Title: Gearing Up for Erate Year 5
1Gearing Up for E-rate Year 5
- Technology Coordinators Videoconference
- December 5, 2001
2E-rate starts Kindergarten
3Todays Lesson Plan
- Year 5 dates to remember
- Forthcoming MiCTA contracts
- New notification letters
- Things made easier (so they say)
- Not-so-easy Kindergarten Math
- Year 5 tidbits
- Pre-K tidbits
- Supply and Demand
4Year 5 Dates
- July 1, 2002 - June 30, 2003 (Blue)
- Form 471 application window
- Noon, Monday, November 5, 2001 through 1159PM
Thursday, January 17, 2002 - Forms 470 must be posted by Dec. 20, 2001
- CIPA compliance must be in place by July 1, 2002
if you certified that you were attempting to
comply with CIPA in Year 4
5MiCTA Contracts
- Michigan collaborated with MiCTA once again to
establish a statewide master contract for
Internal Connections - Will result in a statewide Form 470
- Contracts will be good for three years (USF
funding years 5, 6 and 7) - Contracts will be posted to MiCTA web site as
soon as they become finalized
6New Notification Letters
- Form 486 Notification Letter
- Currently under development at the SLD to confirm
receipt of your Form 486 - Form 500 Notification Letter
- Currently under development at the SLD to confirm
receipt of your Form 500
7Things Made Easier(So they say)
- SPIN Changes
- Change is allowed under state local procurement
laws - Change is allowed under terms of contract
- Original Service Provider (SP) has been notified
of the intent to make change
Thanks to the Copan ruling!
8Things Made Easier
- Product and Service Substitutions
- 1-to-1 changes no longer required
- Does not have to be initiated by the SP
- Same functionality now more broadly interpreted
9Things Made Easier
- E-certification
- Now operational for Form 470 and 471
- Applicant must apply for User ID and PIN
- PINs assigned only to those individuals who have
hand-signed Forms 471 and 486 that have been data
entered at SLD - User ID and PIN will reside with the person,
not an entity
10Things Made Easier
- Forms to have E-cert capability
- 470 - Services Requested
- 471 - Services Ordered
- 486 - Services Confirmed
- 500 - Service Change
- 472 (BEAR) - Applicant Invoice
- Refer to SLDs E-certification Update
presentation on MIN and Merit web sites
11Things Made Easier
- FCC Deadline Extensions
- Deadline for delivery and installation of
non-recurring services is the Sept. 30 that
follows the June 30 close of the relevant funding
year - Non-recurring services may be delivered through
Sept. 30 of the following calendar year if
certain decisions (e.g., FCDL SP change
approved ) are issued after March 1
12Things Made Easier
- Item 21 Attachments
- May be sent to the SLD after the Jan. 17, 2002
Year 5 Form 471 postmark deadline - Must be received by the SLD within a reasonable
timeframe - Form 471 must still be filed electronically and
certified by Jan. 17, 2002 - Your Form 471 application cannot be processed
until Item 21 Attachments are received - Label as Item 21 Attachment with Form 471 app
13Things Made Easier
- Block 4 Worksheets
- You can now copy Block 4 Worksheets from
application to application within the Funding
Year - You can now copy Block 4 Worksheets from Funding
Year 4 to Funding Year 5 - Simplifies online filing!
14Kindergarten Math
- One-time off-premise charges of 500,000 or
more must be amortized over at least three (3)
years - On-premise equipment lease costs cannot exceed
67 of funding amount requested to acquire
services - 500,000 eqpmt 60,000 recurring 560,000
- 500,000/560,000 89 which is gt 67
15Kindergarten Math
- 30 percent rules still in effect
- If more than 30 of a funding request is for
ineligible services, the entire request will be
denied - If more than 30 of a telecommunication or
Internet access request is deemed as internal
connections, the entire request will be turned
into internal connections and most likely not
funded
16Year 5 Tidbits
- Original signature requirement eliminated
- Photocopied signature or signature stamp allowed
- New materials on Reference Area of SLD web
site - Administrative Offices and Buildings Fact
Sheet - Calculating Your Discount section
- Demonstrating Compliance with Program Rules
section (new!)
17Year 5 Tidbits
- Eligible Services List - revised Oct. 19, 2001
- Tiptoeing Through the E-rate Minefield
- Entertaining article (satire) on the E-rate
program - http//www.andmore.com/Tiptoeing20through20the2
0e-rate20minefield.html
18Pre-K Tidbits
- Technology Plans
- Required for anything beyond POTS
- Watch out for approval expiration dates
- Entire consortium will likely not be penalized
due to lapse in approval or lack of a tech plan
by one member (reference FCC LOA appeal and Form
479 instructions)
19Pre-K Tidbits
- BEAR Deadlines
- PY4
- Due 90 days after the vendors 486 notification
letter - PY3
- Consider deadline to be 3 months after submitting
your PY3 Form 486 (since there are no 486
notification letters to applicants for PY3)
20Pre-K Tidbits
- Free Filtering Service
- We-Blocker
- Same capabilities as N2H2 genre (on a limited use
basis) - Is claimed to meet CIPA requirements
- Telecommunications Carriers List
- http//gullfoss2.fcc.gov/cib/form499/499a.cfm
- Not all telecom carriers are common carriers
21Supply and Demand
- Number of applications has steadily increased
over the life of the USF program
22Supply and Demand
- Total discount dollars funded to applicants
reached program cap in Years 2 and 3
23Supply and Demand
- Michigan schools and libraries have benefited
from the E-rate program to the tune of 260
million over the past 4 years - Not an easy way to earn a buck, but there are
definitely to try and go after
24Resources
- Resources to go to for assistance
- www.sl.universalservice.org
- www.state.mi.us/cio/min
- www.merit.edu
- www.micta.org
- http//www.dpi.state.wi.us/dlcl/pld/cipafaq.html
- Ask your E-rate Training Coordinator
25Time for Recess!
- Laurie Taylor
- Michigan Information Network
- 517.241.1642
- taylorL4_at_michigan.gov