Title: INTERREG IIIB project RAIL BALTICA
1INTERREG IIIB project RAIL BALTICA
- The Partnership Agreement
- 5th December 2005
Project part-financed by the European Union
within the BSR INTERREG IIIB programme
2The Partnership Agreement
- Main purpose
- Define conditions of co-operation among project
partners - Divide responsibility of project implementation
and finance among the lead partner and other
project partners. - The Agreements will be signed between the lead
partner (RRDA) and each project partner.
3Content of Agreement (I)
- Subject of Agreement
- Duration of Agreement
- Lead partner's obligations
- Project partners obligations
- Modification
- Reports
- Information and publicity
- Confidentiality
4Content of Agreement (II)
- Third parties
- Non-fulfillment of obligations
- Demand for repayment
- Working language
- Applicable law
5Subject of Agreement (I)
- There are attached following annexes to the
partnership agreement - The approval of application by the Baltic Sea
Region INTERREG III B Neighbourhood Programme
Steering Committee. - The subsidy contract between the managing
authority of the CIP and the lead partner (RRDA).
6Subject of Agreement (II)
- The application form with amendments for the
project RAIL BALTICA. - The project partners budget (separate budget for
each project partner).
7Duration of Agreement
- The earliest date from which cost for the project
can be considered as eligible is the day after
the date of approval by the Steering Committee
03.06.2005. - The Agreement will enter into force
retrospectively from 03.06.2005 onward. - Termination of the Agreement - the date each of
the partners receive their quotas of the final
payment by the EU Commission to the CIP.
8Lead partner's obligations
- Execute overall monitoring
- Overall financial responsibility
- Audit and reports of the project
- Communication
9Project partners obligations
- Involvement in activity planning and
implementation - Financial responsibility of own budget
- 1st level audit and reports
- Communication
10The Partners and Work-Packages (WP) activities
planning (I)
- The partners, who responsible to carry out WP
activities plan - Best solutions for internal information flow
- Schedule of necessary contact meetings
- Funding schemes for WP activities
- Evaluation of WP results.
- WP managing partner in co-operation with the lead
partner is responsible to pass on WP activities
plan to all project partners and other
institutions involved.
11The Partners and Work-Packages (WP) activities
planning (II)
- The partners, who are involved in WP activities
- Receive information about WP activities plan
- Responsible for providing the necessary
contribution in the WP implementation - Keep strongly all deadlines given by WP managing
partner or the lead partner.
12Modification
- Before applying for reallocation of the project
costs between budget lines or modification of the
work plan, the lead partner shall obtain the
approval of these partner, whom modification
referred - About modification in the project the lead
partner inform all project partners.
13Reports (I)
- Reports from each partner need to be sent till
following dates - Milestone 1 till 1st February 2006
- Milestone 2 till 1st August 2006
- Milestone 3 till 1st February 2007
- Milestone 4 till 1st August 2007
- Milestone 5 one month after the official
closing date of project - The lead partner will indicate the official
closing date to the project partners in due time
14Reports (II)
- Report includes following parts
- Activity report (for all partners)
- An audited financial report and confirmation by
independent auditor (for partners, who receive
co-financing from INTERREG IIIB programme) - Reports must be sent by e-mail and by post.
15Reports (II)
- In case, if
- the progress report by the partner is not
submitted to the lead partner on time - the activities reported by the partner are not
performed in practice - the activities reported by the partner are
performed in bad quality - the lead partner may not approve the partners
progress report and exclude the expenditure as
eligible. - The lead partner may ask the project
international Steering group to make the final
conclusion of this question.
16Information and publicity
- The lead partner and the partners will implement
jointly the project communication plan. - General information about the project partners
and its activities can be published by managing
authority of INTERREG IIIB programme
17Confidentiality
- During the project all confidential documents and
other confidential elements must be with
statement confidential. - All project partners must respect the
confidential nature of this information. - This confidentiality clause shall remain in force
for two years following the termination of this
agreement.
18Third parties
- The partners are responsible for action of third
party. - The partners must inform the lead partner about
the subject and party of any contract concluded
with a third party.
19Non-fulfillment of obligations
- The partner is obliged to inform the lead
partner. - The lead partner shall contact the partner and
resolve the difficulties within one month. - In case of further non-fulfillment of obligations
the lead partner decide to exclude the partner
with approval of the Steering Committee of
INTERREG IIIB programme. - In case of excluding the partner, the lead
partner may demand compensation from excluded
partner.
20Demand for repayment
- In case managing authority of INTERREG IIIB
programme demand repayment of subsidy already
transferred, the lead partner need to repay it. - The partners are obliged to transfer its portion
of the repayment amount to the lead partner
within two weeks.
21Working language
- The official working language - English
22Applicable law
- The Partnership Agreement is governed by the
Latvian law.
23Further activities...
- Planned that the Partnership Agreements project
(English version) will be send out till 9th
December 2005. - Each project partner need to inform the lead
partner about the Agreement clauses where is
necessary some modification. - After harmonization of the Agreement the lead
partner will send out signed agreements with
annexes.
24Thank you for attention!Questions?!