Monthly 9_25 Page 1 - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Monthly 9_25 Page 1

Description:

Over the last period we continued with flight fabrication. We also delivered prototypes of ELS and IMA to Europe ... A new concern surfaced over the last month. ... – PowerPoint PPT presentation

Number of Views:36
Avg rating:3.0/5.0
Slides: 16
Provided by: johnsc4
Category:
Tags: monthly | page | surfaced

less

Transcript and Presenter's Notes

Title: Monthly 9_25 Page 1


1
Monthly Status Report Report due 9/25/00 Schedule
statused as of Sep. 1, 2000
2
Project Status Summary
  • Technical
  • Jul Aug Sep

Programmatic Jul Aug Sep
Resources Jul Aug Sep
Schedule Jul Aug Sep
Detailed Description (for items identified as
yellow or red)
  • Over the last period we continued with flight
    fabrication. We also delivered prototypes of ELS
    and IMA to Europe as pathfinders for future
    flight model testing.
  • A new concern surfaced over the last month. The
    MCPs delivered to us from IRF for IMA had several
    blemishes and stains. We sent these parts back
    to IRF for further disposition. We are in the
    process of updating our test flow / delivery to
    reflect the uncertainty regarding the MCPs.
  • The manufacture of the high tolerance ELS parts
    by an outside subcontractor continues to be a
    concern. The late delivery of the parts will
    likely effect final flight unit delivery
  • Latest project photos and videos are available
    on Aspera-3 web site.

3
Problem and Concern Summary
PProblem CConcern RResolved
4
Accomplishments of the Last Month -ELS
  • Received finished machined sets 1 and 2 from
    Hyperfine. Parts do not meet spec but may be
    acceptable as flight spare.
  • Hyperfine thinks they have determined the reason
    for out of spec condition. Process will be
    modified on set 3.
  • Parts were delivered to Walton Plating for UV
    blackening. We have received the first (which is
    the better machined) set back. Second set is
    held up while Walton personnel are on vacation.
  • Started rough machining of a third set of parts
    to supply to Hyperfine.
  • Delivered prototype ELS to MSSL to be used as a
    pathfinder for flight and flight spare sensor
    calibration.
  • Delivered ELS STM to IRF on 8/28/00.
  • Both amp boards are complete, inspected and bench
    tested.

5
Accomplishments of the Last Month ELS (cont.)
  • HVPS 1 is complete, inspected, bench tested and
    characterized over temperature. HVPS 2 is
    complete, inspected, bench tested and will be
    characterized over temperature 9/22-9/25.
  • Electronics set 1 has been integrated together
    and have completed functional and thermal test.
    Electronics set 2 will be integrated,
    functionally tested and thermal cycled starting
    9/26.
  • Met with FMI (DPU and flight software lead)
    following ASPERA-3 team meeting. We reviewed ELS
    electrical interface, characterization of the DPU
    over temperature, flight software and ELS data
    compression techniques.

6
Accomplishments of the Last Month - IMA
  • Assembled flight and flight spare electronics for
    thermal test (w/o MCPs). Completed test with no
    anomalies.
  • Inspected flight MCPs in preparation for flight
    assembly of both units. Identified several
    blemishes and stains. Sent the MCPs back to
    IRF for their disposition.
  • Have started discussions with IRF about potential
    new plan where we deliver IMA electronics to IRF
    sans MCPs. IRF assumes the responsibility for
    MCP installation (with our support) and testing
    after MCP installation. This change should not
    effect our delivery date or budget.

7
Accomplishments of the Last Month - Data
Reduction Software
  • Began Addressing TBDs in the APAF Software
    Development Plan (SDP), V1.1
  • Will Release Version 1.2 November, 2000
  • Began Updates to the APAF Project Data Management
    Plan (PDMP), V1.0 per PDS Comments
  • Will Release Version 1.1 December, 2000
  • Delivered APAF Data System Interface Document
    (DSID), V1.0 to PDS
  • Waiting for Feedback
  • APAF Software Requirements Documentation is
    Currently on Hold Due to Lack of Information
    Concerning ASPERA-3 Packet Definitions
  • Continued Providing Technical Assistance for EPO
    Web Information
  • Continued Defining and Implementing IDFS Web
    Tools
  • Provided Software Support for ELS
    Characterization
  • Held monthly ASPERA-3 Software Status Meeting
    (September 22, 2000)

8
Planned Activities for the Next Month - ELS
  • (Hopefully) receive MCP flight set 5 to complete
    the order.
  • Finish rough machining set 3 parts. Deliver
    parts to Hyperfine. Receive high tolerance parts
    from Hyperfine.
  • Deliver parts to England for UV coating.
  • Finish flight electronics 2 thermal test.
  • Assemble flight spare unit.
  • Begin flight spare unit characterization and high
    voltage testing.

9
Planned Activities for the Next Month - IMA
  • Assemble flight and flight spare units with dummy
    MCPs.
  • Perform vibe test on both units.
  • Start vacuum testing beginning with high voltage
    breakdown tests.
  • Begin characterization testing.

10
Planned Activities for the Next Month - Data
Reduction Software Tasks
  • Continue Providing Technical Assistance for EPO
    Web Information
  • Continue Defining and Implementing IDFS Web Tools
  • Continue Addressing TBDs in the APAF Software
    Development Plan (SDP), V1.1
  • Continue Updates to the APAF Project Data
    Management Plan (PDMP), V1.0
  • Begin Defining Packet Definitions for ELS

11
Problem and Concern Status
  • Alignment of ELS
  • This remains our biggest concern. We have
    received two sets of parts from Hyperfine. None
    of the parts meet spec though they may be
    acceptable as flight spare. We are rough
    machining another set of parts for Hyperfine per
    their new directions and process. The parts
    will then be sent to Hyperfine for precision
    machining. Walton Plating is shut down until Oct
    10. We are shooting to have set 3 to Walton at
    that time for UV blackening. The problems with
    the machining and blackening will likely cause us
    to slightly slip delivery of ELS. We have
    discussed this with IRF MSSL. They do not see
    any problems with slipping the delivery. We will
    be discussing this officially with them and NASA
    in the coming week.
  • Hyperfines theory on why the parts are out of
    spec is that too little material was left for the
    precision machining operation. The rough
    machining since it was to near final dimensions
    effected the grain structure of the part making
    it impossible for Hyperfine to precision machine
    the part to the specified tolerance. The rough
    machining of the next set of parts will leave
    much more material so that the grain structure is
    not disturbed.

12
Problem and Concern Status (cont.)
  • IMA MCPs
  • A new concern we inspected the IMA MCPs during
    the last month and identified several blemishes
    and stains. These plates were procured and
    provided as CFE by IRF. We sent the plates back
    to IRF for IRF to disposition. At IRFs
    suggestion, we are looking at modifying our test
    and delivery plan to deliver IMA to IRF without
    MCPs. This places the responsibility for the
    MCPs solely on IRF and protects our schedule and
    budget. The proposed test plan (which will be
    discussed with IRF and NASA) still has us
    performing vibration, high voltage, and
    characterization testing of both IMA units. We
    will also support IRF post-delivery for MCP
    installation and testing. The proposed plan does
    not effect our delivery schedule or budget.

13
Schedule Summary
  • ELS The manufacture of the high precision parts
    to spec and the subsequent UV blackening is the
    critical path on the schedule for delivery of the
    flight unit.
  • We are currently updating the schedule to reflect
    the latest knowledge about availability of
    personnel and current plan for testing and
    delivery.
  • Discussions with IRF / NASA / MSSL will continue
    and will be finalized in the coming weeks.

14
Schedule Summary (cont.)
  • IMA Likewise, we are in the process of
    updating our schedule to reflect the new proposed
    plan for delivery of IMA. We feel confident that
    we can still make the current delivery date under
    the new plan and are still planning on a Pre-ship
    Review the week of Nov. 13. The new schedule /
    plan will be reported upon at the upcoming
    Monthly Status Telcon.
  • Software activities continue to be on schedule.
  • The full-up schedule is available on the ASPERA-3
    Web site.

15
ASPERA-3 PHASE B/C/D MASTER SCHEDULE
Write a Comment
User Comments (0)
About PowerShow.com