Title: Guidelines for Costing for discussion
1Guidelines for Costing(for discussion)
Definitions for alignment with MECO project
costing
- Design costs (not in GA study)
- Pertain to costs related to design and analysis
of the delivered items - Examples are conductor design, field solution,
quench analysis, structural analysis, and
creating all drawings of the delivered items. - Manufacturing costs ( GA study)
- Pertain to all manufacturing and manufacturing
support costs through final leak-checking and
shipping the cryostats. - These costs include
- Tooling design, tooling drawings and tooling
fabrication. - Writing manufacturing and QA procedures for each
work station - Work performed at each work station, whether by
trade labor, engineering or management. - Installation and commissioning costs (not in GA
study) - Pertain to all work in the BNL experimental hall
2MECO Magnet System WBS
Top Level
1.4.1 Final design 1.4.2 PS fabrication 1.4.3 TSu
fabrication 1.4.4 TSd fabrication 1.4.5 DS
fabrication 1.4.6 Cryogenic equipment 1.4.7 Vacuum
equipment 1.4.8 Power supplies and protection
equipment 1.4.9 Installation
3PS WBS
- 1.4.2.1 Conductor
- 1.4.2.2 Cold structure (Al outer mandrels)
- 1.4.2.3 Winding tooling
- 1.4.2.4 Winding and VPI
- 1.4.2.5 Coil assembly
- 1.4.2.6 He can
- 1.4.2.7 LN2 Shield MLI
- 1.4.2.8 Support rods
- 1.4.2.9 Vacuum shell and gravity supports
- 1.4.2.10 Vapor cooled leads
- 1.4.2.11 Misc. instrumentation cryo lines
- 1.4.2.12 Shipping
4TSu WBS
1.4.3.1 Conductor 1.4.3.2 Cold structure (cold
mandrels) 1.4.3.3 Winding tooling 1.4.3.4 Winding
and VPI 1.4.3.5 Coil assembly 1.4.3.6 LN2 Shield
MLI 1.4.3.7 Support rods 1.4.3.8 Vacuum shell
and gravity supports 1.4.3.9 Vapor cooled
leads 1.4.3.10 Misc. instrumentation cryo
lines 1.4.3.11 Shipping
5TSd WBS
1.4.4.1 Conductor 1.4.4.2 Cold structure (cold
mandrels) 1.4.4.3 Winding tooling 1.4.4.4 Winding
and VPI 1.4.4.5 Coil assembly 1.4.4.6 LN2 Shield
MLI 1.4.4.7 Support rods 1.4.4.8 Vacuum shell
and gravity supports 1.4.4.9 Vapor cooled
leads 1.4.4.10 Misc. instrumentation cryo
lines 1.4.4.11 Shipping
6DS WBS
1.4.5.1 Conductor 1.4.5.2 Cold structure (cold
mandrels) 1.4.5.3 Winding tooling 1.4.5.4 Winding
and VPI 1.4.5.5 Coil assembly 1.4.5.6 LN2 Shield
MLI 1.4.5.7 Support rods 1.4.5.8 Vacuum shell
and gravity supports 1.4.5.9 Vapor cooled
leads 1.4.5.10 Misc. instrumentation cryo
lines 1.4.5.11 Shipping