UN ICTY ENERGY ANALYSIS
BACKGROUND
  • Building Description
  • - c. 1953
  • - Office space 16,000 m2
  • - Gross space 33,000 m2 and
  • - Staff of 900.
  • 2005 Annual Energy Details
  • - Gas use 500,000 m3 (16,000 GJ), cost
    155,000 Euros
  • - Electricity use 500,000 kWh (46,000 GJ,
    cost 375,000 Euros and
  • - Combined total for 2005 is 62,000 GJ (1,850
    GJ/m2),
  • and annual cost of 530,000.
  • Matters for Investigation
  • - Increase of use and
  • - Better utilization and savings.

2
UN ICTY ENERGY ANALYSIS
BACKGROUND
  • Goal
  • - Reduce Energy Use by 10 within one year.
  • Description of Work Proposed
  • - Review and Analyze Invoices
  • - Create Building Specific Energy Balance
  • - Produce Benchmark Comparison
  • - Investigate irregularities and
  • - Propose Energy Saving Actions.
  • Note
  • - Time limited institution, so return period
    must be 3 to 5 years.

3
UN ICTY ENERGY ANALYSIS
OVERVIEW
  • Review of Energy Invoices
  • - Errors were not identified and
  • - Advised to lower contracted power.
  • Energy Benchmark
  • - Extremely inefficient building and
  • - Two electricity and one heating balance
    performed
  • Specifics and Savings Potentials Noted
  • - Disparities between registered and calculated
    base loads
  • - Disparities between 2004 and 2005 base loads
    and
  • - Calculated maximum load in-line with
    registered load on invoices.

4
UN ICTY ENERGY ANALYSIS
ACTION PROPOSED
  • Ventilation, Heating and Cooling
  • - Lower outside air quantity
  • - Lower air-flow in offices
  • - Install swirl air diffusers
  • - Provide thermostatic valves on radiators
  • - Estimated savings of 50 on ventilation, 30
    on heating,
  • and 10 on cooling and
  • - Estimated monetary details and implementation
    plan.
  • Base Load Reduction
  • - Accurate measurements
  • - Inventorying equipment and
  • - Further study recommended

5
UN ICTY ENERGY ANALYSIS
ACTION PROPOSED
  • Lighting
  • - Install motion detectors
  • - Invest in computerized lighting controls and
  • - Consider renewal of old lights.
  • Heat Generation
  • - Consider ventilation heat recovery system and
  • - Replace boilers/burners with higher efficiency
    ones.
  • Cooling
  • - Consider higher set points
  • - Place chillers and water cooler off line
    during intermediately season
  • - Lower delta T set points for chillers and
  • - Check buffers on AC units to prevent cycling.

6
UN ICTY ENERGY ANALYSIS
PROJECTS WITH MININAL INVESTEMNT
  • Description Est. Annual Saving
  • Decrease Contracted Electrical Power 5,000
    Euros
  • Optimize Heating and Cooling Set Points 20,000
    Euros
  • Lower Air Flow 25,000 Euros
  • Reduce Based Load by
  • - Turn off all PCs and Monitors 16,000 Euros
  • - Turn off other equipment 19.000 Euros
  • One-Hour Less Ventilation 6,000 Euros
  • One-Hour Less Lights 12,000 Euros
  • Estimated Annual Total 125,000 Euros
  • Over Five Years Total 625,000 Euros

7
UN ICTY ENERGY ANALYSIS
PROJECTS WITH SOME INVESTEMNT
  • Overview
  • - Items proposed are estimated to have annual
    savings of 225,000 Euros and a return period
    between 2 to 5 years.

8
UN ICTY ENERGY ANALYSIS
SUMMARY
  • Old inefficient building
  • Rising use and cost of energy
  • Identifications of wastes of energy
  • Identifications of improvements without and with
    investments
  • Investigate Local Law requiring on investments in
    improvements when pay back period is less than 5
    years
  • Lower air flow to 40 to 50 m3/h and install
    swirl diffusers
  • Install thermostatic valves
  • Prepare action plans as indicated earlier and
    detailed in the report
  • Estimated overall savings of 1,750,000 over 5
    years with the same return period on investment
    and
  • Cost or report was 10,000 Euros.