Power Supply Adequacy Forum Roundtable Discussion on IRP - PowerPoint PPT Presentation

1 / 6
About This Presentation
Title:

Power Supply Adequacy Forum Roundtable Discussion on IRP

Description:

Power Supply Adequacy Forum Roundtable Discussion on IRP – PowerPoint PPT presentation

Number of Views:32
Avg rating:3.0/5.0
Slides: 7
Provided by: melis77
Category:

less

Transcript and Presenter's Notes

Title: Power Supply Adequacy Forum Roundtable Discussion on IRP


1
Power Supply Adequacy ForumRoundtable Discussion
on IRP
  • Overview
  • History of IRP
  • PacifiCorps Position
  • Key IRP Assumptions
  • Reviewing Assumptions
  • Studies Issues
  • May 2003

2
History of PacifiCorps IRP
Dec. 01 to Feb. 02
Mar. 02 to May 02
Jun. 02 to Aug. 02
Sep. 02 to Jan. 03
  • History of IRP
  • Used Henwood models (ProSym and MarketSym) to
    perform analysis
  • Risk was introduced as an important factor in
    this IRP process
  • Required to file an IRP every two years
  • Ten Public Input Meetings were held between
    December 2001 and February 2003
  • Eleven Public Technical Workshops were held with
    participants
  • The IRP was filed in all states on January 24,
    2003
  • Began public input meetings
  • Selected IRP model
  • Gathered and input model data and assumptions
  • Held technical workshops
  • Finalized risk model
  • Ran portfolios through models
  • Processed data and produced preliminary results
  • Refined portfolios based on findings, ran new
    portfolios
  • Produced final set of IRP Results
  • Developed Action Plan
  • Prepared IRP Draft Report
  • Communicated IRP findings and issued Draft Report
  • Modified Draft Report based on public input
  • Filed IRP with all State Public Service
    Commissions
  • Evaluated risk models
  • Consolidated models and verified preliminary
    results
  • Updated inputs and assumptions
  • Selected initial new resources for portfolios
  • Completed initial model runs

3
Analysis of Current Position
  • PacifiCorps current position reveals a
    substantial need for new resources
  • Anticipate need of about 4,000 additional
    megawatts of capacity over the next 10 years
  • The 15 Planning Margin accounted for 1,700 MW
    of the 4,000 MW in the least-cost, low risk
    portfolio
  • Results of Analysis
  • Both deterministic and stochastic analysis were
    performed on top portfolios
  • Thirteen stress tests were also performed on top
    portfolios
  • Least-Cost Portfolio included
  • 1,400 MW Renewables
  • 1,200 MW Peakers
  • 2,100 MW Base Load
  • 450 MWa DSM
  • 700 MW Shaped Products

4
IRP Planning Margin Assumption
  • Base Case Assumptions
  • Average hydro
  • Average loads
  • No Capacity credit for wind
  • Market sales and purchases were limited to 500 MW
    for each control area
  • Decision Criteria used in filed IRP
  • Limit initial net short energy position to less
    than 5 of the hours in any year
  • Build portfolios to meet 15 capacity planning
    margin for the system by fiscal year 2007
  • Planning Margin Load (LT Sales - LT
    Purchases) x 0.15
  • This is mid-way between 12-18 mentioned in SMD
    discussions
  • Reserve peakers were built to cover planning
    margin
  • Issues with Decision Criteria
  • 5 criteria seemed arbitrary to third parties
  • FERC's SMD White Paper issued on April 28, 2003
    specifically said it would not require a minimum
    level of resource adequacy
  • FERC indicated that resource adequacy will be
    left up to the states and/or regions

NoteFERCs Standard Market Design - Notice of
Proposed Rulemaking
5
Review of Planning Margin Assumption
  • Planning Margin Analysis
  • Planning margin was used to provide sufficient
    resources to cover unplanned outages, provide
    operating reserves, regulatory margin, and demand
    growth uncertainty
  • PacifiCorps view is planning margin needs to
    reflect the operating requirements
  • Operating Reserves (vary by control area)
  • Obligated by WECC to carry operating reserves
    above firm load at any time plus additional as
    seemed appropriate by operators
  • One measure of operating reserves is 5 of hydro
    and 7 of thermal generation being used to serve
    load at that time
  • Generator Unplanned Outages
  • Historical and future unplanned outages between
    10 - 12
  • Appropriate amount of planning margin for each
    control area is still under review
  • PacifiCorp has transmission constraints on the
    East side of its system that may mandate a higher
    planning margin requirement
  • More flexibility on West side of PacifiCorp
    system

6
Next Steps - Studies Issues
  • Goals of IRP
  • Plan for new resources to provide reliable
    service
  • Gain key stakeholder involvement and commitment
  • Comply with PUC requirements
  • Gain PUC acknowledgement of the Action Plan
  • Foundation for future investment and long term
    business planning
  • Studies Under Review
  • Demand-elasticity in our load forecast
  • Reliability and economic risk associated with
    varying planning margin levels
  • Capacity contributions associated with wind
    plants
  • Different planning margin requirements for
    transmission constrained areas
  • Issues
  • Appropriate trade-off between risk and cost is a
    policy/regulatory issue
  • Building reserves is expensive - production cost
    models should always choose less reserves unless
    extreme assumptions are made for market prices
    penalties
Write a Comment
User Comments (0)
About PowerShow.com