Title: MINERnA Main INjector ExpeRiment for vA


1
MINERnAMain INjector ExpeRiment for v-A
Minerva Reviews
2

The Big Picture
Directors Trial CD 12 Review First week of Dec.
2005 (focus on the project cost and schedule)
CD0 Oct. 2005 (project cost reporting begins)
3
How much time to freeze schedule?
  • Directors review first week December
  • Talks completed (posted) Dec. 1
  • Practice talks Nov. 28/29
  • Freeze schedule for talks ??

4
The Big Picture
  • Hard to report costs/project status if we
    microsoft project (MSP) schedule does not reflect
    the work to be done
  • Cant really do the MOUs/SOWs until we have the
    MSP relatively accurate
  • Directors Trial Review for CD1 2s Focus is on
    the MSP cost and schedule and Basis of Estimates
    (BOEs)
  • Main point of the reviews is to
  • Consistently define the design specifications
  • and assembly process for each WBS (how many
  • and where they go) 80 there?
  • Put this process and the associated costs/labor
  • in MSP 70 there?
  • BOEs go in the notes field in MSP or on a
    separate
  • BOE form (use the BOE form for tasks gt10K)
    60 there?
  • Get appropriate milestones into MSP xx there?

n
5
Review Status
  • Table of WBS, name, review 1 date, review 2 date
    (final) and put in color green complete, red to
    go and big stars to schedule

6
Review talks morph to Directors Review Talks
  • We all need to have a uniform template for the
    Directors Reviews talks.
  • Cost, schedule, resource tables etc. extracted
    from MSP will be provided to each L2 to put in
    their talk.
  • One talk per L2?
  • Talks to cover
  • Name, overall cost (total 7 MS vs. SWF)
  • Scope of system (what your system is in one or
    two pages)
  • Specifications for your system (what drives your
    designs)
  • Cost and schedule drivers
  • NuMI baseline template? Show?
  • Pretty pictures of progress and what you have
    done so far.
  • Doesnt hurt to make your internal Design/Cost
    Review talk to have most of these elements such
    that it will not be too much work for you to make
    your Directors Review Talk.

7
MOU/SOWs
  • Table of Univ. then FY05, FY06 need MOU/SOW
    (order I will do/dates?)
  • So much has changed in MSP, need new MOUs for
    FY06
  • Need to determine those tasks in FY05 SOW
  • Not done in FY05, but will be done in FY06 (need
    not to put in FY06 SOW)
  • Done in FY05, but not in FY05 SOW (need to put in
    FY06 SOW)
  • Need to make MSP reflect reality with these tasks
    and what was done in FY05 (and will be done in
    FY06)
  • I will draft MOUs/SOWs for everyone but Rochester
    which Kevin will do (thank god as that is the
    most complicated one!)
  • I can not do this until you have put into MSP the
    work you did in FY05 and plan to do in FY06
  • We have to extract the tasks from a pretty
    accurate MSP schedule or we cant keep track of
    costs/invoices and progress. CD0 is upon us!!!
  • You will need to review what I give you and make
    corrections asap (if you want the money asap)

8
Invoicing Cost Reporting
  • Money in your FY05 SOW for work that you did not
    complete in FY05 will not go away, we just need
    to make sure we dont double-count it in the FY06
    SOW
  • Suzanne has in the FY06 MOU
  • The MINERvA group at Institution will invoice
    all MINERvA-related expenditures in each item of
    work by Work Breakdown Structure (WBS) category
    on monthly basis through the appropriate MINERvA
    Level 2 Manager to the MINERvA co-Project
    Managers. The MINERvA group at Institution agrees
    to furnish complete documentation of the quality
    control and performance checks.

9
Invoicing Cost Reporting
  • The sooner you get MSP updated, the sooner we can
    get your MOU/SOW going.
  • Monthly reporting has started (CD0 in October).
  • Report at L2 (thus 1.2, 1.3.3.1, 3.2, etc) with
    a few words on status of each WBS at that level
  • TJ will be giving you a MPS output with WBS tasks
    and you will have to status them each month (
    complete and update start and finish times as
    necessary)
  • In monthly reports you should report any cost or
    schedule concerns you have in order to give us a
    heads up
  • If something goes over the cost in MSP, you need
    to let us know. The threshold for when you need
    to do a change request is being determined.
    (amount????!!!!!)

10
  • Oct. 2005 need to draft documents
  • CDR (have, move to TDR, Jorge)
  • Preliminary PMP, PEP (have Dave B.)
  • Baseline Resource Loaded Schedule
  • Preliminary Hazard Analysis Report
  • (Mike Andrews)
  • Value Management Document (need)
  • Draft Configuration Management
  • Document (need)
  • Acquisition Strategy Document (need)
  • March 2006 documents done
  • Preliminary Design (TDR)
  • Baseline Cost Estimate Resource
  • Loaded Schedule
  • Final PMP (PEP approval 12/05)
  • NEPA Approved Safety Documents
  • Final Design Procurement Packages
  • Final Configuration Management Doc.
  • Updated Value Management Document

11
Documents to be working on now
  • CDR (have, move to TDR, Jorge)
  • Preliminary PMP, PEP (have Dave B.)
  • Baseline Resource Loaded Schedule
  • Preliminary Hazard Analysis Report
  • (Mike Andrews)
  • Value Management Document (need)
  • Draft Configuration Management
  • Document (need)
  • Acquisition Strategy Document (need)

n
12
L2 Project Work
  • MSP Update MSP with TJ ASAP!!!!
  • Design/Cost Review Schedule your final
    Design/Cost review with Nancy (before mid-Nov,
    after that it will be too late.)
  • Address comments/recommendations
  • Basis of Estimates Write BOEs for tasks with
    10K or more base cost
  • MOU/SOW
  • Check template on reviews page with your
    university, is it OK?
  • When you get a draft MOU/SOW from FNAL,
    read/update it quickly and get it back to
    Nancy/Dave B.
  • Monthly Report Do your Monthly reporting (first
    week of every month).
  • Monthly Status also around the first week of
    every month (now on)
  • Change Requests if costs are not as specified
    in MSP, over a certain dollar amount, you will
    need to get approval (a Change Request, CR)
  • Then there is the real work.