Refurbishment of the tritium laboratories at SCKCEN - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Refurbishment of the tritium laboratories at SCKCEN

Description:

Infrastructure room 2: process cell, fume hoods, furniture. Not to be reused ... Process cells / glovebox / fume hoods. Ventilation / pulsation ... – PowerPoint PPT presentation

Number of Views:88
Avg rating:3.0/5.0
Slides: 16
Provided by: kdy5
Category:

less

Transcript and Presenter's Notes

Title: Refurbishment of the tritium laboratories at SCKCEN


1
Refurbishment of the tritium laboratories at
SCKCEN
  • Johan Braet, Kris Dylst, Sven Vanderbiesen

8th International Conference on Tritium Science
and Technology September 16-21, 2007 Rochester,
New York
2
Agenda
Introduction
Strategy
DD Figures
Economics
Conclusions
  • Introduction
  • Strategy
  • Dismantling and decontamination figures
  • Economics
  • Conclusions

3
The SCK Tritium laboratory is in use for more
than 30 years
Introduction
Strategy
DD Figures
Economics
Conclusions
  • The tritium laboratories at SCKCEN were
    commissioned in 1975 for a maximum tritium
    inventory of 37 TBq tritium.
  • A number of major tritium projects have been
    executed
  • Detritiation of atmospheres 0.5 TBq
  • Detritiation of water (CECE) 2.0 TBq
  • Detritiation of solvents 18.0 TBq
  • Various detritiation projects 2.5 TBq
  • LPCE catalyst testing
  • Detritiation of steel
  • Detritiation of concrete
  • 22.5 TBq

4
The new layout provides more and better work
areas
Introduction
Strategy
DD Figures
Economics
Conclusions
New layout
Old layout
  • 100 m² controlled area
  • 3 process cells 19 m²
  • 2 gloveboxes
  • 3 Fume Hoods
  • Extraction rate 10,758 m³/h
  • Max. Tritium inventory of 37 TBq
  • 100 m² controlled area
  • 1 process cell 15 m²
  • 6 gloveboxes (ETHEL)
  • 5 1 Fume hoods
  • Extraction rate 15,350 m³/h
  • Max. Tritium inventory of 370 TBq

5
Refurbishment plan
Introduction
Strategy
DD Figures
Economics
Conclusions
  • Continue working in room 1 decommission room 2
  • Reinstall room 2
  • Commission room 2
  • Decommission room 1 start working in room 2
  • Reinstall room 1
  • Commission room 1

? Busy ? ? ? ?
6
Decommissioning requires a strategy for disposal
or free release
Introduction
Strategy
DD Figures
Economics
Conclusions
  • Room 2 needed to be cleared for decommissioning.
  • Equipment in room 2 meters, pumps,
  • To be reused
  • Move to working lab
  • Move to warehouse
  • Infrastructure room 2 process cell, fume hoods,
    furniture
  • Not to be reused
  • Several tons of material need to be disposed/
    free released
  • A disposal / free release strategy is necessary

7
The free release limit is a key factorin the
disposal / free release strategy
Introduction
Strategy
DD Figures
Economics
Conclusions
Decontaminate
Yes
BelowFRL?
Further decont.?
Clean up
Dispose as nuclear waste
No
No
Yes
Recycle
Free release
Dispose as nonnuclear waste
8
Tritium limits
Introduction
Strategy
DD Figures
Economics
Conclusions
Contamination ? Activation
  • Belgian law 100 Bq/g

Destructive measurement
Total surface contamination limits Bq/dm²
Removable surface contamination limits Bq/dm²
200 000 000 CEA 1 000 000 European
Commission 16 667U.S. Department of
Energy 2 500
SCKCEN
2 000 000CEA 250 SCKCEN
167 U.S. Department of Energy
4Interpretation of IAEA transport norm for ß,?
emitters
Indirect measurement
Direct measurement
9
The infrastructure was decommissioned in 3 main
phases
Introduction
Strategy
DD Figures
Economics
Conclusions
  • Probably not contaminated equipment 1.2 t
  • Furniture
  • Possibly contaminated equipment 5.3 t
  • Process cells / glovebox / fume hoods
  • Ventilation / pulsation
  • Covering of floor, wall and ceiling 10.6 m³

0.3 t
0.3 t
0.9 t
0.6 m³
10 m³
0.9 t
4.1 t
10
Decontamination generates secondary radioactive
waste
Introduction
Strategy
DD Figures
Economics
Conclusions
ProbablyContaminated
Prob. notContaminated
Floor, Walland ceiling
  • Free released
  • Nuclear metal recycling
  • Disposed radioactive waste
  • Secondary radioactive waste
  • Compressible waste
  • Scintillation liquid
  • Air filters

0.9 t 0.3 t 7 kg 10 L
4.1 t 0.3 t 0.9 t 131 kg 20 L 48 kg
10 m³ 0.6 m³ 6 kg 3 L
11
Safety measures prevented personnel to receive
measurable tritium dose
Introduction
Strategy
DD Figures
Economics
Conclusions
  • Safety measures during project
  • PPE
  • PEDI suits
  • Gloves, dust masks, overalls
  • Infrastructural
  • Ventilation
  • Airborne tritium monitoring
  • Dosimetry
  • Regular analyses of urine samples
  • The tritium concentration in all urine samples
    were below the detection limit to calculate the
    received dose.

12
The low release limit made decontamination labour
intensive
Introduction
Strategy
DD Figures
Economics
Conclusions
  • Example Process cells
  • 2.8 Tons of painted metal
  • Underlying paint layers can contain up to 47000
    Bq/dm² (fixed)
  • Decontamination method
  • Scouring off paint from floor and walls in cell
  • Scouring off thin metal layer
  • Washing cell
  • 31 of the total manhours have been spent on the
    decontamination of the process cells.
  • Could disposing of metals to a nuclear melting
    facility a valid alternative?

13
Cost balanceFree release Nuclear melting
facility
Introduction
Strategy
DD Figures
Economics
Conclusions
Free Release
Nuclear meltingFacility
  • Entry
  • Manhours
  • Equipment
  • Radioactive waste
  • Nuclear melting facility
  • Total

EUR 213 000 13 000 64 000 2 000 292 000
EUR 146 000 13 000 48 000 21 000 228 000
  • Disposing metals to a nuclear melting facility
    could have saved 22 of the costs.
  • Free release socially more acceptable?

14
Conclusions
Introduction
Strategy
DD Figures
Economics
Conclusions
  • One room has been decommissioned and
    reinstallation activities are taken place.
  • For free release purposes tritium was classified
    as regular ß,? emitter which leads to too
    restrictive free release limits and a very labour
    intensive decontamination process.
  • Decontamination also generates secondary nuclear
    waste.
  • Most of the materials have been denuclearised
    without personnel receiving measurable tritium
    dose.
  • Disposing metals to a nuclear melting facility
    would have saved 22 of the costs, but free
    release might be socially more accepted

15
Tritium 2007
refurb
tritium
Thank you for your attention
lab
Write a Comment
User Comments (0)
About PowerShow.com