Title: Systems Engineering During the Formulation Phase
1Systems Engineering During the Formulation Phase
January 24, 2005
References SMAD text. Chapters 1-4 JPL
Project Manager Roles/Responsibilities Training
2System Engineering
- Responsibility Direct, coordinate, and monitor
the system design and product development
activities to ensure that the Projects intended
technical content is delivered. - Understand and communicate the big picture
- Balance risk across science objectives, technical
implementation, cost and schedule
3Project Life Cycle
APPROVAL
NASAPhases
IMPLEMENTATION
FORMULATION
JPL Life CyclePhases
Pre-Phase AAdvanced Studies
Phase AMission Systems Definition
Phase BPreliminary Design
Phase CDesign Build
Phase DATLO
Phase EOperations
Major Project Reviews
Project PDR
Project CDR
Assembly, Test Launch Operation Readiness
Review ARR
Critical Events Readiness Review CERR
Concept Review
Operations Mission Readiness Reviews ORR
MRR
Post Launch Assmnt Review PLAR
STEP 1 TMC
STEP 2 TMC
PMSR
Major NASA Enterprise Reviews
Confirmation Review CR
Mission Briefing
Concept/ Proposal Review
Initial Confirmation Review ICR
Major Events
Contract
Commitment, Select for STEP 2
Launch
Down Select for STEP 1
Notes
4Major Systems Engineering Responsibilities During
Project Formulation
- Requirements development and flowdown
- Architecture options
- Identifies key trade studies
- Defines functions within and boundaries between
systems - Perform trade studies for crosscutting issues
- Risk Management
- Margins
5System Engineers Objective Achieving Balanced
Risk
Margins
Threats
Risk
Power-30
Mass-30
CPU-MS gt2
S/W Loc/ Language
Funding profile
Linked funding
Structure-MS gt2
Battery-40
RDM gt2
Instrument Xface Complex.
Schedule (i.e. Launch Date)
Mission Complexity
Schedule 1 mo./yr.
Testbeds 2
Dollars-25
Data return and quality
Success criteria
Pointing Accuracy
1,000 Operating Hours
Elec. Parts Derating
Delta -V-30
New Technologies
Number of instruments
Partner Cont. Capability
Deployables- MS gt2
JPL Workforce Availability
Thermal 25?
Program Requirements
Physical Environments
Inheritance H/W-S/W
Launch Vehicle Performance
Dynamics MS gt 6 db ENV.
Memory 200
Review Process
Systems Engineering
Fault Tree Analysis Safety Mission Assurance
Failure Mode Effect Analysis Configuration
Management
6Requirements Development Is Key
- Requirements flowdown from the mission objective
into a hierarchy that defines the Projects
technical scope - What must be done (Functions)
- How well it must be done (Performance)
- Requirements bound scope
- A hierarchy of traceable requirements ensures
that the Project develops only what is required,
i.e., no frivolous activities - A hierarchy of negotiated requirements ensures a
balanced system design - Requirements are the basis for the Projects
verification and validation efforts - Poorly written, unverifiable requirements are
trouble
7Requirements Hierarchy and Flowdown
8- Numbered ARES Science Objectives are described
in Section D.1.2 - ARES Instrumentation MS mass spectrometer,
MAG magnetometer CC context camera, PS
point spectrometer, ADS air data system
Figure D.2-1 ARES Science, Measurements, and
Platform Selection Flow Directly from MEPAG and
COMPLEX
9ARES Example Airplane Design Derived Directly
From Science Objectives
- AFS flight altitude driven by science objectives
1, 2, 4 and 5 - AFS baseline science range requirement driven by
science objectives 2, 4, 5 and 6 - Derived AFS propulsion and configuration
requirements
10ARES Example Payload Requirements Are
Accommodated by Airplane
11Architecture Options
- Systems engineering personnel are responsible
for major trades and architecture decision across
the Project system - Trades are performed in such a manner so as to
keep the project system design in balance - Ensure that all systems share comparable levels
of risk - Ensure that all systems are designed to the same
standards and levels of expectation for
performance
12Design Decisions
- Make architecture decisions early
- On a fixed schedule, it is important to keep the
design process moving - Enabled by early definition of requirements and
performance of rapid system analyses - Design decisions must balance science objectives,
technical risk, cost and schedule constraints
13Probability of Mission Success
- For a generic Mars mission,
- Pms PlaunchPTMIPcruisePMOIPEDLPSciencePDataretur
n - A selectable concept is likely to have strong
science, low mission risk, and satisfy the cost
and schedule constraints - Pms will drive architecture selections towards
focused science, simplicity, redundancy,
reliability, operational flexibility, large
margins and minimal use of new technology
14ARES Example Key Mission Architecture Trades
High-level architecture options to analyze in
determining Baseline Science Mission
15Keep A Record of Your Major Trades Document
Performance Improvement and/or Risk Mitigation
16Baseline Science Mission Performance Floor
- Baseline Science Mission BSM refers to that
investigation that, if fully implemented, will
accomplish the entire set of proposed scientific
objectives. - Performance Floor Minimum science return below
which the investigation is not considered
justified for the proposed cost. Failure to
maintain a level of science return at or above
the Performance Floor as determined by NASA may
be cause for termination of the investigation. - Descope Options The difference(s) between the
Baseline Mission and the Performance Floor will
be assessed to determine the investigation's
resiliency
17ARES Example Descope Options
18Performance Floor Mission Reduces Complexity,
Increases Margins
19Risk Management
- Risk Combination of the likelihood of occurrence
and the severity of the consequences of an event - Aspects of risk
- Likelihood
- Consequence
- Uncertainty in assessment
- Risk management An organized means of managing
risk by assuring that uncommitted resources are
sufficient to enable mission success
20Risk Management
21Risk Rating Matrix
22ARES Example
23(No Transcript)
24Margins and Margin Management
- Projects maintain margins in order to provide
resiliency during planning and implementation - Projects define, track, and actively manage
margins throughout the life cycle of the project - Generally, projects compute and track margins for
schedule, cost, mass, power, computer throughput,
memory, telecom and any other parameter or
resource that is critical to mission success
25Definitions
- Current Best Estimate (CBE) Cognizant engineers
best estimate of the system value - Growth Maximum expected value based on technical
maturity of the system - Allocation Maximum allowable value of the system
based on some physical limit - Contingency Difference between Growth and CBE
- Generally under system managers control
- Margin Difference between Allocation and Growth
- Generally under project managers control
26Contingency as a Function of Technical Maturity
- During formulation,
- New designs shall use a 30 or larger contingency
depending on the nature, maturity, amount of new
technology/ concepts, and complexity of the
design - Inherited designs shall use a 15 or larger
contingency - Inherited hardware shall use 10 or larger
contingency - Inherited hardware shall use 2 contingency if
hardware is totally known to be without change,
and is build-to-print. Any change to these
conditions should be evaluated and a larger
growth percentage applied.
27Technical Margin Calculations
Contingency Max Expected Resource Value CBE
Resource Value Contingency
__________Contingency_________________ X 100
CBE Resource Value Margin Max Possible
Resource Value Max Expected Resource Value
Margin __________ Margin_________ X 100
Max Expected Resource Value
28Budget Reserves
Definitions Budget Reserve Unencumbered
Budget Reserve/Estimated Cost to Go x 100 Total
Budget Estimated Cost to Go Unencumbered
Budget Reserve Notes 1. Cost to Go includes the
funded schedule margin, but excludes the launch
vehicle costs
29Technical Margins
30Schedule Margin
Definitions Total Schedule Planned Activities
Schedule Margin Schedule Margin No Planned
Activities, but Funded Schedule Schedule Margin
Rate Schedule Margin/(Planned Activity
Schedule Margin)
31ARES Example
- Project will exercise descope options as
necessary to maintain the above resource profile
32Example for Last Years Competition EGReSS
33Europa Science Objectives
- Characterize surface and near surface ice
composition - Confirm and redefine possible Europan subsurface
ocean - Provide geological visualization of samples and
the landing site - Investigate Europan surface mineral composition
- Characterize Europan life sustaining ability and
the probability of life
34Baseline Mission
35Mission ImplementationArchitecture Trades
36Descope Options
- Descope options will enhance mass, power, cost
and schedule reserves - Decisions must be made prior to PDR (End of Phase
B)
37Risk Mitigation
38EGReSS Reserves
- Large reserves ensure a highly conservative
program - Program margins reduce mission system risk
39EGRESS Spending (M FY16)
40Cost and Reserve Breakdown
All Figures M FY16