Title: BeamBased Alignment Results
1Beam-Based Alignment Results
- Henrik Loos, for the LCLS Commissioning Team
2Undulator Trajectory Requirements
- Beam through undulator rms 2 µm per gain length
- Undulator with 33 segments total 100 m
- Not possible with conventional alignment
- Use beam based alignment using set of different
energies - RF BPM resolution lt 1 µm
3Undulator Configuration
- Undulator, Quad, BPM, BFW move with girder
- Beam Finder Wire (BFW) retractable
- Horizontal translation of undulator
- Complete retract (80 mm)
- Undulator K adjustment ( 5 mm)
4Beam Based Alignment Principle
- BPM offsets unknown
- Magnetic fields (earth, quad kicks, etc.) unknown
- Correct field integrals with quad offsets or
correctors for dispersion free trajectory at BPM
position - Trajectory between BPMs remains unknown
- Measure trajectory at different energies to
extrapolate to straight line at infinite energy - Fixed undulator quad fields
- BPM position is BPM offset at infinite energy
5BBA Measurement Schematic
?b1
?b3
?b2
?b0
?b0
?q1
?q3
?q2
E2
x,x
E1
?y1
?y3
?y2
?y0
?y4
BPM Offsets ?bi Quad Offsets ?qi
E1 lt E2
6BBA Procedure
- Model beam position (yj) at BPMs as function of
initial launch at 1st BPM (xi), quad offsets
(?qi), BPM offsets (?bi) - y Rx Rq Rb x ?q ?b
- Rxj Rj1,12
- Rqj R1,jend - R1jbeg Riltj,jend - Riltj,j 0
011 - Rb -I
- Fit solution for y arbitrary to adding linear
function to quad and BPM offsets - Add constraint equations for quad or BPM offsets
- 0 Si ?qi and Si zi ?qi for linear quad offset
constraint - 0 ?qi for minimum quad offset constraint
7BBA Implementation
- Setup accelerator for one energy
- Calculate response matrix for this energy
- Measure N orbits at this energy and average
- Repeat for all energies
- Generate final matrix with separate launch
parameters for each energy and selected
constraints - Fit quad and BPM offsets and implement
- Repeat BBA procedure
8BBA Simulation
Simulation Orbits
Simulation Fit Lin. Quad
9BBA Results 1st Run
- First test Energy range only 10 13.64 GeV
- 50 orbits each, averaged
- BPMs not well calibrated
- Large oscillation in fit of quad offset, 1mm
error bar - Assume BPM offset worse than quad offset
- Apply instead constraint for minimal quad offset
- Initial position rms 300 µm
Measured Orbit
10BBA Results 1st Run
Fit with Linear Quad Constraint
Fit with Min. Quad Constraint
Applied this to BPM offsets
11BBA Results 2nd Run
- Energy range now 7 13.64 GeV
- Still large 1 mm oscillation on quad offset fit
- Apply relaxed minimum quad constraint, 100 µm
error bar - Orbits very similar after correction
- Position rms 50 µm after
Measured Orbit
12BBA Results 2nd Run
Fit with Min Quad Scale 20
Measured Orbit after Correction
13BBA Results 3rd Run
Measured Orbit 4.3 13.64 GeV
Fit with Linear Quad Constraint
14BBA Results 3rd Run
Measured Orbit 4th Iteration
Fit with Linear Quad Constraint
Position rms 2 10 µm
Offset Error Bar 10 µm
15BBA Results Best Orbit
- Carefully calibrated BPMs
- Energy range 4.3 13.64 GeV
- 4 different energies
- Undulator launch feedback on
- Average position rms 1 2 µm
- Betatron jitter 20 µm
16BBA Results Girder Bump Test
58um bump _at_ 13.7 GeV -58um BPM offset
-48um bump _at_ 13.7 GeV
BBA procedure finds both quad offsets and BPM
offsets
17Typical BBA After Several Months
Observe mostly changes in BPM offsets 10 30um
Some quad BPM offsets in end region of
undulator from incremental orbit corrections
(retracting undulators, changing of taper)
18Quad Alignment Measurement
- Measure quadrupole offset from beam axis
- Vary quad magnetic field and fit offset to
trajectory kick - Verifies earth field compensation from BBA
Z (m)
P. Emma
19BBA User Interface
Fit Options
Simulation
Measurement
Corrections
20Fast Linac Energy Change
- User interface to run an automated script
- Block/unblock beam
- Activate saved klystron configuration
- Trim saved magnet configuration
- Toggles feedbacks
- Enables one BBA run in 10 - 15min (at best), 2
4 h (worst)
21BBA Undulator Taper
- Orbit effects from undulator motion
- No earth field shielding with retracted undulator
- Undulator translation (80 mm) shifts entire
girder by 10 - 100 um (quad BPM) - Undulator field integral depends on taper
- Goal
- Straight trajectory for all undulator
translations - Strategy
- Do BBA at design taper, correct quad position
- Compensate field integral change for different
taper with corrector coil - Compensate girder shift for retracted undulator
with corrector coils and BPM offset
22Undulator Field Integral Measurement
Apply 1st field integral to corrector coil
23Summary
- Achieved
- BBA procedure successfully implemented
- Converges to 1 µm trajectory rms
- Important to have full energy range
- Errors on fitted quad offsets decreased from 1 mm
to 10 µm with increasing energy range - Fast energy switching 15 min BBA possible
- Complemented by measurement of quad offsets by
varying quad strength - To Do
- Fully automate energy change (Interface to energy
management, orbit feedback in linac) - Study BBA at low charge (lt 250 pC)
- Implement orbit correction from undulator
translation - Compare girder position from BBA with alignment
diagnostic system (ADS) - Monitor and study BPM offset drifts