Title: SRF Vertical Test Cryostat Design Review
1SRF Vertical Test CryostatDesign Review
2Introduction
- Welcome and introductions
- Charge to the committee
- Assess the technical design of the ILCTA IB1 SRF
Vertical Cryostat and its readiness for the
procurement/fabrication process - Comment on all technical aspects of the Cryostat
design, including integration to the IB1
cryogenic system - Provide a written report.
3- not a facility safety review
- Focus on
- Cryostat technical specifications
- Readiness for procurement
- Review outline
- Location of and purpose of facility in IB1 (Joe
Ozelis) - Cryostat system requirements (Mayling Wong)
- Integration with IB1 Cryogenic System, PID, and
Cryogenic Design Parameters - (Roger Rabehl and Yuenian Huang)
- 3D model overview (Clark Reid / Mayling Wong)
- Documentation requirements (Mayling Wong)
- Cost estimate, procurement plan, and schedule
(Cosmore Sylvester)
4- Goals of the ILC Vertical Cavity Test Program
- Verify cavity processing improvements by
quantifying cavity performance in a reliable,
reproducible, and efficient manner. - Measure Q0 vs Temperature
- Measure Q0 vs E
- Measure Field Emission (radiation)
- Investigate effect of low temperature externally
performed bakeout on Q-drop - Initial throughput expected to be 2
cavities/month, increasing to 2 cavities/week.
Multiple tests/cavity (Q-drop) increase this. - System is to be capable of testing cavities
designed for the ILC Main Linac cryomodule. - Baseline Design Tesla cell shape, 9 cells, 1.3
GHz. Alternate geometries, cells,
superstructures, may also be evaluated.
5Cavity Test Facility Location
6Cavity Test Facility Location
Existing cryogenic services
Approx size/location of cryostat pit/hole
7- Cavity Test Facility Cryostat/Cryogenic
Requirements - LHe bath capable of operation between 4.3 and
1.6K - Cooldown rate from 300K to 4K that minimizes
Qdisease susceptibility (minimize time spent
between 100-150K) - Sufficient volume of LHe above cavity to preclude
need for active LHe level control during testing
(190-200cm 165cm to top cavity flange) - Instrumentation to provide readout of Dewar
pressure, temperature, and LHe level - Fast turnaround
- Cooldown fill 4-6 hours
- Pumpdown 2-4 hours (can be concurrent w/ fill
if not performing Q0 vs T measurements) - Remnant LHe boiloff 3-5 hours (150-180W for
800L) - Warmup to 300K 10-12 hours (400K He gas at
2g/s)
8Example Test Cycle (w/ Q0 vs T measurement) Inser
t stand into Dewar Leak check Dewar seal Leak
check test stand Attach RF instrumentation
cables Pump/purge Dewar w/ GHe, check for
contamination Cooldown Fill _at_ 4K Cable
calibrations _at_ 4K Measure cavity frequencies (all
modes) Perform low field (2-3 MV/m) Q0
measurement (1W amplifier) Begin pumpdown to
1.5K, take low field Q0 data Warm back up to
2K Perform Q vs E measurements at 2K Boiloff
remnant LHe Warm Dewar
0.5hr 0.5hr 1hr 0.25hr 1hr 1.5hrs 4hrs 0.5hr 0.25h
r 0.5hr 3hrs 0.5hr 2hrs 4hrs 12hrs
Total warm-warm cycle time 31.5hrs
9Example Test Cycle (w/o Q0 vs T
measurement) Insert stand into Dewar Leak check
Dewar seal Leak check test stand Attach RF
instrumentation cables Pump/purge Dewar w/ GHe,
check for contamination Cooldown Fill _at_ 4K, begin
pumping to 2K when LHE collects Cable
calibrations _at_ 2K Measure cavity frequencies (all
modes) Perform Q vs E measurements at 2K Boiloff
remnant LHe Warm Dewar
0.5hr 0.5hr 1hr 0.25hr 1hr 1.5hrs 4hrs 0.5hr 0.25h
r 2hrs 4hrs 12hrs
Total warm-warm cycle time 27.5hrs
10Example Test Schedule (includes Q0 vs T
msmt) Day 1 Load test stand, all checkouts,
cooldown fill to 4K Day 2 Q0 vs T, Q0 vs E,
boiloff Lhe and begin Dewar warmup Day 3 Remove
test stand, setup for 120 C bake 24 hours Day
4 Load test stand, all checkouts, cooldown
fill to 4K Day 5 Q0 vs T, Q0 vs E, boiloff LHe
and begin Dewar warmup This scenario supports 2
tests per week of the same cavity, with a 24hr
120 C bake between tests. If Day 3 is a Friday,
can do a 48hr bake over a weekend.
11Example Test Schedule (w/o Q0 vs T msmt) Day 1
Load test stand, all checkouts, cooldown, fill,
pump to 2K, Q vs E, start boiloff warmup script
(long day) Day 2 Remove test stand, setup for
120 C bake 48 hours, swap cavities Day 3
Load test stand, all checkouts, cooldown, fill,
pump to 2K, Q vs E, start boiloff warmup script
(long day) Day 4 Remove test stand, setup for
120 C bake 48 hours, swap cavities (baked
one) Day 5 Load test stand, all checkouts,
cooldown, fill, pump to 2K, Q vs E, start boiloff
warmup script (long day) This scenario
supports 3 tests per week, 2 different cavities,
one of which gets a 48hr 120 C bake between
tests.
12- Conclusions
- The aggressive test schedules described here can
be fully supported by a - cryostat/cryogenic system that provides
-
- LHe bath capable of operation between 4.3 and
1.6K - Cooldown rate from 300K to 4K that minimizes
Qdisease susceptibility (minimize time spent
between 100-150K) - Fast turnaround
- Cooldown fill 4-6 hours
- Pumpdown 2-4 hours (can be concurrent w/ fill
if not performing Q0 vs T measurements) - Remnant LHe boiloff 3-5 hours (150-180W for
800L) - Warmup to 300K 10-12 hours (400K He gas at
2-4g/s) - The present design will be shown to meet these
requirements. - Additionally, it does not preclude testing of
alternate cavity designs or - more extensive (RD) testing.
13Cryogenic System Requirements
14Cryogenic System Requirements
15IB1 Refrigeration Capability
- Calculated cooling capacity of 125 W at 2 K.
- Assumes 88-90 efficient J-T heat exchanger
pre-cooling the supplied LHe. This HX is
identical to one used in the MTF LHC quadrupole
feed box. - Assumes 3 Torr pressure drop through the pumping
line between the new test facility and the Kinney
pumps.
16ILCTA-IB1 Vertical Dewar PID
17Integration with IB1 Refrigerator
- LHe supplied across the roof of IB1 through the
existing transfer line from the 10 kl dewar.
Drawn off a phase separator, 5 K boiloff will
cool a dewar intercept and a baffle. - GHe pumped away via Kinney pumps, returned
directly to compressor suction, or vented to
atmosphere. The first option requires a new
pumping line, the last two options will use
existing VMTF piping. - LN2 supplied from 10 kgal dewar, tying into
existing VMTF piping. - GN2 vented to atmosphere, tying into existing
VMTF piping.
18Helium Vessel Thermal Design
- Heat load to 2 K helium bath is controlled 80 K
shield and heat intercepts at 80 K and 5 K level - 80 K shield and intercept will be cooled by LN2
- 5 K heat intercept will be cooled by GHe vapor
from phase separator, 10 W heater to control
vapor flow - Heat load to 2 K from other sources (pumping line
and instrumentations wired) will be estimated
later, however, it should be around 2 W or so
level
19Helium Vapor Pressure Drop
- The total vapor pressure drop will be about 3
torr and thats our design goal - 2 line is 150 ft and 6 line is 300 ft
- Total vapor pressure drop breaks down to three
parts in the pumping line in our calculation - Pressure drop within JT heat exchanger, lt 1 torr
- Pressure drop along 150 ft, 2 insulated piping,
3.5 K inlet and 5 K outlet, the average pressure
drop is 1.01 torr - Pressure drop along 300 ft, un-insulated 6
piping, 5 K inlet and 300 K outlet, the average
pressure drop is estimated to be 0.843 torr
20Cryostat Layout
21Helium Vessel
- ASME BPVC vessel
- Dimensions - 304SS shell
- 28-inch OD
- 0.094-inch thick
- Thickness driven by external pressure (due to
leak in insulating vacuum) - To minimize thickness ( conduction heat load)
use Stiffeners every 30-inch along length - L1X1X1/4-inch angle bent intermittently welded
- 16-feet long
22Helium Vessel (contd)
- Relief system
- Burst disc
- 65-psig set pressure
- 1.5-inch - Sized assuming complete helium
vaporization during leak of insulating vacuum
(resulting flux of 0.6 W/cm2) - Code Relief valve
- 50-psig set pressure
- Connected to top plate of removable insert (not
part of this assembly/procurement) - Heater for dewar warm-up
- Temperature of helium 420K
- Helium pressure 3-psig
23Top flange of helium vessel
- Thickness 1-inch
- Sized to ensure welded joint to the helium vessel
shell is adequate, following guidelines of ASME
BPVC
Top flange of Helium vessel
24Status of Documentation
- Engineering drawings
- 75 exist for initial design iteration
- Engineering notes
- Helium vessel 75 complete
- Vacuum vessel
- Pressure drop calculations
- Heat load analysis
- Relief valve sizing
- Technical specification for vendor (required at
the time the RFP is issued)
25Cost Estimate
26Procurement Plan
- Complete the Design of the Cryostat assembly and
release via. an RFP. Select the best qualified
vendor based on a technical evaluation of the
vendors proposal - not solely on lowest bid. - While cryostat Procurement is underway-
- Continue to work towards a final design of the
magnetic shielding and release these drawings for
fabrication (estimated del 6 weeks ARO) - Continue to work on the final design of the top
plate and suspension components and then release
these for fabrication - located a supplier of the Lead and has a quote
and estimated delivery (6 weeks ARO) - located a supplier for an encapsulant (rated for
4.5K use) which could be used on the exposed lead
surfaces
27Schedule