Title: FEDERAL PANEL TIPS STREAMLINING THE PERMITTING PROCESS
1FEDERAL PANEL TIPSSTREAMLINING THE PERMITTING
PROCESS
Cynthia Wood Jacksonville District 29 September
2009
2PERMIT REVIEW PROCESS
Joint Permit App Submittal to State
App Received from State Begin Processing
Public Notice
Corps
Individuals Special Interests
Local Agencies Federal Agencies
Application Approved
PermitIssued
Decision Document
404(b)(1) Guidelines Public Interest
Review NEPA ESA, NHPA, EFH State Territorial
Certifications(CZM, WQC)
Application Reviewed
Application Denied
3ESA CONSULTATION PROCESS
Application
Corps makes Initial Determination of Effect
(Opt 1)
(Opt 2)
(Opt 3)
Not Likely to Adversely Affect (NLAA)
May Affect
No Affect
Corps requests Formal Consultation by letter that
includes Information describing project and
effect
Corps sends NLAA letter to Service for
concurrence
(Opt 3)
(Opt 1)
(Opt 2)
Service advises project NLAA
Services Biological Opinion concludes adverse
affect Formal Consultation concluded
Services Biological Opinion concludes
NLAA Formal Consultation concluded
Review/request Service to stop Formal
Consultation and changes to NLAA
Service Concur?
Yes
NO May Affect
Service concurs--Formal consultation is
terminated
Corps proceeds with final decision
4STREAMLINING PERMIT PROCESS -- TIPS
- Request a pre-application meeting for larger
projects. - Provide a complete application with clear
drawings. Complete all necessary checklists for
TE issues. - Provide information requested by the Corps in a
timely manner. - Utilize the Corps and other Federal agency
webpages.
5HOW TO STAY OUT OF ENFORCEMENT
- Read all permit conditions - general and specific
- Adhere to all permit conditions
- Never initiate work without permit in hand
- Post-permitting changes or accidental fills -
contact the Corps - When in doubt, call
6QUESTIONS?