Planning Iterative Software Development Projects - PowerPoint PPT Presentation

1 / 13
About This Presentation
Title:

Planning Iterative Software Development Projects

Description:

Iterative software development projects require a different approach ... Develop next iteration plan mid-way through this iteration. Resource Plan Development ... – PowerPoint PPT presentation

Number of Views:186
Avg rating:3.0/5.0
Slides: 14
Provided by: uni6157
Category:

less

Transcript and Presenter's Notes

Title: Planning Iterative Software Development Projects


1
Planning Iterative Software Development Projects
  • Raj Agrawal, PMP
  • Unisys

2
Synopsis
  • Iterative software development projects require a
    different approach to project planning as
    compared to traditional waterfall projects. This
    is especially true in areas such as estimation of
    effort, technical risk mitigation, schedule
    development, resource planning scope
    management. Experiences, lessons learned and
    best practices derived in parametric estimation,
    iterative development of schedules, requirements
    development analysis will be discussed.

3
Overview
  • Introduction
  • What is iterative development?
  • Reality Requirements Change!
  • Why iterative development?
  • Challenges of iterative development
  • Estimation
  • Estimation techniques
  • Top down or bottom-up estimation?
  • Planning
  • Project Plan development
  • Resource Plan development
  • Scope management iteration by iteration
  • Conclusion

4
What is Iterative Development?
  • Development methodology to improve software
    project delivery
  • Divides project into mini waterfall projects
    called iterations
  • Requirements per iteration are based on technical
    risk mitigation and business value
  • Iteration duration is typically 4-12 weeks
  • Iterations are timeboxed fix end date and
    remove requirements if slippage
  • Each iteration delivers a partial working system
  • Requires continuous negotiation between scope,
    solution project plan

5
Reality Requirements Change!
Source How to Fail with the Rational Unified
Process Seven Steps to Pain and Suffering,
Craig Larman, Philippe Kruchten, Kurt Bittner
6
Why Iterative Development?
  • Mitigates risk
  • Assumes requirements will change over project
    life
  • A tested partial solution enables feedback to
    align requirements and design
  • Provides early indication of project progress
  • Provides basis for early scope negotiations
    management
  • Reduces Gold-plating Requirements Creep

7
Challenges of Iterative Development
  • Cost estimation without a detailed WBS
  • Rolling Window Planning - Project Plan only
    detailed to next iteration
  • Requirements analysis during each iteration may
    lead to changes to baseline
  • Clients need to prioritize requirements
  • Architects need to identify and prioritize
    technical risks
  • Waterfall milestones such as SDR, PDR, CDR need
    to be mapped

8
Estimation Techniques
  • Top down estimation requires
  • A cost estimation tool
  • Measure of volume
  • Input for languages
  • Environment parameters
  • Bottom up estimation requires
  • A detailed WBS
  • Estimates for each lowest element of WBS

9
Top Down or Bottom Up Estimation?
  • They complement each other
  • Use top down estimation for application
    development
  • Bottom up estimation
  • Validation of top down estimate
  • Estimate each iteration and discipline within
    iteration
  • Add other items such as business modeling
    system integration

10
Project Plan Development
  • Create high level plan based on estimate
  • Phase dates
  • Iteration plan
  • Iteration dates
  • Key milestones
  • Detail the first phase first iteration
  • Develop next iteration plan mid-way through this
    iteration

11
Resource Plan Development
  • Use hours estimate from the cost model
  • Use hours by roles from cost model
  • Spread hours over the timeline
  • Assign staff to roles

12
Scope Management Iteration by Iteration
  • Each iteration is time-boxed
  • Requirements dropped from an iteration move into
    next iteration
  • Only if requirements are prioritized
  • Architecture is defined
  • Technical risks are prioritized
  • Close stakeholder involvement is needed for scope
    management

13
Conclusion
  • Iterative development requires a different
    mindset do the hard work first
  • Stakeholders need to involved closely
  • Estimation tools aid planning
  • Requirements should be prioritized
  • Architecture centric design
  • Iteration plan should mitigate risks
  • Leads to adaptive development
Write a Comment
User Comments (0)
About PowerShow.com