New Dawn Barge Grounding Hood River, OR - PowerPoint PPT Presentation

1 / 8
About This Presentation
Title:

New Dawn Barge Grounding Hood River, OR

Description:

Unified Command (UC) established and transitioned to Tidewater Office in Vancouver ... Need secondary / forward Command Post near actual site ... – PowerPoint PPT presentation

Number of Views:55
Avg rating:3.0/5.0
Slides: 9
Provided by: privateR
Category:
Tags: barge | dawn | grounding | hood | locations | new | office | post | river | us

less

Transcript and Presenter's Notes

Title: New Dawn Barge Grounding Hood River, OR


1
New Dawn Barge GroundingHood River, OR
  • Regional Response Team
  • Northwest Area Committee Meeting
  • Portland, OR
  • October 14-15, 2009

2
Tidewater New Dawn Barge GroundingHood River, OR
July 9
  • No notification to EPA by NRC. EPA notified by
    Tidewater at 650 AM
  • EPA FOSC dispatched to scene with START
    contractor
  • EPA made notifications internally and to other
    agencies - DOI, Tribes, NOAA NMFS, states, etc.
  • FOSC arrived SDS Lumber at White Salmon
    (temporary CP), met up briefed with OR, WA SOSCs

3
Tidewater New Dawn Barge GroundingHood River, OR
July 9
  • Early attempts to free barge failed
  • Attempt to raise river pool elevation thru US ACE
    dams and pull barge free unsuccessful
  • Discussion on bringing in another barge and
    lighter New Dawn

4
Tidewater New Dawn Barge GroundingHood River, OR
July 9
  • Questions on approach salvage vs response slowed
    jelling of Unified Command
  • With location / visibility of barge, potential
    from spill, need for lightering, media interest -
    became clear that response is ramping up
  • EPA requested another on-site OSC and PIO

5
Tidewater New Dawn Barge GroundingHood River, OR
July 9
  • Unified Command (UC) established and transitioned
    to Tidewater Office in Vancouver
  • EPA FOSC, WA OR SOSCs
  • Tidewater staffed most positions in UC Ops,
    Liaison, Logs, Finance
  • EPA lead PIO, excellent coord with Tidewater, OR
    WA PIOs
  • Media releases by USCG quick, accurate, UC then
    took on media lead
  • 3 media releases, TV interviews
  • Need for PIO at site

6
Tidewater New Dawn Barge GroundingUnified
Command (continued)
  • Unified Command
  • Developed River Security Plan
  • Security around vessel (County Sheriffs, USCG
    Auxiliary)
  • Use of GRPs Protection of downriver resources
    at risk
  • Downriver staging of Clean Rivers Coop and NRCS
    personnel equipment, boats, boom
  • NOAA help in spill modeling
  • Developed Lightering Plan
  • Operations, timing, volumes, etc.

7
Tidewater New Dawn Barge GroundingHood River, OR
July 10
  • Fuel lightered to another barge safely and
    successfully with no spills
  • 500,000 gallons transferred
  • USCG state oversight
  • Barge freed late on July 10. moved to nearby
    (SDS) dock
  • Re-inspected by USCG and Tidewater marine
    chemist, no damage. Underway to destination

8
Tidewater New Dawn Barge GroundingHood River, OR
July 10
  • Several Hotwashes by Agencies, Tidewater
  • Lessons Learned (many), highlights
  • Response and salvage successful no spills
  • Previous NPREP oil spill drills by Tidewater very
    helpful
  • UC successful
  • Salvage vs Response approach created stalled
    early jelling of UC - needs vetting by agencies
  • Media need covered well. Media releases
    consistent. Need for Public Information Officer
    (PIO) at UC earlier, also at site
  • Need secondary / forward Command Post near actual
    site
  • Communications and jurisdictional improvements
    and understandings needed between agencies
  • GRPs need updating