure by 2000
- Fix Shelter
- Final completion of K2-R4
- Modernization of power industry
IG98040040.3
4Chornobyl Time Line (Cont.)
- 1996
- April -- US Delegation tours shelter
- Safety and health conditions for workers
intolerable - May
- Technical team performs Shelter needs assessment
- International Shelter Project initiated
- August - Bilateral projects initiated at Shelter
- Hanford experts
- October - International Shelter Study Report
completed - Accepted by G-7 and Ukraine in December
IG98040040.4
5Chornobyl Time Line (Cont.)
- 1997
- January - SIP initiated
- May - SIP completed
- 760 million/ 8-year project
- July - G-7 pledges 300 million
- Dedication of Chornobyl Center in Slavutych
- Nov/Dec - Kutchma/Gore Pledging Conference In New
York - 87 million additional pledged
- 22 countries now participating
IG98040040.5
6Chornobyl Time Line (Cont.)
- 1998
- December - SIP RFPs issued by ChNPP
- February - Chornobyl Center facility completed
- May - Bechtel/EDF/Battelle win competitive bid
IG98040040.6
7The Chornobyl Accident
- April 26, 1986, Ukraine's ChNPP Unit 4 reactor
sustained a tremendous surge in reactor power - Ruptured the reactor's fuel rods and pressure
tubes - Steam explosion lifted the reactor core and the
2,000-ton shielding block 14 m (45 ft) - Explosion destroyed 3/4 of reactor building,
spewed hot fragments of graphite and reactor fuel
from the core, starting 30 fires in nearby
buildings - Radioactive dust/gases (50 megacuries)
- Contaminated gt 60,000 miles2 of Ukraine, Belarus,
and Russia (State of Washington 68,000 square
miles)
IG98040040.7
8Chornobyl Accident - April 1986
- 31 people died as a result of intense radiation
exposure from the Unit 4 accident - All people (about 116,000) within a 30-km zone
around the plant were evacuated and relocated - The town of Pripyat was closed and citizens
working at the plant were relocated to Slavutych - Completed in 1987
- 40 km from plant
- Population 26,000
IG98040040.8
9Chornobyl Accident - April 1986
- Radiation Deposition
- Radioactive release was 200 times greater than
that of Hiroshima and Nagasaki combined - Contaminated areas Belarus - 25, Ukraine - 5,
and Russia - 0.5. - The contaminated area of Ukraine and Belarus is
about 61,780 square miles- the size of England,
Wales, and Northern Ireland combined - Crops, milk, and livestock were destroyed in
Austria, Hungary, Germany, Poland, and Nordic
countries - More than 400,000 emergency personnel worked to
alleviate the immediate consequences of the
accident - Ukraine has spent 12of National budget since
1991 on Chornobyl-related activities
IG98040040.9
10Chornobyl Accident - April 1986
- Disaster continued to release radioisotopes to
the environment - Enclosed ruined reactor with 20-story steel and
concrete "shelter built in 7 months - Shelter has questionable foundation and shows
cracks/holes - Fuel corium is degrading to radioactive,
respirable dust - Shelter is unstable and could collapse, injuring
workers and spreading radioactive dust - Total radionuclide activity still contained by
shelter is substantially reduced today
IG98040040.10
11Improve Nuclear Safety in FSU
- Mission - reduce risks at Soviet-designed nuclear
power plants and assist host countries in
developing sustainable internationally accepted
safety practices. - Range of Activities
- Operation Safety
- Emergency Operating Instructions, training,
simulators, safety maintenance, nondestructive
evaluation - Safety Systems
- Safety parameter display system, fire safety,
confinement, emergency feedwater - Safety Analysis
- Training, tools, evaluation
- Regulatory and Institution
- Liabilities, separate authorities
IG98040040.11
12Solving Problems of the Chornobyl Shelter
- A team of Ukrainian and international experts
proposed measures to prevent shelter collapse and
contain reactor dust - May 1997, the international team proposed the
Shelter Implementation Plan - SIP estimated at 760 million over eight-years
- To support developing the Shelter Implementation
Plan, the U.S. team, led by the Pacific Northwest
National Laboratory, provided substantial
technical support and led development of the
plan's cost and schedule estimates.
IG98040040.12
13Solving Problems of the Chornobyl Shelter
- June 1997, Ukraine and the G-7 nations approved
the Shelter Implementation Plan - G-7 selected EBRD to manage project finances
hire SIP Project Management Unit (PMU) contractor
- EBRD selected Chornobyl plant for PMU and
required a Western PMU Consultant to help them
succeed - Ukraine selected the team, composed of Bechtel,
Electricité de France and Battelle - Negotiations continue today, with focus on
nuclear liability issues - The final contract likely this week
IG98040040.13
14Liability issues of doing work at Chornobyl -
Background
- Liability problems are not new INSP encountered
problems convincing United States industry to
work in the former Soviet Union, because of
concerns about liability - Pacific Northwest National Laboratory had to
develop some international nuclear liability
expertise - Our experience contracting at Chornobyl accents
the importance of this issue for all firms doing
business in the FSU - Clear liability understandings are essential for
the Chornobyl SIP, if the world is to succeed in
stabilizing this damaged plant
IG98040040.14
15Liability issues of doing work at Chornobyl - The
Risk
- Assessments have been performed
- The Shelter may collapse in an earthquake or high
wind, or due to contractor errors while
stabilizing it - Intermediate events identified as common stack
failure and common separation wall failure - A nuclear explosion of Unit 3, based on
propagation of a Shelter collapse, is incredible
(lt 10-6). It was determined that Unit 3 can be
safely shut down after collapse of vent stack or
the separation wall - The safety of workers in the facility and people
in the near vicinity would be at hazard by a
Shelter collapse
IG98040040.15
16Liability issues of doing work at Chornobyl -
Background
- Elements necessary to limit third-party nuclear
liability risk for a United States company doing
business in a foreign country - Domestic Liability Legislation
- Transboundary Victims Liability Treaty Relations
- U.S. Treaty Relations
IG98040040.16
17Liability issues of doing work at Chornobyl -
Background
- INSP helped DOE/DOS sponsor the Convention on
Supplementary Compensation for Nuclear Damage,
held in Vienna on September 29, 1997. - Secretary of Energy Peña signed the Convention
for the United States on that date, subject to
congressional ratification. Ukraine also signed. - The Senate Foreign Relations Committee sent the
Convention on Nuclear Safety to the full Senate
in early April, for its advice and consent to
ratification. - The Convention on Nuclear Safety will be followed
immediately by the Convention on Supplementary
Compensation. - Approval of these conventions is key to opening
business in Ukraine and elsewhere in the former
Soviet Union. - Your (nuclear industry) support is critical to
timely congressional approval.
IG98040040.17
18Chornobyl Centerfor Nuclear Safety, Radioactive
Waste and Radioecology
- Socio-Economic Impacts in Slavutych
- Education Exchange between Slavutych, Ukraine and
Richland, Washington - Student optimism
- Future for jobs
- Public Council for Economic Development
- Called for in Slavuytch Social Impact Plan
- Democratic Institution
- DOE may convene conference on skills needed for
SIP projects
IG98040040.18
19(No Transcript)
20Chornobyl Centerfor Nuclear Safety, Radioactive
Waste and Radioecology
- Shelter Visit Feb. 25, 1998
- U.S. team led by Ray Hunter and John Wagoner
- Current Status of SIP pledges
- 300M from G-7
- 50M from Ukraine
- 37M from Pledging Conference
- Heat Plant
- Size - 290 MWT, Project completion - October 1999
- Cost - 18M (US), 36M (Ukraine)
- Critical to ensuring closure by year 2000
IG98040040.20
21Improve Nuclear Safety In FSU National/Internation
al Participants
U.S. Department of Energy Office of Nuclear
Energy, Science and Technology
U.S. Nuclear Regulatory Commission
U.S. Agency for International Development
Policy Funding
Russia Ukraine Bulgaria Czech Republic
Hungary Kazakhstan Lithuania Slovakia
Armenia
Coordination with G-7 and International
Financial Institutions
Participating Countries
Program Implementation
Lead Technical and Administrative Support Pacific
Northwest National Laboratory
Host Country Organizations and Nuclear Power
Plants
U.S. Industrial Organization
U.S. National Laboratories
IG98040040.21
22Participating Organizations
National Laboratories
Department of Energy Department of State Nuclear
Regulatory Commission Agency for International
Development
Pacific Northwest National Laboratory Argonne
National Laboratory Brookhaven National
Laboratory Sandia National Laboratory Idaho
National Engineering Laboratory
Private Industry
Honeywell International Management Development
Corp. Mariner Engineering, Inc. Matrix
International Logistics, Inc. Orion/Atlantic Path
Training Corp. Promatec Raytheon Engineers
Constructors, Inc.
ABB-CE American Technologies, Inc. Babcock
Wilcox Bechtel Power Corp. Burns Roe Control
Data Duke Engineering Services Ebasco General
Physics Corp. Gilbert/Commonwealth
Corp. Halliburton NUS Corp.
S3 Technologies Science Application International
Corp. Scientech Sierra Nuclear Corp. Stone and
Webster, Inc. Sonalysts, Inc. Taurus Westinghouse
Electric Co.
IG98040040.22
23Improve Nuclear Safety in FSU65 Reactors at 20
Nuclear Power Plants in 8 Countries
- Problems
- Inadequate operating procedures and training
- Design deficiencies
- Lack of infrastructure to sustain safe operation
- Inadequate nuclear regulatory authority
Percent of Electricity from Nuclear Power
80
83
60
45
44
42
41
37
40
20
13
20
0
Russia
Czech Republic
Ukraine
Bulgaria
Hungary
Slovakia
Lithuania
Armenia
IG98040040.23