Title: Mitigation of Anomalies In CIDH Piles


1
Mitigation of Anomalies In CIDH Piles
  • Anomaly Identification
  • Design Concerns
  • Remediation Methods
  • Standard Mitigation Plan

One test is worth a thousand expert opinions...
Presented By Brian Liebich, P.E.
2
Mitigation Process
  • Anomaly Identification
  • Design Review
  • Contractor Plan
  • Review / Approval
  • Perform Repair
  • Evaluation

3
Mitigation of Anomalies in CIDH Piles
  • Anomaly Identification

One test is worth a thousand expert opinions...
4
Need for Non-Destructive Evaluation
  • Visual Observation Difficult / Inadequate
  • Structural Element Constructed Under Field
    Conditions
  • Critical Design Requirements

5
Non-Destructive Testing
  • Gamma-Gamma Logging Primary Method
  • Performance Evaluation for Homogeneity
  • Test Every Wet CIDH Pile

6
Sizing the Anomaly
  • Representative Sample / Proportional
    Apportionment
  • Can Use CSL to Further Define Anomaly

7
Mitigation of Anomalies in CIDH Piles
  • Design Concerns

One test is worth a thousand expert opinions...
8
Designer Involvement
  • Foundation Testing Knows Anomaly Location
  • Designers Know Importance of an Anomaly
  • Three Design Inputs Structural, Geotechnical,
    Corrosion

9
Structural
  • Usually Most Critical
  • Lateral / Shear Cannot be Transferred
  • Zone of Maximum Moment

10
Geotechnical
  • Significant Portion of Skin Friction Reduced
  • End Bearing Compromised
  • Axial Capacity Diminished

11
Corrosion
  • Corrosive Environment
  • Water Table Influence / Oxygen
  • Stray Current

12
Identify Critical Defects Quickly
13
Mitigation of Anomalies in CIDH Piles
  • Remediation Methods

One test is worth a thousand expert opinions...
14
Successful Repair
  • No One Size Fits All
  • Meets Design Requirements
  • Assurance of Repair
  • Timely Resolution

15
How Mitigation Methods are Selected
  • Contractor Selects
  • Mitigation Committee Approves
  • Competing Concerns Cost vs. Effectiveness

16
Mitigation Methodologies
  • Replacement / Supplement
  • Structural Bridging
  • Unearth and Recast
  • Pressure Grouting

17
Replace / Supplement
  • Based on Design Concerns
  • May not be Possible
  • Typically Most Expensive

18
Structural Bridging
  • Core Drill Hole
  • Insert Steel Supplement
  • Grout into Place

19
Unearth and Recast
  • Physical Replacement
  • Visual Inspection
  • Access and Restoration

20
Pressure Grouting
  • Gain Access Usually PVC
  • Wash and Clean Deleterious Material
  • Inject Grout

21
Field Inspection
  • Contractor Follows Plan
  • Washing Operations
  • Water Test Results
  • Grout Injection Volumes and Pressures

22
Downhole Camera
  • QA of Contractor Procedure
  • Verify Anomaly Type / Extent
  • Useful for Confirming Anomaly

23
Mitigation of Anomalies in CIDH Piles
  • Standard Mitigation Plan

One test is worth a thousand expert opinions...
24
ADSC Standard Mitigation Plan
  • No One Size Fits All But not Reinvent the
    Wheel
  • Cooperatively Developed ADSC - Caltrans
  • Accelerated Review of Repair Plans
  • Basic Repair (A) or Grouting (B)

25
Basic Repairs
  • Expose / Unearth
  • Chip Visible Anomaly
  • Recast
  • Restore Soil

26
Pressure Grouting
  • High-Pressure Water Jetting, Clean/Scour
  • Water Test for Grout Selection
  • Grouting Process Detailed
  • Flowchart

27
Mitigation of Anomalies In CIDH Piles
  • Anomaly Identification
  • Design Concerns
  • Remediation Methods
  • Standard Mitigation Plan

One test is worth a thousand expert opinions...