Title: EVALUATION OF NEW MODELS FOR SIMULATING EMBANKMENT DAM BREACH
1EVALUATION OF NEW MODELS FOR SIMULATING
EMBANKMENT DAM BREACH
- Tony L. Wahl
- Bureau of Reclamation Denver, CO
2What is CEATI International?
- Since 1891, the Canadian Electrical Association
(CEA) has been the forum for electrical business
in Canada - In 1974, CEA initiated its RD Program to serve
the research needs of Canadian electric utilities - In 1998, CEAs RD Program opened its doors to
international participation - In 2001, CEA Technologies Inc. (CEATI) was
separated from the Canadian Electrical
Association - CEATI International is now the Centre for Energy
Advancement through Technological Innovation
3(No Transcript)
4Interest Groups
- 14 Interest Groups in the areas of electrical
energy - Generation
- Transmission
- Distribution
- Utilization
- Dam Safety Interest Group
- About 40 dam owners
- Jointly sponsors research development projects
- Participants from Canada, the United States,
Europe, Australia, and New Zealand
5Dam Safety Interest Group (DSIG)
- Areas of Interest
- Risk assessment for dam safety
- The use of geophysical methods in the diagnostics
and monitoring of embankment dams - Erosion and piping in dams
- Reliability of discharge facilities
- Ice loadings
- Probability (frequency) of extremefloods
- Emergency preparedness
- Testing of embedded dam anchors
6Dam-Break Modeling Recent History
- Lethal Dam Failures in 1970s
- Canyon Lake
- Kelly Barnes
- Laurel Run
- Buffalo Creek
- Teton
- 1977 DAMBRK model developed
- Could route peak breach outflows to determine
inundation depths, flood consequences - Could determine peak breach outflow, given a
description of how a breach would develop
7Modeling Breach Development
- Concrete dam failure modes (sliding, overturning,
structural) are usually instantaneous and
complete - Embankment dam failures usually involve erosion,
which takes time and depends on many factors - Regression equations to relate breach parameters
to dam and reservoir characteristics - Many developed in 1980s and refined in 1990s
- Adequate for cases in which the area of interest
was in the far-field - Too crude for the near-field
8Physically-Based Breach Modeling
- Dr. Danny Fread recognizedneed for modeling
erosionprocesses to obtain betterresults in
near field - May 18, 1980 eruption ofMt. St. Helens
createdlandslide dam on Toutle River - Dr. Fread developed NWS-BREACH model to analyze
possible breach of this dam - NWS-BREACH released to public in 1988
9Modeling Developments in 1990s
- Flood routing capabilities much improved
- 2D modeling
- Integration with GIS to improve consequence
analysis - Little change in breach modeling during this time
10CEATI Dam Erosion and Breach Project
- Since 2001 the DSIG has had an interest in
improving the tools used to model embankment dam
erosion and breaching - Key Questions
- Will a dam breach?
- What is the outflow hydrograph?
- What is the warning time?
- Available methods mostly unchanged since late
1980s - Regression models for predicting peak outflow
- Regression models for predicting breach
parameters - Breach erosion models, such as NWS-BREACH
11Shortcomings of Available Methods
- Regression models for peak outflow
- No aid in determining whether breach occurs
- Little detail about hydrograph shape or warning
time - Regression models for predicting breach
parameters - Uncertainties are large, especially for time
parameters - Breach initiation time
- Breach formation time
- Breach erosion models (e.g. NWS-BREACH)
- Used sediment transport equations, not true
erosion models - Poor modeling of erosion of cohesive materials
12Large-Scale Physical Tests
- Since 2000, many organizations have been
performing small-scale and some large-scale
embankment breach tests - European IMPACT Project (22 lab tests and
sponsorship of Norwegian field tests) - Norwegian tests (23 lab tests, 5 field tests of
6-m-high dams) - Agricultural Research Service (7 overtopping
tests and 4 piping tests of 2-m-high dams) - New breach erosion models under development
- Physically-based simulation of erosion processes
- Better modeling of the erosion of cohesive soils
13Project Objectives
- Dam breach erosion project was initiated in 2004,
with a focus on erosion and breach processes and
prediction of breach outflow hydrographs at the
dam - We want to develop physically-based models for
overtopping erosion and internal erosion leading
to dam breach and facilitate the integration of
those technologies into existing flood routing
tools like HEC-RAS, MIKE11, Telemac, InfoWorks,
etc.
14Participants
- Electricité de France
- Case studieserodimeter and piping erosion
research - Hydro Québec / Ecolé Polytechnique Montréal
- Numerical modeling of dam breach, development of
Firebird breach model - Bureau of Reclamation
- Laboratory testinginvestigate erodimeters
- Agricultural Research Service
- Large-scale laboratory testing and development of
SIMBA/WinDAM models - HR Wallingford
- Large-scale testing (IMPACT project), developers
of HR-BREACH model - US Army Corps of Engineers
- Integration of breach modeling technology into
HEC-RAS suite - Elforsk AB
- Model evaluation
- Other interested parties and sponsors
- BC Hydro, Churchill Falls, Elforsk AB, EoN
Vasserkraft, Great Lakes Power, Manitoba Hydro,
New York Power Authority, Ontario Power
Generation, Seattle City Light, Scottish
Southern Energy, National Weather Service
15Project Overview
- Phase 1 Information Gathering
- Reviewed and assembled case-study and large-scale
laboratory test data - Reviewed and identified numerical models under
development - Phase 2 Model Development and Implementation
- Phase 3 Model Enhancement
16Tasks in Phase 2
- Evaluation of three numerical breach models
- SIMBA (ARS)
- HR-BREACH (HR Wallingford)
- FIREBIRD BREACH (Montreal Polytechnic)
- Evaluation of methods for quantifying erodibility
of cohesive embankment materials - leading to
- Integration of breach modeling technologies into
HEC-RAS dynamic routing model - Potential efforts to facilitate integration with
commercial flood routing models
17The Models Common Characteristics
- Models are all physically-based
- Models utilize quantitative input parameters
describing erodibility of cohesive materials - Models are intended to perform well without
specific calibration to a particular case - Models are not computationally intensive
18The Models
- SIMBA Simplified Breach Analysis (USDA-ARS)
- Simulates breach by overtopping of homogeneous
earth embankments with negligible protection on
the downstream face - Four stage failure process
- surface erosion leading to development of a
headcut on the downstream face of the embankment - headcut advance through the crest to initiate the
breach - breach formation as the headcut advances into the
reservoir - breach expansion during reservoir drawdown
- Erosion formulas are fixed and most calibration
factors have been determined from lab testing.
Complete model is not calibrated to any specific
data set.
19The Models
- HR BREACH (HR Wallingford)
- Overtopping or piping-induced breach of cohesive,
non cohesive and simple composite (i.e. zoned)
structures. - Simulated processes
- Initial erosion of embankment surface protection
(grass or rock cover) - Headcut erosion through embankment
- Potential failure of breach side slopes by shear
or bending - Potential for sliding or overturning of core
section - Limited selection of erosion formulas
- Not calibrated to any specific data set
20The Models
- FIREBIRD BREACH (Montreal Polytechnic)
- Overtopping-induced breach of homogeneous
earthfill or rockfill dams - One dimensional unsteady flow, St. Venant
equations coupled with sediment continuity - Able to handle transcritical flows
- Side slopes are evaluated for ability to resist
sliding along a simple inclined face - Choice of erosion formulas
- Can be more computationally intensive
21Model Evaluation
- Evaluate model performance against large-scale
laboratory tests and case-study data - 2 ARS outdoor laboratory tests 2.3-m high
homogeneous dams, overtopping 1 breach, 1
non-breach - 3 overtopping breach tests performed in Norway
during the IMPACT project (5- to 6-m high dams) - homogeneous clay
- homogeneous gravel
- zoned embankment
- 2 real dam failures
- Oros (Brazil)
- Banqiao (China)
22ARS Tests
- Two overtopped embankments, 2.3 m high
- SM Silty Sand, complete breach in 51 minutes
- CL Lean Clay, headcut damage, but no breach after
20 hours - 2.5 orders of magnitudedifference in erodibility
ofmaterials - Constant inflow, smallreservoir
- Hanson, G.J., Cook, K.R., Hunt, S. 2005. Physical
modeling of overtopping erosion and breach
formation of cohesive embankments. Transactions
of the ASAE, 48(5)1783-1794.
23Norwegian Tests - Part of IMPACT
- Three overtopped embankments, 5 to 6 m high
- Homogeneous clay, placed very wet
- Homogeneous gravel, surface frozen
- Zoned rockfill with moraine core
- Inflow regulated at upstream reservoir
- Clay dam Peak inflow arrivedshortly after
initial breachreservoir level went back
uppeak outflow driven by peakinflow - Flow regulation not attempted forgravel dam test
- Inflow was too little, too latefor zoned test
24Oros Dam (Brazil, 1960)
- 35-m high dam, failed by overtopping during
construction - Core material probably a Sandy Lean Clay, with
PI10 - Well-compacted, except maybe last lifts
25(No Transcript)
26Oros Dam - Summary
- Thick, erosion-resistant embankment, large
reservoir - Slow erosion
- 12 hrs to initiate breach
- 6.5 to 12 hrs to form breach and drain reservoir
27Banqiao Dam (China, 1975)
- Hand-built dam with homogeneous earth shells and
clay core wall of arenaceous shale - Assumed to be poorly compacted and highly
erodible - 1 hr breach initiation
- 2 to 2.5 hrs to fully form breach
28Evaluation Criteria
- Evaluate performance using
- initial inputs (best available information and
judgment) - optimized inputs
- Objective criteria
- Time to initiate breach (erode through crest)
- Time to form breach (reach full width)
- Final breach width
- Breach widening rate
- Peak outflow
- Subjective criteria
- Do models exhibit appropriate sensitivity?
- Ease of determining input data and selecting
parameters - Ease of operation
29Current Status
- Team met at last years USSD meeting in Portland
- Members have been working this summer to perform
the evaluation runs - Group will meet again later this week to compare
results and try to reach consensus on - Which models and model components are working
well? - What technologies are presently ready to be
integrated into state-of-the-art models? - Where is more work needed?
- SIMBA and HR-BREACH models are being integrated
into USDA WinDAM and Wallingford Software
InfoWorks products
30Challenges
- TIME Too many models, cases, scenarios
- Each case study presents unique evaluation
challenges - Real failures have questions about dam materials
and erodibility, and about observed breach and
outflow characteristics - Lab tests have real-world logistical
complications and limitations related to
reservoir size - Failure to accurately model breach initiation
phase can require judgment to evaluate how well
the model reproduced later stages of the breach
process - Evaluation process has already been extremely
valuable
31(No Transcript)
32CEATI InformationChris HayesDirector, Business
Development1155 Metcalfe St., Suite
1120Montreal, QC H3B 2V6 (514) 866-5377
www.ceatech.ca info_at_ceatech.ca