Title: Estimating Activity Durations
1Estimating Activity Durations
2Purpose
3Implicit Assumptions Revealed
4Source of Data
- Expert opinions
- Time studies
- Statistical analysis
5Source of Data
- Expert opinions
- Time studies
- Statistical analysis
6Source of Data
- Expert opinions
- Time studies
- Stop motion studies
- Diary
- Statistical analysis
7Source of Data
- Expert opinions
- Time studies
- Statistical analysis
8Assessing Experts Opinions
- Assumptions
- Estimate, talk and estimate
- Delphi
9Assessing Experts Opinions
- Assumptions
- Estimate, talk and estimate
- Delphi
10Assessing Experts Opinions
- Assumptions
- Estimate, talk and estimate
- Delphi
11Example of Estimate Talk Estimate
12Example of Estimate Talk Estimate
Thanks for agreeing to help usplease write down
13Example of Estimate Talk Estimate
Responses from different expert are collected and
displayed on the flip chart without attribution
14Example of Estimate Talk Estimate
This is great. Lets discuss why it could take a
long time
15Example of Estimate Talk Estimate
Well it depends on the experience of the person
configuring the system
16Example of Estimate Talk Estimate
And it also depends on how cooperative the
clinicians are.
17Example of Estimate Talk Estimate
Discussion of Assumptions
18Example of Estimate Talk Estimate
You have said please re-estimate
19PERT
- Optimistic
- Realistic
- Pessimistic
20PERT
- Optimistic
- Realistic
- Pessimistic
21PERT Dialogue
How long do you think it would take to send 100
surveys out?
22PERT Dialogue
It all depends. I have seen people do it in 6
hours and I have seen others do it in 1 hour.
23PERT Dialogue
But given what I know about your operations I
think it will take 2 hours.
24PERT Dialogue
25Take Home Lesson
- Estimate-Talk-Estimate and PERT method can
increase accuracy of estimate of duration of
activities