Title: PROJECT ORGANISATION AN INTRODUCTION
1 PROJECT ORGANISATIONAN INTRODUCTION
2Objectives
- By the end of the presentation participants
- Appreciate projects as an intervention that needs
to fit a wider context - Have acquired some basic knowledge to develop a
(library development) project using the Logical
Framework Approach (LFA) -
-
3Multi level planning
- Different institutional levels
- University as a whole
- Different faculties/research centres/support
units - Different scope
- Strategic planning
- Project planning
4Strategic/Project planning
- Strategic planning concerns long term goals that
cannot be planned in the same manner as projects - Human, material and other resources cannot be
accurately planned over longer periods - Requires a long-term vision that is flexible
enough to accomodated flexible changes not
compromising the envisaged goal - Project planning concerns efforts to achieve
limited goals with limited resources in a more
limited period of time - Tactical manoeuvre within a long term strategy
- Given its scope it can be planned with much more
precision
5Multi level planning
6Multi level planning
- CORPORATE STRATEGIC PLAN
- WORKPLAN
- UNIVERSITY LIBRARY IMPROVED
- Compu(terisation plan approved
- Printing press operational
- Electronic devices installed
- Book lending system computerised
- Mechanism to acquire up to date literature
instituted
LONG TERM LIBRARY DEVELOPMENT PLAN
PROJECT 1
PROJECT 2
PROJECT 3
7A library development plan
- To contribute effectively to the overall
strategic plan of the university - To serve as an overall guide/reference for all
stakeholders (in particular for resource
utilisation) - As a PR document in support of resource
generation (within the university and in relation
to donors) in an increasingly competitive
environment
8Projects and Programmes
- Funding and contributions that are additional to
ongoing activities - Limited in time and resources
- Contribute to process of change taking place in a
context that is complex, continuously changing
and undergoing the influence of many actors
9Project Management
- Structuring and facilitating of processes of
change in order to attain certain objectives in
the most effective and efficient way - Ensuring that all major stakeholders are
consulted, that their knowledge and insights are
used to improve the quality of the
project/programme - Requires continuous information collection and
analysis enabling timely decisions and
adaptations to the planned intervention
10 Tool for management
- Experience has shown that many projects have
failed due to lack of analysis, leadership by
technicians etc. - In the late 60s, USAID adopted the logical
framework approach (LFA) or participatory project
design and logical planning of objective oriented
projects. - LFA is a methodology for analysing, planning,
managing and evaluating programmes and projects,
using tools to enhance participation and
transparency and to improve orientation towards
objectives (more project oriented) - LFA is currently mainstream project management
tool - In the 90s the more comprehensive PCM approach
was developed. PCM has meanwhile been adopted by
most donors, including VLIR
11LFA - some reflections
- Not revolutionary but likely to frame and
articulate ongoing practices - Not an exact science but a supporting tool to
structure learning processes - Widely applicable usefulness goes beyond
development - Value added depends on quality of its application
12Logframe Approach
PLANNING PHASE
ANALYSIS PHASE
- Logframe - defining the project/ programme
structure, testing its internal logic,
formulating objectives in measurable terms,
defining means and cost (overall) - Activity scheduling - deter-mining the sequence
and depen-dency of activities estimating their
duration, setting milestones and assigning
responsibility - Resource scheduling - from the activity schedule,
developing input schedules and a budget
- Stakeholder Analysis - identifying
characterising major stakeholders, target groups
beneficiaries, defining whose problems will be
addressed by a future intervention, and which
potentials can be used - Problem analysis - identifying key problems,
constraints and opportunities determining cause
and effect relationships - Analysis of objectives - developing objectives
from the identified problems identifying means
to end relationships - Strategy analysis - identifying the different
strategies to achieve objectives selecting the
most appropriate strategy(ies) determining the
major objectives (overall objectives and project
purpose)
Define the project logic
Identify stakeholders
Specifying and operationalising
Deduct
Select the option
13Stakeholders
- Any individuals, groups of people, institutions
or firms that may have a relationship with the
project/ programme - They may directly or indirectly, positively or
negatively affect or be affected by the process
and outcomes of projects or programmes
14Stakeholder Analysis (4 steps)
- Identifying Key Stakeholders (beneficiaries,
vulnerable groups, possible adversely effected
groups, socio-economic characteristics,
relationships etc.) - Determining Stakeholder Interests (benefits,
expectations, resources they could mobilise etc) - Determining Stakeholder Power and Influence
(power and dependency relationships, control of
decision making, resources etc.) - Formulating a Stakeholder Participation Strategy
in view of analysis, planning and implementation
15Stakeholder Analysis (Summary)
Potentials deficiencies knowledge,
experience... potential contribution
Implications and conclusions for the
project possible action required how to deal with
the group
Interest expectations interests,
objectives... Expectations
Characteristics social, economic gender
differentiation structure, organisation,
status attitudes...
Stakeholder
16Step 1Problem analysis (I)
- Is a procedure which allows to
- analyse an existing situation
- identify key problems in this context
- visualise the problems in form of a diagram/tree
(cause-effect relationships)
17Problem analysis (II)
Establishing cause-effect relations between
problems
Teaching/research is based on outdated and
fragmented information
Effects
Irrelevant and incomplete information access
Ignorance and neglect of user community on value
added of sourcing quality information
Attrition of library materials
Inability to access electronic information
sources effectively
Inadequate ability of users to access information
Low institutional emphasis on information based
academic work
Causes
18Problem analysis (III)
- agree on the unit of analysis
- identify major problems existing within a given
situation (brainstorming) - select a starter problem
- look for related problems to the starter problem
- establish hierarchy of cause and effects
- problems which are directly causing the starter
problem are put below - problems which are direct effects of the starter
problem are put above - complete with all other problems accordingly
- connect the problems with cause-effect arrows
- review the diagram and verify its validity and
completeness
19Analysis of objectives (II)
- Describes the future situation that will be
achieved by solving the problems - by turning the negative aspects into positive
ones (desired, realistic) Reformulate all
negative situations of the problem analysis into
positive situations that are - desirable
- realistically achievable
- Check the means-end relationships
20Analysis of objectives (III)
Turning the negative aspects into future desired,
but realistic situations
Teaching/research is based on updated information
Ends
Relevant and complete collection
available/accessible
Users are fully aware and motivated regarding
scientific information usage
Teaching and research culture favours active
information retrieval/use
High standard of management and maintenance are
observed in place.Coral man-grove habitats
conserved
Efficient electronic access to external data
sources
User community is fully conversant with
information services
Means
21Step 3 Analysis of Strategies (I)
- The purpose is
- to identify possible alternative options or ways
to contribute to the overall objectives - to agree on priority strategies based on an
assessment of the relevance, the feasibility and
the sustainability of each of them - to concentrate the means of the project on what
is really important, effective and feasible
22Analysis of Strategies (III)
Teaching/research is based on updated information
OVERALL
OBJECTIVE
Relevant and complete collection
available/accessible
Users are fully aware and motivated regarding
scientific information usage
SPECIFIC
OBJECTIVE
High standard of management and maintenance are
observed in place.
Efficient electronic access to external data
sources
User community is fully conversant with
information services
Teaching and research culture favours active
information retrieval/use
RESULTS
Decision based on budget, priorities, human
resources available, social acceptability,
urgency, ...
23The Logical Framework?
- The Logical Framework Matrix provides a summary
of - why a project is carried out
- what the project is expected to achieve
- how the project is going to achieve it
- which external factors are crucial for its
success - where to find the information required to assess
the success of the project - which means are required
- what the project will cost
24Step 4 From Strategy Analysis to Intervention
Logic
- Complete formulation of objectives
- Transfer objectives to logframe (intervention
logic) OO, SO, Results - Review and complete the objectives at different
levels - Identify possible activities
25Logical framework
- Intervention Objectively Sources
of Assumptions - Logic Verif. Indicators Verification
Overall Objectives
Specific Objective
Results
Activities
Means
Costs
Pre-condi-tions
26Intervention Logic
- Overall objectives the academic long term
benefits to which the project/programme will
contribute. - Specific objectives the key project/programme
objective that indicates the benefit(s) the major
project beneficiary will obtain. - Results the services or products to be realised
by the project/programme. - Activities the measures to be taken by the
project to ensure the outputs.
27(No Transcript)
28(No Transcript)
29(No Transcript)
30Step 5 Completing the Logframe
- Identify assumptions
- Identify indicators and sources of verification
31Assumptions
- What are they?
- They are external factors that influence or even
determine the success of the project - Why are they required?
- The intervention logic never covers all aspects
of reality. External factors have an important
influence on the success and should be identified
and taken into account - What is a pre-condition?
- An assumption that must be fulfilled/met before
activities can start
32Assumptions
- Identify in the hierarchy of objectives those
objectives that are not included in the
intervention logic but important for the success
of the project - Identify other external factors not included in
the hierarchy which must be fulfilled to achieve
the Overall Objectives, the Project Purpose, the
results and the activities - Place them as external factors at the
appropriate level of the logframe
33Logframe Basics
Objectively Verifiable Indicators
Intervention Logic
Sources of Verification
Assumptions
Overall Objectives
Specific Objective
Results
Activities
Means
Cost
Pre-condi-tions
... IF results are delivered, AND assumptions
hold true, THEN the project purpose will be
achieved ...
34Assumptions
- Assess the importance of the external factors
by using the assessment algorithm - Check the intervention logic and assumptions on
completeness
35Assessment of Assumptions
Is the external factor important?
Yes
No
Do not include in logframe
Will it be realised?
Almost certainly
Do not include in logframe
Likely
Include as an assumption
Unlikely
Is it possible to redesign the project in order
to influence the external factor?
Redesign the project by adding activities or
results reformulate the Project Purpose if
necessary
Yes
No
The project is not feasible
36Indicators
- To
- Clarify the characteristics of the OO, PP and R
- Manage the project more objectively
- Provide a basis for performance measurement,
monitoring and evaluation - Note
- Often, it is necessary to establish several
indicators for one objective. Together, these
will provide reliable information on the
achievement of objectives.
37SMART Indicators
- SPECIFIC
- MEASURABLE
- AGREED UPON
- REALISTIC SENSITIVE
- TIME BOUND COST EFFECTIVE
38Some criteria for good indicators
39Indicators An Example
- Objective Pollution load of wastewater
discharged into the Blue river is reduced - Select the indicator Concentration of heavy
metal compounds (Pb, Cd, Hg) - Define the targets
- Define the quantity Concentration of heay metal
compounds (Pb, Cd, Hg) is reduced by 75
compared to year x levels (particular attention
should be paid to the availability of baseline
information) - Define the quality ... to meet the limits for
irrigation water ... - Define the target group ... , used by the
farmers of Blue village, ... - Define the place ... in the Blue river section
of the District ... - Determine the time ... 2 years after the project
has started
40Sources of Verfication
- They describe where and how to find the
information with regard to the indicators - Issues to be analysed
- Do there exist external sources of verification?
- If so, are they specific enough, reliable and
accessible? - If not, how can the information with regard to
the indicators be obtained?
41Proposal writing
- Proposals are often defined as selling through
writing. It differs from other documents in that
is has a greater degree of persuasion that drives
it. - Similar to a good sales promotion, it has a
mixture of art and science - Visually attractive, concise and capturing the
readers imagination - It follows logic and is based on a set of
assumptions and facts
42Proposal writing sales tips
- Emphasize value (quality, service, timeliness,
pay in dollars) It takes away the emphasize from
price - Sell benefits, not features focus on the needs
of the reader, not simply talk about the quality
of the proposed project - Use emotional appeals without exaggeration
- Supply evidence (key information not all
information) - Establish a unique selling proposition Show a
unique value added such that it stands out - Use persuasive and positive approach not weak or
defensive language (eg. Title)
43Excercise
- Work in small buzz groups
- Find 4 rows that have been mixed up.
- Reconstruct the rows as objectives, indicators
and sources of verification. - Review and assess the indicators/targets.
44Activity Resource Scheduling
Logframe
Results-based workplans budgets
45Activity Scheduling
- An activity schedule
- Maintains objective-oriented approach of logframe
- Breaks activities down into operational detail
- Clarifies sequence, duration and precedence of
activities - Identifies key milestones
- Assigns management responsibilityand
implementing responsibilitiesand should include
management tasks
46(No Transcript)
47Resource Scheduling
- A resource schedule
- Maintains objective-oriented approach of logframe
- Facilitates results-based budgeting and
monitoring of cost-effectiveness - Provides basis for planned mobilisation of
resources (external local) - Identifies cost implications
- Counterpart funding requirement
- Post-project financial sustainability
48Criteria for evaluation
Sustain-ability
Overall Objectives
Impact
change
Project Purpose
Assumptions
Effective- ness
utilisation
Results
Assumptions
action
Efficiency
Activities
Assumptions
allocation
Means
Pre-conditions
Relevance