Title: Need to Align Publication of Standards and SW Blocking
1Need to Align Publication of Standardsand SW
Blocking
- Dave Couturier
- April 6, 2005
2Problem
- System Implementers need Standards and SWBlocking
Cycles Aligned - Some Block TV-1s Have Old Versions of Standards
- Some Standards are Published Well Into Execution
Phase - ICPs and SCCs Need to be Managed for SWB Blocks
3TV-1 Revision Frequency
- SW Blocking
- New Requirements Every 18 Months
- New SW Fielded Every 18 Months
- Standards
- New VMF Every 2 Years
- New USMTF Every 1 Year
- 6016 Every 16 to 30 Months
- 47001
- 188-220
- 2525 Every TBD
4Software Blocking Planning Schedule
4/05
6/02
9/01
Block 1 Execution
Prepare
10/06
12/03
06/02
Block 2 Execution
Preparation
04/08
04/05
12/03
Block 3 Execution
Preparation
10/09
10/06
04/05
Block 4 Execution
Preparation
04/08
04/011
10/06
Block 5 Execution
Preparation
10/12
10/09
04/08
Block 6 Execution
Preparation
5Comparison of SW Blocks Standards Published
Dates Execution Phase
6Comparison of SW Blocks Standards Published
Dates Preparation Phase
7Architecture ProductsFlow and Schedule
Oper. Activityto Syst. Function Traceability
Matrix SV-5
5/31/04 D 7/30/04 P9/30/04 F
High Level Operational Concept OV-1
Overview and Summary Information AV-1
IntegratedDictionary AV-2
10/1 D
Integrated Data Environment
6/1 D9/1 F
10/30 D 12/30 F
High Level Operational Mission Threads OV-2
10/31 F
9/30 D
Activity Model OV-5
10/30 D12/30 F
Data FlowDiag.
Operational Information Exchanges OV-3
Logical Data Model OV-7
Physical Data Model SV-11
5/31/04 D 7/30/04 P9/30/04 F
9/30 D12/30 F
5/31/04 D 7/30/04 P9/30/04 F
System Interface Description/Matrix SV1/SV-3PITM
Detailed System Interface Matrix SV-6
8/29 D9/30 F
Shortfall Analyses
8/8 QL9/29 D
System Mission Threads SV-7
5/31/04 D 7/30/04 P9/30/04 F
5/31/04 D 7/30/04 P9/30/04 F
SWB
System Commo.Desc. SV-2
Detailed Operational Mission Threads OV-6c
9/10 F
9/30 D12/30 F
System Standards Specifications Profile TV-1 PI
SM
System/Programs
Detailed System Mission Threads SV-10c
9/10 F
5/31/04 D 7/30/04 P9/30/04 F
Block Standards Specifications Profile TV-1
D DraftP PreliminaryF FinalQL
Quick Look
8Potential SWB4 Standard Versions
18 Months
Need to Develop a Standards Publishing Schedule
To Align With A Standard SWB Schedule
9Recommendations
- Work with Standards Groups to Get Standards
Published within the Preparation Phase of
Implementing Block - Limit Changes (e.g. ICPs, SCCs, CPs) with a
Cut-off Date Early in the Execution Phase