CTC Presentation - PowerPoint PPT Presentation

1 / 40
About This Presentation
Title:

CTC Presentation

Description:

CTC Presentation – PowerPoint PPT presentation

Number of Views:241
Avg rating:3.0/5.0
Slides: 41
Provided by: kenne8
Learn more at: https://dot.ca.gov
Category:
Tags: ctc | presentation

less

Transcript and Presenter's Notes

Title: CTC Presentation


1
  • CTC Presentation
  • April 15-16, 2009

2
Project Purpose
  • Improve the seismic, structural, and traffic
    safety of the roadway within the setting and
    context of the Presidio of San Francisco and its
    purpose as a National Park

3
Doyle Drive History
  • Built 1933-36 to bypass Army Base
  • (Under Golden Gate Bridge Highway District)
  • 1945 Became a State Route
  • 2000 Began new EIS/EIR for replacement
  • 2005 Completed Draft EIS/EIR
  • 2005 Introduced Parkway Alternative
  • 2007 Preferred Alternative selected
  • Dec. 18, 08 Record of Decision (ROD) signed

4
Doyle Drive Existing Condition
  • Structural deterioration
  • No median
  • No shoulders
  • Narrow lane widths
  • No direct Presidio access

5
Significance of Doyle Drive
  • Interregional Route
  • Over 100,000 vehicles per day
  • Vital to the economic and social well being of
    region.
  • Designated as a Post Disaster Recovery Route
  • Located in the Presidio, a National Historic
    Landmark District

6
Project Consensus and Coordination
7
Presidio Parkway (Alternative 5)
Structure
At-Grade Roadway
At-Grade Roadway
At-Grade Roadway
Tunnel
Tunnel
High Viaduct
Halleck St.
Girard Rd.
  • Current Structural/Seismic standards
  • Meet capacity demands
  • Parkway Appearance
  • Presidio Access
  • Total Project Cost 1,045 Million

8
ROD Project Estimate
  • The Parkway Alternative option Estimate
    submitted in the FEIS (2008 Estimates)
  • Roadway Items 233.3 Million
  • Structural Items 474.3 Million
  • Sub-total 707.6 Million
  • Escalated (to MCP of 2012) 853.7 Million
  • Right of Way Items 36.3 Million
  • Total Capital cost 890.0 Million
  • Support 154.6 Million
  • Project Total 1044.6 Million
  • Assuming Construction from Dec. 2010
    April 2014
  • MCP Mid Construction Point

9
Original Project Timeline
Preferred Alt Sept. 2006
Fall 2010
Feb. 2000
Spring 2014
Dec. 2005
Winter 2011
Summer 2000
Dec 2008
Detailed Design Completed
Project Complete
Environmental Studies begin
Draft ESI/EIR Public Comment Begins
Final EIS/EIR
Construction Start
ID Alternatives Begin Prelim Engineering
Draft EIS/EIR For Comment
Final EIS/EIR ROD
Start Construction
Milestones Completed
10
  • Project Acceleration

11
Why Accelerate ?
  • To achieve seismic safety earlier
  • To reduce risk of cost growth
  • To meet Economic Stimulus timetable
  • To take advantage of the favorable market
    conditions
  • Help create jobs and support the local and
    regional economy

12
Split Contracts
  • Pre-Construction Contracts
  • Contract 1 Environmental mitigation
    (Built-Environmental Treatment Plan) Active
    through roadway contracts
  • Contract 2 Utility Plan and Relocation
  • Roadway Construction Contracts
  • Contract 3 Southbound Presidio Interchange/High
    Viaduct
  • Contract 4 Southbound Battery Tunnel and
    At-Grade Detour
  • Contract 5 Girard Interchange, Low Viaduct and
    Main Post Tunnels
  • Contract 6 Northbound Battery Tunnel
  • Contract 7 Northbound Presidio Interchange/High
    Viaduct
  • Contract 8 Landscaping

13
Draft Schedule
Seismic Safety Achieved Early 2011
Roadway Complete Summer 2012
Original Project Schedule Completion Spring 2014
14
Contract No. 3 SB Presidio IC
  • Construction Capital 134 Million
  • Begin/End Construction
    October 2009 - Early 2011

15
Contract No. 4 SB Battery Tunnel
  • Construction Capital 110 Million
  • Begin/End Construction
    December 2009 Early 2011

16
Contract No. 5 Girard IC
  • Construction Capital 305 Million
  • Begin/End Construction
    Fall 2010 - Fall 2012

17
Contract No. 6 NB Battery Tunnel
  • Construction Capital 77 Million
  • Begin/End Construction
    Fall 2010 - Fall 2012

18
Contract No. 7 NB Presidio IC
  • Construction Capital 103 Million
  • Begin/End Construction
    Fall 2010 - Fall 2012

19
Contract No. 8 Landscaping
  • Construction Capital 9 Million
  • Begin/End April 2012 April 2015
  • Total Project Construction Capital 760 Million

20
Presidio Parkway Simulation
21
  • Presidio Parkway
  • Multi-modal Enhancements

22
Presidio Parkway
  • Setting and Context
  • Guide Design
  • Provide opportunity to support transformation of
    the Presidio from a military base to a National
    Park
  • Offer opportunity for integrated, intelligent
    design appropriate to the surroundings

23
Presidio Parkway
  • Setting and Context
  • More than a roadway
  • A network of areas and connections within the
    Presidio

24
Existing Doyle Drive Connections
  • Facility built to restrict access to military
    base
  • 2 connections across Doyle Drive

25
Presidio Parkway Future Connections
  • Enhanced access to/from/within the Presidio
  • 9 connections across Doyle Drive
  • Increase multi-use trails and pathways within the
    Presidio

26
Lincoln Boulevard Enhancements
27
Presidio Promenade at Lincoln
28
Battery Tunnels Revived Connection
29
Battery Bluff Revived Connection
30
Main Post Tunnel Revived Connection
31
East Parkway Revived Connections
32
East Parkway Revived Connections
33
Girard Road Enhancements
  • Dedicated Bike Lanes
  • Accommodate Future Transit/Rail in Median

34
Presidio Parkway Corridor
35
  • Questions?

36
The Presidio
37
Presidio ParkwayKey Design Goals
  • Reduce mass and scale of the facility
  • Reduce speeds entering city streets
  • Parkway and not freeway standards
  • Over 100 design exceptions
  • Minimize conversion of park land to highway
  • Enhance the multi-modal network within the
    Presidio
  • Consistent with land use plans
  • Presidio Trust Management Plan
  • Presidio Trails and Bikeways Master Plan
  • Presidio Vegetation Management Plan

38
Existing Battery Bluff
  • Current roadway severs connection

39
Existing Main Post /Crissy Field Area
  • Current roadway reduces connections and is a
    visual barrier

40
Presidio Parkway
Write a Comment
User Comments (0)
About PowerShow.com