Plow Residential Streets Using Non-Traditional Techniques and Save Money - PowerPoint PPT Presentation

1 / 26
About This Presentation
Title:

Plow Residential Streets Using Non-Traditional Techniques and Save Money

Description:

... handoutMaster1.xml ppt/theme/theme1.xml ppt/media/image6.jpeg ppt/media ... theme3.xml ppt/media/image1.jpeg ppt/media/image2.png ppt/media/image10. ... – PowerPoint PPT presentation

Number of Views:109
Avg rating:3.0/5.0
Slides: 27
Provided by: westernsn
Category:

less

Transcript and Presenter's Notes

Title: Plow Residential Streets Using Non-Traditional Techniques and Save Money


1
Plow Residential Streets Using Non-Traditional
Techniques and Save Money
  • APWA WESTERN SNOW AND ICE CONFERENCE
  • Estes Park, Colorado
  • September 23, 2008

2
Loveland Facts and Figures
3
Loveland Facts and Figures
  • 65,000 population
  • 36 inches of snowfall per year, average
  • 12 snow events per year, average
  • November 6.8 inches
  • December 6.4 inches
  • January 6.0 inches
  • March 5.6 inches
  • February 5.0 inches
  • April 4.0 inches
  • City street network totals 358 centerline miles
  • Priority One arterials 70 c/l miles 20
  • Priority Two collectors 133 c/l miles 37
  • Priority Three residentials 155 c/l miles
    43

4
Loveland Facts and Figures
  • PRIMARY SNOW EQUIPMENT
  • 16 truck plows
  • 11 w/ salt spreaders
  • 5 w/ MgCl anti-icers
  • 5 pickup plows
  • 3 wheel loaders with plows
  • 1 road grader
  • 1 loader-mounted snow blower 1800
    tons/hr
  • 1 sidewalk tractor w/ plow, broom
    blower

5
Snow fighting Chemicals Used
  • Ice Slicer average 1,500 tons per year
  • Apex average 160,000 gallons per year

6
General Snow fighting Operations
  • 5 anti-icing trucks are deployed 3-5 hours before
    the storm to delay ice formation on pavements.
  • When snow starts falling, all plow trucks are
    deployed.
  • We start deicing, as needed.
  • We operate 24/7 until
  • streets are safe our
  • downtown district is
  • cleaned up.
  • Two 12-hour shifts.
  • Utilize employees from
  • 8 other City divisions.

7
December 2006 February 2007Mother of All
Winters
8
December 2006 February 2007Mother of All
Winters
  • Within a 16-day period, over 80 inches of snow
    fell in some areas of Front Range.
  • Snowed every week for 6 weeks straight.
  • On December 20th, Holiday Blizzard I powerful
    blizzard affected the Front Range and eastern
    plains of Colorado and surrounding states.
  • Up to 3 feet fell along the Front Range from
    Pueblo to Fort Collins.
  • Interstate and state highways were closed.
  • Denver International Airport was closed down for
    two days, causing a significant ripple affect
    across the U.S..

9
December 2006 February 2007Mother of All
Winters
  • On December 28th - 29th, Holiday Blizzard II
    dropped another 8 24 inches along Front Range,
    with strong winds.
  • Much of the state was declared a federal disaster
    area.
  • Tens of thousands of livestock were killed.
  • Hay drops were implemented helicopters were
    deployed to break the ice on stock tanks.
  • On January 4th - 5th, Holiday Blizzard III
    yet another 12 inches.

http//www.drovers.com/news_editorial.asp?pgID715
ed_id3983
10
December 2006 February 2007Lovelands Woes
  • On December 20th-21st , 25 inches fell with
    strong winds, 4-6 foot drifts and cold temps.
  • This was a record-breaking storm for December.
  • By early pm on December 21st, Priority 1 and 2
    streets were plowed we then started plowing
    Priority 3 residentials.
  • With snow 2-3 feet deep, our plow trucks and
    contract road graders became stuck dozens of
    times. Very slow going..
  • Our trucks and graders left behind 3-4 foot
    windrows which blocked all driveways.

11
December 2006-February 2007Lovelands Woes
  • Because it was slow going and we blocked
    driveways the phones started ringing. Up to
    800 calls per day!
  • We asked the local construction community for
    help in dealing with this emergency situation.
  • By December 27 one week later nearly all
    residentials were either plowed and/or passable.
  • IMPORTANT POINT residentials that saw a plow
    early on were mostly down to bare pavement.
    Those plowed a few days later were, at best,
    ice-packed and rutted.

12
December 2006 February 2007Lovelands Woes
  • On December 28th, we received another 8-14
    inches, and we started all over with Priority 1s,
    2s and finally 3s again.
  • It snowed each of the next four weekends, for a
    total of six weeks in a row.
  • Due to cold temps, our plows could not pop the
    bonded ice loose the plows just chattered over
    the top. Road graders worked only slightly
    better.
  • On these last-plowed streets, the norm was
    severe icepack and deep ruts, ice potholes, and
    very slick surfaces.

13
December 2006 February 2007Lovelands Woes
  • Beginning early January, contractors and City
    crews loaded and hauled many hundreds of
    truckloads of snow/ice from our arterial and
    collector roads and business districts.

14
December 2006 February 2007Mother of All
Winters
  • In late January, we again attempted to plow off
    ice and ruts from our 140 residential miles, by
    deploying 20 contract graders and 25 frontend
    loaders.

15
December 2006 February 2007Lovelands Woes
  • With over 50 inches of combined snows and
    resulting snow piles and blocked gutters, we had
    DRAINAGE PROBLEMS EVERYWHERE!
  • Only two solutions load/haul from key
    locations, and hope for a warm-up.
  • Ultimately, temps warmed up, we could plow off
    the snow/ice, and drainage finally under-cut the
    piled snow banks.

16
December 2006 February 2007Mother of All
Winters
  • The Cost?
  • 500,000 spent on plowing contractors 100/hour
    average.
  • 250,000 spent on loading/hauling, traffic
    control.
  • Untold curb/concrete damage throughout town from
    heavy equipment.
  • Untold asphalt damage throughout town from
    never-ending freeze-thaw cycle.
  • Bruised egos and frayed nerves.

17
Lessons Learned?
  • Our arterial/collector S I program works quite
    well. However, our Achilles Heel is our
    residential plowing program.
  • Must plow fresh snow!! Waiting too long causes
    it to become packed down by traffic, and then
    freeze tightly to pavement.
  • Must plow all streets simultaneously, and
    continue to plow as needed.
  • Heavy equipment contractors are unfamiliar with
    the residential street network miss too many
    streets and even entire neighborhoods.

18
My hopefully not-so crazy idea?
  • Put snowplows on trash trucks.

19
Why might this be better than using heavy
equipment contractors?
  • Its already being done in several cities NYC,
    Chicago, Milwaukee, etc.
  • We have a ready fleet of 20 trash and recycling
    trucks sitting in our yard.
  • We have equipment operators for every one of
    these trucks.
  • These residential trash and recycling operators
    know our street network better than anyone.

www.innogize.com/adrian/tz/archive/2006/02/
20
Trash truck plows versus heavy equipment
contractors
  • With 10 plow-equipped trash trucks, it would take
    approximately 4 hours to plow the center 1/3 of
    our 288 miles of collectors/residentials i.e.
    576 plow-miles _at_ two passes.
  • Assumes each truck could average 15 mph.
  • Each operator would drive his normal collection
    routes, plowing left to right, eventually plowing
    both sides of each street.

21
Trash truck plowing
  • Timing of each snowfall would dictate our
    strategy
  • If an overnight snowfall, trash crews would plow
    residentials first, then unhook plows and resume
    their normal collections.
  • If a daytime snowfall, crews would complete their
    normal daily collections, then hook up plows and
    plow residentials.
  • Collections are performed Monday-Thursday, so
    snowfalls on Fridays, Saturdays and Sundays,
    would not impact collections.

22
Cost Comparison
  • Grader/loader contractors typically charge about
    100 per hour.
  • Our estimated cost for each trash truck plow and
    operator is 60 per hour.
  • However, our net out-of-pocket cost for trash
    truck plowing 10/hour i.e. OT only
  • Capital cost 26,000 retrofit i.e. for
    frame/bumper extension, hitch/plow and hydraulic
    hookups.
  • For 10 trucks 260,000 /-.

23
Other Advantages
  • Can deploy trash-truck plows immediately versus
    waiting for contractors to trickle in.
  • Immediate deployment means plowing fresher snow
    before residential traffic creates packed
    snow/ice, ruts, etc.
  • Trash trucks can plow faster than road graders.
  • Residential streets can be
    plowed concurrently with our
    arterials and collectors.

24
Still More Advantages
  • The faster the entire street network is opened
    up, the faster our community returns to normal
  • Employees can get to work
  • Students can get to school
  • Buses can run
  • Shoppers can get to the stores
  • Sales taxes get rung up
  • Fewer frustrations and frazzled nerves.

25
Bottom Line?
  • Big snowstorms are fairly common community
    emergencies in the Snow Belt Region, and we need
    to be better prepared.
  • Being prepared means utilizing all of our
    existing resources.
  • The community will receive better, faster, and
    cheaper service.
  • Buying plows for existing trucks is a reasonable
    expense, given the high cost and risk that snow
    emergencies present.

26
Questions? Comments?
  • Mick Mercer
  • Streets and Solid Waste Manager
  • City of Loveland, CO
  • 970.962.2530
  • mercem_at_ci.loveland.co.us.
Write a Comment
User Comments (0)
About PowerShow.com