Title: LArTPC Detector Costs
1LArTPC Detector Costs
- Context
- History
- Next (perhaps) steps
2ContextMaking the Ultimate Step for Large
Liquid Argon TPC Detectors
- What is the penultimate step?
David Finley to LArTPC Group Meeting Fermilab
June 12, 2006
3(No Transcript)
4The Ultimate Step
- Assumptions for beginning the ultimate step
- A timely, cutting edge physics justification
- Examples may be Neutrino oscillations, proton
decay, neutrinoless double beta decay,
supernovae, etc - A project for a 50 to 100 kton TPC liquid argon
detector - An international collaboration that agrees
detectors will be in one or more of these
locations - Under rock/dirt in Italy
- Under rock/dirt in the Western US
- On the surface in the NuMI beam (or anywhere else
on the planet)
5The Penultimate Step
- Making the penultimate step assumes completion
of - A compelling physics case for the ultimate step
- In the context of a globally coordinated neutrino
physics program, which in turn requires - A functional international collaboration in place
with possible, but unapproved, funding sources
for the ultimate detector, and - A physics case for the penultimate step would be
a BIG bonus - A credible schedule, which requires (see next
slide) - A credible cost estimate, which requires (see
next slide) - A compelling demonstration of the
engineering/technology and the experimental
physics capability for the ultimate detector,
probably with the construction and operation of a
penultimate detector as well as the physics
analysis of data provided by it.
6The Penultimate Step
- Making the penultimate step requires completion
of - A compelling physics case for the ultimate step
(see previous slide) - A credible schedule, which requires
- Time for peer reviews, lab reviews, and
government approvals - Completion of RD for the engineering/technology
and physics capability required for the ultimate
detector - Time for construction and operation of the
ultimate detector - A credible cost estimate, which requires
- A technical design to accomplish the physics
- A credible schedule (see above)
- Engineers and project management techniques
- A compelling demonstration (see previous slide)
7Penultimate thoughts from Hans
- Thanks, David.
- Very well said.
-
- Unfortunately I did not receive your last slide
which must say something like -
- "The Penultimate Detector
- Requires
- --finding a physics justification for a (1 to 3
kton ?) detector - --implies defining the location, rates, physics
expectation - --A credible schedule
- --A credible cost estimate
- -- A credible collaboration"
-
- Hans
- email to lar_at_fnal June 8, 2006
-
8Now for costs
- A credible cost estimate which requires
- A technical design to accomplish the physics
- A credible schedule
- Engineers and project management techniques
- And the cost estimate will be used to
- Identify large costs (and cost uncertainties)
which might be reduced by - technical RD including more detailed engineering
designs or - getting information which is closer to firm
quotes from vendors - Increase costs to reduce risk or improve
technical performance or to advance/stretch the
schedule (for whatever reasons) - Identify all tasks (i.e., costs) by using a WBS
(see later slide) - Compare to other techniques and approaches (e.g.
Water Cherenkov, surface vs. below ground, etc.)
9History What has been done?
- ICARUS
- Rumored cost is 20M for 1.2 kton
- Math gives 17M/kton or 830M/50 kton
- And math gives a factor of ten cheaper would be
83M/50kton - This is an experienced based cost estimate.
10History What has been done?
- ICARUS
- Rumored cost is 20M for 1.2 kton
- Math gives 17M/kton or 830M/50 kton
- And math gives a factor of ten cheaper would be
83M/50kton - This is an experienced based cost estimate.
- LArTPC NuSAG submission
- 57.45M for 15 kton
- Math gives 3.8M/kton or 190M/50kton
- This is not an experienced based cost estimate.
- NuSAG response
- See next slide
11NuSAG February 28, 2006
12NuSAG Submission Costs
15 kton
1350 kton estimate
1450 kton estimate
1550 kton estimate
16NuSAG LArTPC Cost Pie
15 kton
17End of History WBS here
18Schedule
- The LArTPC schedule in the NuSAG submission
allowed our Director a moment of levity. - The DOE approval process was not included.
19(No Transcript)
20Schedule in NuSAG Submission
21 Next (perhaps) cost steps - 1
- Methodology and archeology
- Include project management items so that the
Directorate can compare LArTPC costs to other
DOE-costed competitors for the funds. - Get ICARUS costs directly from INFN
- and relate Italian cost accounting to DOE cost
accounting - so one can better specify what NuSAG meant by
about an order of magnitude less - OR NOT because why is a relative cost
improvement relevant? - Is it not the TOTAL cost to various taxpayers
that is important?
22 Next (perhaps) cost steps - 2
- What does cost mean? Does it mean
- DOE defensible or
- Engineering credible or
- Just more physicist scaling?
- Or some combination?
- Specific design choices
- 3 kton three 15 kton ten 3 kton 50 kton
- what else? and what experimental requirements
drive these choices?
23 Next (perhaps) cost steps - 3
- Next on the hit list for cost
- Is it not obvious that there are added costs for
the many small approach? - More argon (see next slide) and more steel.
- And what exactly does fiducial volume mean
anyway? - And what does the increased cost buy?
- Reduction in risk by having shorter wires how
short is short enough? - Obvious control of systematics
- similar to Braidwood Reactor Neutrino design with
multiple detectors - how well does a single large detector control
systematics? - Staging
24All the argon will be bought, but how much is
used for physics?
From Pushka Spring 2005
Radiation length is 14cm
25 Next (perhaps) cost steps - 4
- The 3 kton penultimate PHYSICS detector needs
its TPC specified - Strike a balance between engineering
demonstration for the ultimate detector and
reducing risk to the physics experiment - This may be harder to do than it may seem.
- All credible costs require Engineering support
from PPD. - Is this actually true? Can the engineering not
be bought? with US dollars and/or with Euros?
26Todays Final Ultimate Questions
- Is there any chance at all that
Europe/INFN/Japan/Asia/et al would cost share
on the Ultimate Detector in the US? - Or will three different detectors, one in each
region, be the obvious thing to do because - ultimate LArTPCs will become the obvious
detector for several obvious physics
experiments - for less than (a mere) 0.5B each
- over the next 20 years or so?