Title: Monthly 9_25 Page 1
1Monthly Status Report Report due 9/25/00 Schedule
statused as of Sep. 1, 2000
2Project Status Summary
Programmatic Jul Aug Sep
Resources Jul Aug Sep
Schedule Jul Aug Sep
Detailed Description (for items identified as
yellow or red)
- Over the last period we continued with flight
fabrication. We also delivered prototypes of ELS
and IMA to Europe as pathfinders for future
flight model testing. - A new concern surfaced over the last month. The
MCPs delivered to us from IRF for IMA had several
blemishes and stains. We sent these parts back
to IRF for further disposition. We are in the
process of updating our test flow / delivery to
reflect the uncertainty regarding the MCPs. - The manufacture of the high tolerance ELS parts
by an outside subcontractor continues to be a
concern. The late delivery of the parts will
likely effect final flight unit delivery - Latest project photos and videos are available
on Aspera-3 web site.
3Problem and Concern Summary
PProblem CConcern RResolved
4Accomplishments of the Last Month -ELS
- Received finished machined sets 1 and 2 from
Hyperfine. Parts do not meet spec but may be
acceptable as flight spare. - Hyperfine thinks they have determined the reason
for out of spec condition. Process will be
modified on set 3. - Parts were delivered to Walton Plating for UV
blackening. We have received the first (which is
the better machined) set back. Second set is
held up while Walton personnel are on vacation. - Started rough machining of a third set of parts
to supply to Hyperfine. - Delivered prototype ELS to MSSL to be used as a
pathfinder for flight and flight spare sensor
calibration. - Delivered ELS STM to IRF on 8/28/00.
- Both amp boards are complete, inspected and bench
tested.
5Accomplishments of the Last Month ELS (cont.)
- HVPS 1 is complete, inspected, bench tested and
characterized over temperature. HVPS 2 is
complete, inspected, bench tested and will be
characterized over temperature 9/22-9/25. - Electronics set 1 has been integrated together
and have completed functional and thermal test.
Electronics set 2 will be integrated,
functionally tested and thermal cycled starting
9/26. - Met with FMI (DPU and flight software lead)
following ASPERA-3 team meeting. We reviewed ELS
electrical interface, characterization of the DPU
over temperature, flight software and ELS data
compression techniques.
6Accomplishments of the Last Month - IMA
- Assembled flight and flight spare electronics for
thermal test (w/o MCPs). Completed test with no
anomalies. - Inspected flight MCPs in preparation for flight
assembly of both units. Identified several
blemishes and stains. Sent the MCPs back to
IRF for their disposition. - Have started discussions with IRF about potential
new plan where we deliver IMA electronics to IRF
sans MCPs. IRF assumes the responsibility for
MCP installation (with our support) and testing
after MCP installation. This change should not
effect our delivery date or budget.
7Accomplishments of the Last Month - Data
Reduction Software
- Began Addressing TBDs in the APAF Software
Development Plan (SDP), V1.1 - Will Release Version 1.2 November, 2000
- Began Updates to the APAF Project Data Management
Plan (PDMP), V1.0 per PDS Comments - Will Release Version 1.1 December, 2000
- Delivered APAF Data System Interface Document
(DSID), V1.0 to PDS - Waiting for Feedback
- APAF Software Requirements Documentation is
Currently on Hold Due to Lack of Information
Concerning ASPERA-3 Packet Definitions - Continued Providing Technical Assistance for EPO
Web Information - Continued Defining and Implementing IDFS Web
Tools - Provided Software Support for ELS
Characterization - Held monthly ASPERA-3 Software Status Meeting
(September 22, 2000)
8Planned Activities for the Next Month - ELS
- (Hopefully) receive MCP flight set 5 to complete
the order. - Finish rough machining set 3 parts. Deliver
parts to Hyperfine. Receive high tolerance parts
from Hyperfine. - Deliver parts to England for UV coating.
- Finish flight electronics 2 thermal test.
- Assemble flight spare unit.
- Begin flight spare unit characterization and high
voltage testing.
9Planned Activities for the Next Month - IMA
- Assemble flight and flight spare units with dummy
MCPs. - Perform vibe test on both units.
- Start vacuum testing beginning with high voltage
breakdown tests. - Begin characterization testing.
10Planned Activities for the Next Month - Data
Reduction Software Tasks
- Continue Providing Technical Assistance for EPO
Web Information - Continue Defining and Implementing IDFS Web Tools
- Continue Addressing TBDs in the APAF Software
Development Plan (SDP), V1.1 - Continue Updates to the APAF Project Data
Management Plan (PDMP), V1.0 - Begin Defining Packet Definitions for ELS
11Problem and Concern Status
- Alignment of ELS
- This remains our biggest concern. We have
received two sets of parts from Hyperfine. None
of the parts meet spec though they may be
acceptable as flight spare. We are rough
machining another set of parts for Hyperfine per
their new directions and process. The parts
will then be sent to Hyperfine for precision
machining. Walton Plating is shut down until Oct
10. We are shooting to have set 3 to Walton at
that time for UV blackening. The problems with
the machining and blackening will likely cause us
to slightly slip delivery of ELS. We have
discussed this with IRF MSSL. They do not see
any problems with slipping the delivery. We will
be discussing this officially with them and NASA
in the coming week. - Hyperfines theory on why the parts are out of
spec is that too little material was left for the
precision machining operation. The rough
machining since it was to near final dimensions
effected the grain structure of the part making
it impossible for Hyperfine to precision machine
the part to the specified tolerance. The rough
machining of the next set of parts will leave
much more material so that the grain structure is
not disturbed.
12Problem and Concern Status (cont.)
- IMA MCPs
- A new concern we inspected the IMA MCPs during
the last month and identified several blemishes
and stains. These plates were procured and
provided as CFE by IRF. We sent the plates back
to IRF for IRF to disposition. At IRFs
suggestion, we are looking at modifying our test
and delivery plan to deliver IMA to IRF without
MCPs. This places the responsibility for the
MCPs solely on IRF and protects our schedule and
budget. The proposed test plan (which will be
discussed with IRF and NASA) still has us
performing vibration, high voltage, and
characterization testing of both IMA units. We
will also support IRF post-delivery for MCP
installation and testing. The proposed plan does
not effect our delivery schedule or budget.
13 Schedule Summary
- ELS The manufacture of the high precision parts
to spec and the subsequent UV blackening is the
critical path on the schedule for delivery of the
flight unit. - We are currently updating the schedule to reflect
the latest knowledge about availability of
personnel and current plan for testing and
delivery. - Discussions with IRF / NASA / MSSL will continue
and will be finalized in the coming weeks.
14Schedule Summary (cont.)
- IMA Likewise, we are in the process of
updating our schedule to reflect the new proposed
plan for delivery of IMA. We feel confident that
we can still make the current delivery date under
the new plan and are still planning on a Pre-ship
Review the week of Nov. 13. The new schedule /
plan will be reported upon at the upcoming
Monthly Status Telcon. - Software activities continue to be on schedule.
- The full-up schedule is available on the ASPERA-3
Web site.
15ASPERA-3 PHASE B/C/D MASTER SCHEDULE