Description:

The order of the tasks (recipe) ... The weight of the recipe-arcs can be changed ... Based on the cycle search algorithm. It can reduce the size of the search tree ... – PowerPoint PPT presentation

Number of Views:66
Avg rating:3.0/5.0
Slides: 20
Provided by: holczing
Category:

less

Transcript and Presenter's Notes

Title: Sgraph Framework in Batch Process Scheduling


1
S-graph Framework in Batch Process Scheduling
  • T. Holczinger1, R. Adonyi1, G. Biros1,
  • J. Romero2, L. Puigjaner2, F. Friedler1
  • 1Department of Computer Science, University of
    Veszprém, Veszprém, Egyetem u. 10., H-8200,
    Hungary
  • 2Department of Chemical Engineering, Universitat
    Politècnica de Catalunya, Barcelona, Av. Diagonal
    647, E-08028
  • CAPE Forum 2004
  • Veszprem

2
Problem definition
  • Given
  • The order of the tasks (recipe)
  • The set of plausible equipment units for each
    task (with operation times)
  • Necessary amount of products
  • Storage policy
  • Timing data
  • Aim
  • The optimal order of the tasks
  • Using the given resources

3
Conventional representation
  • Notations
  • PT processing time
  • Eq. equipment unit

4
Graph representation
5
Recipe
  • Directed graph Products A, B, and C

6
S-graph representation
  • Directed graph
  • The changeovers are denoted by arcs

7
NIS vs. UIS
Unlimited Intermediate Storage
Non Intermediate Storage
8
Schedule-graph
  • An S-graph is a schedule-graph, if
  • the equipment-task assignment and
  • the operation order of the tasks are given
    (schedule-arc)

9
Basic algorithm
  • Branch and bound framework
  • Extension of the recipe-graph with schedule-arcs
    according to the rules
  • Introduction of schedule-arcs
  • Identical set of nodes
  • The weight of the recipe-arcs can be changed
  • The number of the possible extensions are finite
    ? the algorithm is finite

10
More than one batch per product
  • Considering each batch as an individual product
    is not efficient enough

11
Single equipment unit for a task
12
Optional equipment units for a task with
identical processing time
13
Acceleration tools
  • Cycle prediction
  • To predict that a subgraph has no feasible
    solution
  • Based on the cycle search algorithm
  • It can reduce the size of the search tree
  • LP model for sharpening the lower bound

14
Illustrative example
S-graph
Search tree
S-graph
Search tree
1
2
3
4
2
15
Illustrative example
S-graph
Search tree
1
3
4
2
5
1
3
4
2
6
6
5
16
Illustrative example search tree
1
3
4
2
6
5
1
1
7
3
4
2
2
3
4
5
6
5
6
7
8
9
10
7
11
12
13
With cycle prediction
Without cycle prediction
17
Industrial size scheduling problem
  • 123 products
  • 31 different base products
  • 13 possible pack sizes from 5 to 20000 liters
  • Necessary amount is from 5 to 12000 tons for a
    year (solved the production of a week)
  • Batch size is 6 tons for each mixer
  • Two types of tank
  • T901 T922 (8 tons)
  • T951 T968 (15 tons)
  • 120 minutes minimum residence time for
    intermediate products in a tank (bubbling)

18
Parameters of the problem
  • Number of products 123
  • Total number of batches 389
  • Number of equipment units
  • Mixer 5 (batch type equipment unit)
  • Tank 40
  • Packing line 26 (continuous type equipment
    unit)
  • Running time on PC (1 GHz) is less than 4 minutes
    and the optimality gap is 2.6

19
Further information
  • Publications
  • E. Sanmartí, F. Friedler, and L. Puigjaner,
    Combinatorial technique for short term scheduling
    of multipurpose batch plants based on
    schedule-graph representation, Comput. Chem.
    Engng. 22 (1998)
  • E. Sanmartí, L. Puigjaner, T. Holczinger, and F.
    Friedler, Combinatorial framework for effective
    scheduling of multipurpose batch plants, AIChE J.
    48 (2002)
  • Holczinger, T., J. Romero, L. Puigjaner, and F.
    Friedler, Scheduling of Multipurpose Batch
    Processes with Multiple Batches of the Products,
    Hung. J. Ind. Chem., 30, 305-312 (2002)
  • Demonstration programs
  • http//www.dcs.vein.hu/CAPO/demo/sch/