Title: TEAMwork Project (IST-2000-28162)
1TEAMwork Project (IST-2000-28162)
- Welcome to Review Meeting
- 25 June 2002,
- Valladolid, Spain
- Brian Foley
- Co-ordinator
- TEAMwork Project (IST-2000-28162)
2Structure of Presentation
- Presentation of meeting agenda
- Introduction to TEAMwork project and partners
- Overview of progress since 1 July, 2001
- Future work
3AGENDA
- 1. Presentation on the overall project
progress - (TecNet) (20)
- 2. Presentation on Deliverable D.2 - Methodology
- (ISCN) (15)
- 3. Presentation on Deliverable D.3 - Technology
- (ISCN) (15)
- 4. Demonstration of configured NQA
- (ISCN) (15)
- 5. Private meeting for Reviewers (30)
-
4AGENDA (Continued)
- 6. Presentation on the Validation and Evaluation
(WP4) plan (FGUVA) (15) - 7. Presentation on the planned social analysis
- (MTA SZTAKI) (15)
- 8. Presentation on the organisation of the
trials (WP4) - 8.1 Software Engineering QinetiQ and GMV (20)
- 8.2 Public Service Organisation FGUVA and APS
(20) - 8.3 Research Network Domain TecNet (15')
- 9. Private meeting for Reviewers (30)
5Introduction to TEAMworkThe Objectives
- Integration of three innovative approaches into a
complete - solution
- Application in three e-working domains
- Role-based team-working methodology for
effective - management and motivation of e-working teams
- Technology platform Adaptable and
- Configurable for effective virtual
decision-making
- Social skills analysis of user behaviour -
- develop a skills solution
6Introduction to TEAMworkThe Methodology
- A Methodology to improve the efficiency and
- effectiveness of organisations by
- Goal Analysis
- Efficient Team-Work
- Improved Infrastructure
- Aiming at a Continuous Learning Process and
Organisation. - http//www.victory-group.net
7Introduction to TEAMworkThe Technology
A Platform Adaptable and Configurable without
Change of Code
Public Service Organisations
(ISCN Partners)
(Hyperwave)
Web-Server
Research Networks
Knowledge Management
NQA Application Software
Software Engineering
8Introduction to TEAMworkThe Social Dimension
- Identify required skills, based on user
behaviour and - analysis
- - Social skills
- - Communication skills
9Introduction to TEAMworkThe Project Structure
Technology
Methodology Skills
Solution
Adapt
Integrate
Exploitation
Dissemination
Configurable
Feedback
Trials in three e-working
environments
10Introduction to TEAMworkThe Project Partnership
- User Domains
- Software Engineering
- - GMV (E)
- - QinetiQ (UK)
- Public Service
- - FGUVA (E)
- - APS (A)
- Research Networks
- - TecNet IOTs (Irl.)
- - Danube (A)
- - University of Maribor (Slo)
Provider / Support Team ISCN (Irl.) Hyperwave (D)
Support
Feedback
Social Analysis Team MTA SZTAKI (HU) BisDato (A)
11Introduction to TEAMworkProject Management
Structure
- Management Structure based on system of
Contractors and Members
University of Maribor
TecNet
Danube
QinetiQ
ISCN
GMV
FGUVA
Hyperwave
MTA SZTAKI
APS
Bisdato
12Progress Highlights (July 2001 June
2002)Workpackage Description
- WP1 Project Management
- WP2 Teamwork Analysis
- WP3 NQA Installation and Adaptation
- WP4 Validation and Evaluation
- WP5 Verification and Refinements
- WP6 Dissemination
- WP7 Exploitation
- WP8 Peer Review and Assessment
13Progress Highlights(July 2001 June 2002)
- WP1 (Project Management)
- Successful kick-off meeting
- Agreement on project planning
- Templates for managing the project developed
- NQA configured for project management (overall
project planning, work package planning, effort
reporting) - Partners reporting effort using NQA since
October, 2001 - Quarterly reports and Periodic Progress Report
submitted to PO on NQA
14Progress Highlights(July 2001 June 2002)
- WP2 (Teamwork Analysis using Bestregit )
- WP Plan produced
- Bestregit Training completed for all partners
- Analysis of scenarios in domains
- Software Engineering
- Public Service Organisation
- Research Networks
- Synergies between scenarios identified and
exploited - Sub-deliverables integrated into Deliverable 2
- Submitted to PO on 14 December, 2001 using NQA
15Progress Highlights(July 2001 June 2002)
- WP3 (NQA installation and configuration)
- Four servers successfully installed
- Configured with all scenarios
- Training programme for Users, Quality Manager
and Administrator undertaken in January 2002 - D.3 produced with training materials
- Scenario-specific training offered to users
16Progress Highlights(July 2001 June 2002)
- WP4 (Validation and Evaluation
- WP Plan produced
- Trials organised in three domains
- Questionnaires finalised
- Evaluation of Methodology, Technology, Social and
Cultural factors - End-users trained and ready to go
- Trials in RND started in June
17Progress Highlights(July 2001 June 2002)
- WP5 Verification and Refinements
- Work has started already
- Early feedback from users in Graz
- Specification document provided to Hyperwave
- Additional refinement after WP4 is complete
- Methodology refinement taking account of
differences between D.2 and D.3
18Progress Highlights(July 2001 June 2002)
- WP6 (Dissemination)
- WP Plan produced
- Project Website developed (www.euteamwork.net)
- Details of project disseminated widely
- Concertation meetings Brussels (June 2001 and
2002) - Presentation at EuroSPI 2001
- Presentation to IRC network
- Presentation at e2001 Venice
- Presentation at IST WISTCIS meeting
- Presentation at Baltic ITT conference, TELEBALT
Forum - TII annual conference, Turin.
- Papers submitted to conferences and publications
- Support of EU acknowledged
19Progress Highlights(July 2001 June 2002)
- WP7 (Exploitation)
- Discussion document prepared and discussed by
partners - Work package plan produced
- Draft Exploitation Plan being
- developed
- - Contact with other projects clusters and
Expressions of Interest in FP6
20Progress Highlights(July 2001 June 2002)
- WP8 (Peer Review and Assessment)
- Nominations received from all Partners for Peer
Assessment Team - Chairman of Peer Assessment Team briefed on
Project Progress in January, 2002 - Report and non conformance reports completed
- Partners are currently demonstrating NQA and
briefing Peer Assessors - Next Peer Assessment report to be completed in
July / August
21Future WorkJuly December, 2002
- Undertake Trials in July, August and September
- Capture end-user evaluations through
questionnaires and interview (methodology,
technology and social analysis) - Write domain-specific reports
- Analyse social and cultural differences
- Produce D.4
- Verify and Refine (WP5)
- Continue Dissemination activities (WP6)
- Develop Exploitation Plan (WP7)
- Continue Peer Review and Assessment (WP8)
22TEAMwork IST-2000-28162
-
- Thank you for your attention!