Title: Constraint


1
Constraint
  • Richard Ford
  • UK Grid Connections Manager
  • Renewable Energy Systems

2
Definitions
  • Constraint
  • Not enough network
  • Location specific
  • Winter evenings?
  • Compensation
  • Requires
  • Network investment
  • Curtailment
  • Not enough demand
  • System-wide
  • Summer nights?
  • No compensation
  • Requires
  • Interconnectors
  • Storage

3
If there are constraints on the network
  • When will they be lifted?
  • How will they be applied?
  • Should there be compensation?

4
  • Given sufficient network investment, all
    generators can receive firm access and
    constraints can be zero.
  • This may not be the optimum economic solution.
  • Interaction between Network Owner and Network
    Operator costs

5
  • Generators should be given the opportunity to
  • offer prices for constrained running
  • be paid when constraints are instructed
  • Otherwise
  • No signal for network reinforcement
  • Distortion of energy market

6
Non firm access
  • Delay connection of the generator until any
    network reinforcements are complete
  • Connect generator without consideration of
    network reinforcements
  • Connect generator on a partially firm basis with
    fully firm connection once network reinforcements
    are complete.
  • Allow connection of generator on a non firm basis
    (i.e. no constraint payments) without a firm
    deadline for the connection to be made fully firm.

7
Non firm access
  • Delay connection of the generator until any
    network reinforcements are complete
  • GB approach
  • Connect generator without consideration of
    network reinforcements
  • Connect and manage
  • Connect generator on a partially firm basis with
    fully firm connection once network reinforcements
    are complete.
  • ROI approach
  • Allow connection of generator on a non firm basis
    (i.e. no constraint payments) without a firm
    deadline for the connection to be made fully
    firm.
  • NI approach