Title: Hall C Research Program
1Hall C Research Program
- Have been running experiments since November 1995
- 613 PAC Days run, or 29.7 experiments (? 61 PAC
days/year) - 263 (77) PAC Days in queue, or 12.6 experiments
- (almost all large-scale
installation experiments) - (Backlog 4.1 Years, assuming 70 PAC
days/year) - 79 Ph.D. Subjects, 51 Ph.D.s awarded
- 38 refereed publications to date (20 PRL), 5
submitted - (not including
NIM papers) - 8 Large Installations to date t20, GEn-98,
HNSS, -
GEn-00, GEn-01, G0 (x2), HKS - 400 users representing 20 different countries
- No collaboration, but steering committee (Beise,
Hashimoto, Opper, Van Oers) to represent user
community involved in diverse Hall C program
dominated by large-installation experiments.
2Experiments completed in Hall C since 2004
DAYS
47
25
10
7
14
4.33
1.67
19
7
- HMS SOS running until mid-January, 2005
- In January, 2005 installation of the HKS
experiment started - In October, 2005 installation of the
G0-Backward experiment started
S 135 70/year
3Hall C Approved Experiment Summary
Base Equipment Experiments (1.6 experiments, 16
days) E04-001 Measurements of F2 and R on
Nuclear Targets 5 days, 1/3
complete E05-017 Measurement of Two-Photon
Exchange in 13 days Unpolarized Elastic e-p
Scattering
Large Installation Experiments beyond HKS (11
experiments, 274 days) E04-115 G0 Backward Angle
Measurements 70 days A E04-101 Measurement
of the PV Asymmetry for the N-D 0
days B E05-108 G0 Backward Angle Measurements
(II) (50) days A- E04-108 Measurement of
GEp/GMp to Q2 9 GeV2 40 days A E04-019 Measu
rement of the Two-Photon Exchange Contribution
18 days A- in e-p Elastic Scattering Using
Recoil Polar. E03-109 Spin Asymmetries on the
Nucleon Experiment 27 days A- E04-113 Semi-Inc
lusive Spin Asymmetries on the Nucleon 25
days A- E05-101 Helicity Correlations in
Wide-Angle Compton Scattering 14
days A- E05-008 The Qweak Experiment A Search
for Physics at the TeV 35 days A Scale via a
Meas. of the Protons Weak Charge E04-110 The
Neutron Electric Form Factor at Q2 4.3 GeV2
from 25 days A- the D(e,en) Reaction via
Recoil Polarimetry E05-115 Spectroscopic
Investigation of Hypernuclei in (II) 20
days A-
4- Realistic Assumption on Hall C experiments,
including - a) hidden backlog
- b) installation times
- Typical Hall C year 70 PAC days 4-month long
installation - G0 Backward at 687 MeV ( N-D) 70 PAC days 5
months 2006 - G0 Backward at 362 MeV (50 PAC days)
- GEp-III 40 PAC days 4 months 2007
- GEp-2gamma 18 PAC days
- SANE Experiment 27 PAC days 3 months
2008? - Semi-SANE Experiment 25 PAC days
- Wide-Angle Compton Scattering 25 PAC days
- HMS L/T (A gt 2) 3 PAC days
- e-p Linearity Test 13 PAC days
- Qweak Phase I 35 PAC days 6 months ?
- HKS-HES Experiment 20 PAC days 4 months
? - GEn at Q2 4.3 25 PAC days 3 months
- HMS L/T (A 2) 9 PAC days
- HKS-HES Experiment II 30 PAC days
5- Present experimental program of Hall C
- Only 1.6 non-large installation experiments left
(16 days) - (cost left to finalize)
- G0 Backward Angle Large Installation 0.1M
- (estimate by Allison Lung collaboration, DOE
contribution only) - GEp-III Two-Photon Exchange Large
Installation 0.5M - (includes FPP cost, scattering chamber, and
0.2M cost for large installations) - Spin Asymmetries of the Nucleon
- Semi-Inclusive Spin Asymmetries of the Nucleon
WACS - Large Installation 0.3M
- (collaborations use grant funds for detectors)
- Qweak Large Installation 1.0M
- (does not include NSF/NSERC funding)
- GEn Experiment at Q2 4.3 Large
Installation 0.3M - (collaboration intends to scrounge purchase
some detectors) - HKS/HES Experiment Large Installation 0.5M
- (needs also new power supply, Japanese have
secured 3M for HES) - Additional (ongoing) work to improve reliability
of HMS magnets and cryotargets, LCW system,
Moller/detector upgrades 0.6M - Compton Polarimeter 9.5KA Power Supply 1.2M
6- Summary (as shown at SANE meeting of September,
2005) - Reduction of technical crew by almost two has
caught up with large installations - HKS installation barely in time ? no quality
checkout before start HKS. - Cant do professional job of preparing well for
next experiments, e.g. G0. - Direct impact (far) longer installation times,
and delay of 2005/2006 - schedule by about 3 months.
- Hall C physics program is now essentially only
large-installation experiments. - Worry about capital funds and beam time needed
to finalize large installations - in reasonable time frame.
- Can only finalize experimental program in
reasonable time scale if - 1) Sufficient Capital funds to keep large
installations moving. ? - 2) Sufficient technical manpower to prepare
installations well, saving - largely on actual installation times. ?
- 3) Schedule large-installation experiments as
large blocks of time. - 4) Need to run at least 70 PAC days per year. ?
- SANE specific will purchase new scattering
chamber early in FY06, construction - of polarized target raster systems ongoing,
anticipated scheduling date 2008? - SANE experiment essential to fulfill DOE
Performance Measure milestone by 2011.
7Very Old Long-Term Experiment
Schedule(assuming continuation of FY05 budgets
early 2005 version)
2005
- Hypernuclear Physics
- HKS Experiment (Hashimoto, Nakamura, Reinhold,
Tang) (1.8-2.0 GeV) - Hypernuclear Life Time Experiment (Hu, Margaryan,
Tang) - Transition to E04-115 Experiment (Beck, G0
Backward) - G0 Backward Run (0.8 GeV)
- Transition to E04-108 Experiment (September, 2005
) - GEp-III Run (Perdrisat, Brash, Jones, Punjabi)
- 2-g Exchange Run intermixed?
- HMS/SOS L/T Runs? (Bodek, Christy, Keppel)
- Polarized Target Runs
- SANE (g2 at high Q2) Run (Rondon, Meziani, Choi)
- Semi-SANE (flavor decompositions) Run (Jiang,
Bosted, Day, Jones) - Qweak (Bowman, Carlini, Finn, Kowalski, Page)
Phase I - GEn Run (Madey, Anderson, Kowalski, Semenov)
- Qweak (Bowman, Carlini, Finn, Kowalski, Page)
Phase II?
2006
2007
2008
2009
2012? Start 12-GeV Program?
8Old Long-Term Experiment Schedule(taking into
account a 3-month delay in the HKS/G0 schedules,
this is the version pre-PAC-28)
2005
- Hypernuclear Physics
- HKS Experiment (Hashimoto, Nakamura, Reinhold,
Tang) - Hypernuclear Life Time Experiment (Hu, Margaryan,
Tang) - Transition to E04-115 Experiment (Beck, G0
Backward) - G0 Backward Run (0.8 GeV 0.4 GeV)
- Transition to E04-108 Experiment (January, 2006
) - GEp-III Run (Perdrisat, Brash, Jones, Punjabi)
- 2-g Exchange Run intermixed?
- HMS L/T Runs? (Arrington, Bodek, Keppel)
- Polarized Target Runs
- SANE (g2 at high Q2) Run (Rondon, Meziani, Choi)
- Semi-SANE (flavor decomposition) Run (Jiang,
Bosted, Day, Jones) - Helicity in WACS Run? (Day, Wojtsekhowski)
- Qweak (Bowman, Carlini, Finn, Kowalski, Page)
Phase I - GEn Run (Madey, Anderson, Kelly, Kowalski,
Semenov)? - Qweak (Bowman, Carlini, Finn, Kowalski, Page)
Phase II? - HKS(II) Run?
-
- Start 12 GeV program?
2006
2007
2008
2009
2010
2012?
9- Hall C FY06 Budget 10/05 (Revised 12/05)
- Operations budget FY04 we used 1,270K
- FY05 we had 1,190K, used it, but had an
- error of the bank ? 100K left
- FY06 expected 1,090K ( 100K carry-over)
- Capital budget 140K carry-over (screw-up in
procurement) - Capital budget 120K G0 Backward
- 536K Qweak (magnet stand, collimators,
target) - 620K 200K needed for GEp-III
- (new scattering chamber, GHS, etc)
- 50K typical for target group work
- 100K for SANE/semi-SANE/WACS
- (long-lead scattering chamber, etc)
- 175K for ½ of 9.5 kA power supply
- 20K for HKS/HES work
- 25K for HMS new controls
- 250K to start Compton work MIT/Bates
- ? of order 200K short on capital
10Upcoming Program in Hall C
Schedule has shifted again due to forced Summer
down
11Spin Asymmetries on the Nucleon Status
Now encompasses two experiments E03-109 SANE
(Rondon, Choi, Meziani) g1 g2
at Q2 4 GeV2 E04-113 Semi-SANE (Bosted, Day,
Jiang, Jones) Semi-Inclusive Spin Asymm.
- Designed to be insensitive to backgrounds and
have good Particle Id. Target field screens much
of low-energy background. - Gas Cherenkov (Temple)
- Particle identifications (e/p)
- Minimal knock-on
- Prototype tested in Hall C
- Design Construction Now
- Lucite Cherenkov (Norfolk State)
- Redundant P.Id. coarse tracking
- Quartz detector as a Hodoscope
- before gas Cherenkov under
- consideration for e/e- separation
- Pb-Glass Calorimeter from GEp-III
- Add gain monitoring system (UVa)
Scattering Chamber under design, long-lead item
in FY06 Uniform polarized target raster RD
completed, construction done